10/6/2021 5:02:14 PM
|
Project Closed
|
10/6/2021 5:02:14 PM
|
Project Approved: 10/6/2021
|
9/17/2021 7:24:58 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
9/16/2021 9:15:35 AM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Elena Krebs on behalf of PCD Administrative Notice
|
9/14/2021 5:19:16 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/30/2021 11:57:14 AM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Ryan Howser on behalf of PCD Project Manager
|
8/30/2021 11:56:05 AM
|
Submission Triaged
|
8/29/2021 8:39:45 PM
|
Submission received from Applicant
|
8/10/2021 11:49:13 AM
|
Submission request sent to Applicant
|
8/10/2021 11:48:08 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/3/2021 10:04:31 AM
|
Request for Review Comments returned by PCD Engineering Division
|
7/29/2021 1:19:43 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Ryan Howser on behalf of PCD Project Manager
|
7/29/2021 1:19:39 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/29/2021 12:15:47 PM
|
Submission Triaged
|
7/28/2021 5:14:21 PM
|
Submission received from Applicant
|
7/23/2021 4:13:57 PM
|
Request for Review Comments returned by EPC Health Department
|
7/15/2021 10:17:19 AM
|
Submission request sent to Applicant
|
7/13/2021 4:27:28 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/13/2021 4:23:28 PM
|
Request for Review Comments email resent for Project CS Mayberry Special Use for review by Ryan Howser on behalf of PCD Project Manager
|
7/13/2021 12:55:52 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/6/2021 8:32:35 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/1/2021 1:24:22 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/30/2021 1:47:22 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/24/2021 11:26:13 AM
|
Request for Review Comments email resent for Project CS Mayberry Special Use for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/24/2021 10:29:24 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/21/2021 2:25:55 PM
|
Request for Review Comments returned by EPC Code Enforcement
|
6/15/2021 4:02:04 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Mindy Madden on behalf of EPC Code Enforcement
|
6/15/2021 4:02:00 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/15/2021 12:04:22 PM
|
Project Manager Assigned: Ryan Howser
|
6/9/2021 9:25:44 AM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
6/8/2021 12:24:40 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by General Email on behalf of Mountain View Electric Association, Inc.
|
6/8/2021 12:24:38 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Bookkeeper Peggy Current on behalf of Ellicott Metro
|
6/8/2021 12:24:36 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Michael Henley on behalf of Ellicott Fire Protection District
|
6/8/2021 12:24:33 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
6/8/2021 12:24:31 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
6/8/2021 12:24:28 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
6/8/2021 12:24:26 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office
|
6/8/2021 12:24:24 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Catherine McGarvy on behalf of EPC Health Department
|
6/8/2021 12:24:17 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Sophie Kiepe on behalf of PCD Project Manager
|
6/8/2021 12:24:15 PM
|
Request for Review Comments email sent for Project CS Mayberry Special Use for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/5/2021 10:46:28 AM
|
Fees paid: 6/5/2021 (Receipt: 1004516)
|
6/4/2021 1:22:51 PM
|
Payment Request sent: 6/4/2021
|
6/4/2021 1:22:51 PM
|
File # Assigned: AL2110
|
6/4/2021 1:22:45 PM
|
Submission Triaged
|
6/3/2021 10:56:23 PM
|
Submission received from Applicant
|
3/31/2021 7:05:23 PM
|
Submission request sent to Applicant
|
3/31/2021 7:05:04 PM
|
Submission Triaged
|
3/31/2021 4:37:57 PM
|
Submission received from Applicant
|
3/30/2021 7:44:49 PM
|
Project Manager Assigned: Sophie Kiepe
|
3/30/2021 7:44:38 PM
|
Submission request sent to Applicant
|
3/24/2020 9:42:13 AM
|
Submission request sent to Applicant
|
3/24/2020 9:41:31 AM
|
EA Assigned: EA18299
|
3/24/2020 9:41:31 AM
|
Project Created
|