6/25/2020 12:29:10 PM
|
Project Closed
|
6/25/2020 12:29:10 PM
|
Project Approved: 6/25/2020
|
6/14/2020 9:16:22 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
6/14/2020 9:15:54 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/5/2020 8:20:48 AM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Lindsay Darden on behalf of PCD Project Manager
|
6/3/2020 4:39:41 PM
|
Submission Triaged
|
6/3/2020 4:13:25 PM
|
Submission received from Applicant
|
6/3/2020 12:03:44 AM
|
Submission request sent to Applicant
|
5/27/2020 11:37:00 AM
|
Request for Review Comments returned by Donald Wescott Fire Protection District
|
5/26/2020 1:31:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/25/2020 4:05:30 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/13/2020 11:24:00 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/12/2020 2:37:49 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
5/12/2020 2:37:48 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Planning Director Larry Manning on behalf of Monument
|
5/12/2020 2:37:47 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Vern Champlin on behalf of Donald Wescott Fire Protection District
|
5/12/2020 2:37:47 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
5/12/2020 2:37:46 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
5/12/2020 2:37:44 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Anthony Pastorello on behalf of Academy Water & Sanitation
|
5/12/2020 2:37:43 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Lindsay Darden on behalf of PCD Project Manager
|
5/12/2020 2:37:42 PM
|
Request for Review Comments email sent for Project Keating Administrative Relief for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/11/2020 7:53:54 AM
|
Fees paid: 5/11/2020 (Receipt: 1002723)
|
5/10/2020 8:53:46 PM
|
Project Manager Assigned: Lindsay Darden
|
5/10/2020 8:53:26 PM
|
Payment Request sent: 5/10/2020
|
5/10/2020 8:53:25 PM
|
File # Assigned: ADR203
|
5/10/2020 8:53:23 PM
|
Submission Triaged
|
5/8/2020 9:55:28 AM
|
Submission received from Applicant
|
5/7/2020 7:53:25 PM
|
Submission request sent to Applicant
|
5/7/2020 7:53:17 PM
|
Submission Triaged
|
5/7/2020 2:20:52 PM
|
Submission received from Applicant
|
5/7/2020 1:17:10 PM
|
Submission request sent to Applicant
|
5/7/2020 1:17:04 PM
|
Submission Triaged
|
5/7/2020 11:28:40 AM
|
Submission received from Applicant
|
4/29/2020 3:30:25 PM
|
Submission request sent to Applicant
|
4/29/2020 3:28:58 PM
|
Project Manager Assigned: Petra Rangel
|
4/29/2020 3:28:58 PM
|
Project Created
|