11/20/2020 3:51:09 PM
|
Project Closed
|
11/20/2020 3:51:09 PM
|
Project Approved: 11/20/2020
|
11/15/2020 9:02:21 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
11/13/2020 4:17:29 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/5/2020 2:53:40 PM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Lindsay Darden on behalf of PCD Project Manager
|
11/5/2020 12:25:03 PM
|
Submission Triaged
|
11/4/2020 3:49:50 PM
|
Submission received from Applicant
|
11/3/2020 9:55:54 AM
|
Submission request sent to Applicant
|
10/23/2020 4:51:06 PM
|
Submission request sent to Applicant
|
10/23/2020 1:37:47 PM
|
Request for Review Comments returned by EPC Health Department
|
10/21/2020 4:30:27 PM
|
Submission request sent to Applicant
|
10/20/2020 11:52:50 AM
|
Request for Review Comments returned by PCD Engineering Division
|
10/20/2020 10:27:15 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/19/2020 4:24:28 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/29/2020 10:53:17 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
9/29/2020 8:53:50 AM
|
Request for Review Comments returned by RBD Floodplain
|
9/29/2020 8:38:01 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Hart Wright on behalf of Southwestern Hwy 115 Fire Protection District
|
9/29/2020 8:37:59 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
9/29/2020 8:37:57 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
9/29/2020 8:37:55 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
9/29/2020 8:37:52 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Kevin Niles on behalf of Arkansas Groundwater Users Association
|
9/29/2020 8:37:49 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Keith Curtis on behalf of RBD Floodplain
|
9/29/2020 8:37:47 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
9/29/2020 8:37:45 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Catherine McGarvy on behalf of EPC Health Department
|
9/29/2020 8:37:36 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Lindsay Darden on behalf of PCD Project Manager
|
9/29/2020 8:37:34 AM
|
Request for Review Comments email sent for Project 14370 Aiken Ride Accessory Structure Permanent Occupancy for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/28/2020 11:42:36 AM
|
Fees paid: 9/28/2020 (Receipt: 1003302)
|
9/28/2020 5:30:50 AM
|
Project Manager Assigned: Lindsay Darden
|
9/28/2020 5:30:32 AM
|
Payment Request sent: 9/28/2020
|
9/28/2020 5:30:32 AM
|
File # Assigned: AL2020
|
9/28/2020 5:30:22 AM
|
Submission Triaged
|
9/25/2020 3:45:40 PM
|
Submission received from Applicant
|
9/23/2020 3:29:50 PM
|
Submission request sent to Applicant
|
9/23/2020 3:29:37 PM
|
Submission Triaged
|
9/23/2020 2:22:56 PM
|
Submission received from Applicant
|
7/29/2020 2:30:15 PM
|
Submission request sent to Applicant
|
7/29/2020 2:29:50 PM
|
Submission Triaged
|
7/29/2020 12:35:09 PM
|
Submission received from Applicant
|
7/9/2020 11:19:50 AM
|
Submission request sent to Applicant
|
7/9/2020 11:16:33 AM
|
Project Manager Assigned: Gabe Sevigny
|
7/9/2020 11:16:33 AM
|
Project Created
|