1/11/2022 10:26:32 AM
|
Project Closed
|
1/11/2022 10:26:32 AM
|
Project completed: 1/11/2022
|
10/5/2021 10:43:05 AM
|
Pursuing Abatement
|
9/7/2021 4:13:20 PM
|
Executive Determination Requested
|
5/19/2021 12:08:01 PM
|
Project Manager Assigned: Charles Carlisle
|
4/29/2021 6:40:21 AM
|
Pursuing Abatement
|
11/24/2020 10:03:34 AM
|
Litigation Pending
|
10/13/2020 6:54:54 AM
|
Executive Determination Issued
|
10/8/2020 10:21:03 AM
|
Executive Determination Requested
|
7/23/2020 8:22:30 AM
|
Notice of Violation sent
|
7/7/2020 4:11:43 PM
|
No Fees
|
7/7/2020 4:11:43 PM
|
File # Assigned: CE20480
|
7/7/2020 4:11:43 PM
|
Project Manager Assigned: Joe Letke
|
7/7/2020 4:11:43 PM
|
Project Created
|
7/7/2020 4:11:40 PM
|
Application Triaged/Accepted
|
7/7/2020 4:11:38 PM
|
Application submitted
|