7/15/2020 7:40:22 AM
|
Project Closed
|
|
7/15/2020 7:40:22 AM
|
Project Approved: 7/15/2020
|
|
7/15/2020 7:40:09 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
7/7/2020 1:37:59 PM
|
Request for Review Comments email sent for Project Link Rd Electrical Substation 1041 Applicability Determination for review by Lindsay Darden on behalf of PCD Project Manager
|
|
6/30/2020 3:39:02 PM
|
Submission Triaged
|
|
6/30/2020 1:54:56 PM
|
Submission received from Applicant
|
|
6/26/2020 9:33:24 AM
|
Submission request sent to Applicant
|
|
6/23/2020 10:08:45 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
6/14/2020 9:25:21 PM
|
Request for Review Comments email sent for Project Link Rd Electrical Substation 1041 Applicability Determination for review by Lindsay Darden on behalf of PCD Project Manager
|
|
6/12/2020 9:33:21 AM
|
Fees paid: 6/12/2020 (Receipt: 1002838)
|
|
6/11/2020 11:35:27 AM
|
Project Manager Assigned: Lindsay Darden
|
|
6/11/2020 11:35:09 AM
|
Payment Request sent: 6/11/2020
|
|
6/11/2020 11:35:09 AM
|
File # Assigned: ADM2019
|
|
6/11/2020 11:35:07 AM
|
Submission Triaged
|
|
6/11/2020 11:03:35 AM
|
Submission received from Applicant
|
|
6/3/2020 4:11:29 PM
|
Submission request sent to Applicant
|
|
6/3/2020 4:10:03 PM
|
Project Manager Assigned: Ryan Howser
|
|
6/3/2020 4:10:03 PM
|
Project Created
|