| 9/25/2020 10:51:18 AM | Project Closed | 
                
                    | 9/25/2020 10:51:18 AM | Project Approved: 9/25/2020 | 
                
                    | 9/22/2020 3:44:52 PM | Submission Triaged | 
                
                    | 9/22/2020 3:41:01 PM | Submission received from Applicant | 
                
                    | 9/22/2020 3:25:25 PM | Submission request sent to Applicant | 
                
                    | 9/21/2020 9:54:29 AM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 9/17/2020 8:35:16 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 9/17/2020 12:38:43 PM | Submission Triaged | 
                
                    | 9/17/2020 9:31:41 AM | Submission received from Applicant | 
                
                    | 9/17/2020 9:27:31 AM | Submission request sent to Applicant | 
                
                    | 9/15/2020 12:44:10 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 9/15/2020 9:11:47 AM | Request for Review Comments email sent for Project Claremont Business Park 2 Filing 1 Early Grading for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review | 
                
                    | 9/15/2020 9:11:43 AM | Request for Review Comments email sent for Project Claremont Business Park 2 Filing 1 Early Grading for review by Lindsay Darden on behalf of PCD Project Manager | 
                
                    | 9/15/2020 9:11:37 AM | Request for Review Comments email sent for Project Claremont Business Park 2 Filing 1 Early Grading for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 9/14/2020 4:12:13 PM | Submission Triaged | 
                
                    | 9/14/2020 1:44:17 PM | Submission received from Applicant | 
                
                    | 9/11/2020 4:26:25 PM | Submission request sent to Applicant | 
                
                    | 9/10/2020 11:37:35 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 8/28/2020 5:07:08 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 8/18/2020 9:12:40 AM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 8/12/2020 3:21:36 PM | Request for Review Comments email sent for Project Claremont Business Park 2 Filing 1 Early Grading for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review | 
                
                    | 8/12/2020 3:21:35 PM | Request for Review Comments email sent for Project Claremont Business Park 2 Filing 1 Early Grading for review by Lindsay Darden on behalf of PCD Project Manager | 
                
                    | 8/12/2020 3:21:33 PM | Request for Review Comments email sent for Project Claremont Business Park 2 Filing 1 Early Grading for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 8/12/2020 2:07:56 PM | Submission Triaged | 
                
                    | 8/12/2020 1:00:26 PM | Submission received from Applicant | 
                
                    | 8/12/2020 10:58:50 AM | Submission request sent to Applicant | 
                
                    | 7/23/2020 8:16:22 AM | Submission request sent to Applicant | 
                
                    | 7/23/2020 8:11:41 AM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 7/23/2020 8:03:56 AM | Request for Review Comments email resent for Project Claremont Business Park 2 Filing 1 Early Grading for review by Lindsay Darden on behalf of PCD Project Manager | 
                
                    | 7/22/2020 5:18:23 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 7/20/2020 4:15:45 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 7/20/2020 12:53:28 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 7/1/2020 7:58:58 AM | Request for Review Comments email sent for Project Claremont Business Park Filing 2 Early Grading for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review | 
                
                    | 7/1/2020 7:58:57 AM | Request for Review Comments email sent for Project Claremont Business Park Filing 2 Early Grading for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer | 
                
                    | 7/1/2020 7:58:56 AM | Request for Review Comments email sent for Project Claremont Business Park Filing 2 Early Grading for review by Lindsay Darden on behalf of PCD Project Manager | 
                
                    | 7/1/2020 7:58:55 AM | Request for Review Comments email sent for Project Claremont Business Park Filing 2 Early Grading for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 6/30/2020 2:55:50 PM | Fees paid: 6/30/2020 (Receipt: 1002912) | 
                
                    | 6/30/2020 2:36:26 PM | Payment Request sent: 6/30/2020 | 
                
                    | 6/30/2020 2:36:26 PM | File # Assigned: EGP204 | 
                
                    | 6/30/2020 2:36:22 PM | Submission Triaged | 
                
                    | 6/30/2020 11:32:58 AM | Submission received from Applicant | 
                
                    | 6/25/2020 5:06:14 PM | Submission request sent to Applicant | 
                
                    | 6/25/2020 4:58:24 PM | Project Manager Assigned: Lindsay Darden | 
                
                    | 6/25/2020 4:58:24 PM | EA Assigned: EA19107 | 
                
                    | 6/25/2020 4:58:24 PM | Project Created |