6/17/2021 12:54:49 PM
|
Project Closed
|
6/17/2021 12:54:49 PM
|
Project completed: 6/17/2021
|
1/20/2021 7:33:34 AM
|
Litigation Pending
|
11/19/2020 4:53:17 PM
|
Executive Determination Issued
|
11/5/2020 7:01:57 AM
|
Executive Determination Requested
|
9/1/2020 11:47:53 AM
|
Project Manager Assigned: Charles Carlisle
|
8/14/2020 1:38:30 PM
|
Project Manager Assigned: Scott Shevock
|
6/26/2020 12:37:38 PM
|
Project Manager Assigned: Joe Letke
|
5/13/2020 1:06:20 PM
|
Notice of Violation sent
|
4/23/2020 2:45:51 PM
|
Project Manager Assigned: Mario Acosta
|
3/19/2020 8:31:37 AM
|
No Fees
|
3/19/2020 8:31:37 AM
|
File # Assigned: CE20150
|
3/19/2020 8:31:36 AM
|
Project Manager Assigned: Mindy Madden
|
3/19/2020 8:31:36 AM
|
Project Created
|
3/19/2020 8:31:33 AM
|
Application Triaged/Accepted
|
3/19/2020 8:31:31 AM
|
Application submitted
|