5/5/2021 7:51:20 AM
|
Project Closed
|
5/5/2021 7:51:20 AM
|
Project completed: 5/5/2021
|
4/27/2021 2:10:26 PM
|
Executive Determination Issued
|
3/23/2021 12:45:52 PM
|
Executive Determination Requested
|
2/16/2021 4:21:01 PM
|
Supervisor Letter Issued
|
1/27/2021 6:22:05 AM
|
Supervisor Letter Requested
|
9/1/2020 12:31:52 PM
|
Project Manager Assigned: Charles Carlisle
|
8/20/2020 2:32:04 PM
|
Notice of Violation sent
|
8/13/2020 11:52:16 AM
|
Project Manager Assigned: Scott Shevock
|
6/26/2020 12:56:46 PM
|
Project Manager Assigned: Joe Letke
|
5/21/2020 1:00:31 PM
|
No Fees
|
5/21/2020 1:00:31 PM
|
File # Assigned: CE20282
|
5/21/2020 1:00:30 PM
|
Project Manager Assigned: Mario Acosta
|
5/21/2020 1:00:30 PM
|
Project Created
|
5/21/2020 1:00:28 PM
|
Application Triaged/Accepted
|
5/21/2020 1:00:26 PM
|
Application submitted
|