3/23/2021 9:04:10 AM
|
Project Closed
|
3/23/2021 9:04:10 AM
|
Project Approved: 3/23/2021
|
3/23/2021 9:03:45 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/12/2021 10:43:22 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Ryan Howser on behalf of PCD Project Manager
|
3/12/2021 10:42:14 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/23/2021 11:05:46 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Ryan Howser on behalf of PCD Project Manager
|
2/23/2021 11:04:20 AM
|
Submission Triaged
|
2/23/2021 8:18:57 AM
|
Submission received from Applicant
|
2/17/2021 1:41:38 PM
|
Submission request sent to Applicant
|
2/17/2021 1:41:23 PM
|
Submission Triaged
|
2/15/2021 4:23:02 PM
|
Submission received from Applicant
|
2/9/2021 10:01:50 AM
|
Submission request sent to Applicant
|
2/9/2021 10:01:09 AM
|
Submission Triaged
|
2/8/2021 12:43:56 PM
|
Submission received from Applicant
|
12/7/2020 11:28:32 AM
|
Project Manager Assigned: Ryan Howser
|
10/30/2020 11:28:48 AM
|
Submission request sent to Applicant
|
10/30/2020 11:28:13 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/29/2020 4:22:07 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/27/2020 1:24:52 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/26/2020 8:19:33 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/21/2020 1:56:45 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
10/13/2020 7:12:48 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Brandon Bernard on behalf of Widefield Water & San
|
10/13/2020 7:12:46 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Dennis Neal on behalf of Widefield SD 3
|
10/13/2020 7:12:44 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
10/13/2020 7:12:41 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Roy Heald on behalf of Security Water & Sanitation District
|
10/13/2020 7:12:39 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist
|
10/13/2020 7:12:37 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Heather on behalf of City of Fountain Electric
|
10/13/2020 7:12:35 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/13/2020 7:12:33 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by DeBerry Drew on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
10/13/2020 7:12:31 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/13/2020 7:12:25 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Catherine McGarvy on behalf of EPC Health Department
|
10/13/2020 7:12:16 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Rad Dickson on behalf of PCD Project Manager
|
10/13/2020 7:12:14 AM
|
Request for Review Comments email sent for Project Vehicle Repair, 4250 Hancock for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/30/2020 7:56:01 AM
|
Fees paid: 9/30/2020 (Receipt: 1003318)
|
9/23/2020 3:20:03 PM
|
Project Manager Assigned: Rad Dickson
|
9/23/2020 3:19:50 PM
|
Project Manager Assigned: Lindsay Darden
|
9/23/2020 3:19:19 PM
|
Payment Request sent: 9/23/2020
|
9/23/2020 3:19:18 PM
|
File # Assigned: PPR2032
|
9/23/2020 3:19:10 PM
|
Submission Triaged
|
9/22/2020 8:00:14 PM
|
Submission received from Applicant
|
9/21/2020 5:31:34 PM
|
Submission request sent to Applicant
|
9/17/2020 5:40:28 AM
|
Submission request sent to Applicant
|
9/17/2020 5:40:21 AM
|
Submission Triaged
|
9/16/2020 10:43:09 AM
|
Submission received from Applicant
|
9/8/2020 9:49:36 AM
|
Submission request sent to Applicant
|
9/8/2020 9:32:34 AM
|
Submission Triaged
|
9/8/2020 9:02:26 AM
|
Submission received from Applicant
|
8/13/2020 7:17:07 PM
|
Submission request sent to Applicant
|
8/13/2020 7:15:50 PM
|
Project Manager Assigned: Nina Ruiz
|
8/13/2020 7:15:50 PM
|
Project Created
|