11/30/2020 1:07:14 AM
|
Project Closed
|
11/30/2020 1:07:14 AM
|
Project Approved: 11/30/2020
|
11/30/2020 1:06:17 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/23/2020 8:52:57 AM
|
Request for Review Comments sent for Project Freedom Springs for review by Lindsay Darden on behalf of PCD Project Manager
|
11/20/2020 11:21:38 AM
|
Fees paid: 11/20/2020 (Receipt: 1003579)
|
11/20/2020 11:09:32 AM
|
Payment Request sent: 11/20/2020
|
11/20/2020 11:08:54 AM
|
Payment Request canceled: 11/20/2020
|
9/21/2020 5:10:22 PM
|
Payment Request sent: 9/21/2020
|
9/21/2020 5:10:21 PM
|
File # Assigned: COM2054
|
9/21/2020 5:10:16 PM
|
Submission Triaged
|
9/21/2020 1:29:54 PM
|
Submission received from Applicant
|
9/21/2020 7:47:12 AM
|
Submission request sent to Applicant
|
9/16/2020 11:07:54 AM
|
Submission request sent to Applicant
|
9/16/2020 11:05:12 AM
|
Project Manager Assigned: Lindsay Darden
|
9/16/2020 11:05:12 AM
|
EA Assigned: EA-17-225
|
9/16/2020 11:05:12 AM
|
Project Created
|