Project Details

Search


File Number
OAR207
Project Name
Templeton Gap Townhomes PUD
Description
PUD Development Plan, PUD Concept Plan, PUD Rezoning, and Final Plat
Parcels
5307000011 5307000011 5307000045 5307000045
Applicant
City of Colorado Springs
Matthew Lepke ( matthew.lepke@coloradosprings.gov ) Matthew Lepke ( matthew.lepke@coloradosprings.gov )
File Prefix
OAR - Outside Agency Review
Year
2020
Project Manager
Ryan Howser
Status
Closed
Created
1/23/2020 11:22:56 AM

View: Review Comments


Approved Documents (1)

Link Document
View Review Comments


Review Documents (21)

Link Document Date
View Application/Petition Form 1/23/2020 1:27:09 PM
View PUD Development Plan - can include phasing if proposed 1/23/2020 1:27:09 PM
View Buck slip 1/23/2020 1:27:13 PM
View Final Plat Drawings 1/23/2020 1:27:12 PM
View Zoning Map 1/23/2020 1:27:13 PM
View Drainage Report - Final 1/23/2020 1:27:11 PM
View Traffic Impact Study 1/23/2020 1:27:12 PM
View Correspondence_V2 6/2/2020 7:58:02 AM
View CPC PUD 20-00014 Application 1/23/2020 1:30:17 PM
View CPC PUD 20-00014 Drawings_V2 6/2/2020 7:58:02 AM
View CPC PUD 20-00014 Elevations_V2 6/2/2020 7:58:03 AM
View CPC PUD 20-00014 Other 1 6/2/2020 7:58:03 AM
View CPC PUD 20-00014 Soil Test Report_V2 6/2/2020 7:58:04 AM
View CPC PUP 20-00013 Application 1/23/2020 1:30:18 PM
View CPC PUP 20-00013 Drawings_V2 6/2/2020 7:58:04 AM
View CPC PUP 20-00013 Traffic Report 6/2/2020 7:58:05 AM
View CPC PUZ 20-00012 Application 1/23/2020 1:30:18 PM
View CPC PUZ 20-00012 Drawings_V2 6/2/2020 7:58:06 AM
View Elevation Plans 1/23/2020 1:27:10 PM
View Final Plat_V2 6/2/2020 7:58:01 AM
View Review Letter_V2 6/2/2020 7:58:06 AM



Events (19)

Date Comment
9/18/2020 10:19:14 AM Project Closed
9/18/2020 10:19:14 AM Project Approved: 9/18/2020
6/12/2020 12:56:11 PM Request for Review Comments returned by PCD Project Manager
6/9/2020 5:16:07 PM Request for Review Comments returned by PCD Engineering Division
6/2/2020 7:59:16 AM Request for Review Comments email sent for Project Templeton Gap Townhomes PUD for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
6/2/2020 7:59:15 AM Request for Review Comments email sent for Project Templeton Gap Townhomes PUD for review by Ryan Howser on behalf of PCD Project Manager
6/2/2020 7:59:13 AM Request for Review Comments email sent for Project Templeton Gap Townhomes PUD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
6/2/2020 7:56:07 AM Project reopened for Review Comments
5/19/2020 10:24:06 AM Project Closed
5/19/2020 10:24:06 AM Project Approved: 5/19/2020
2/4/2020 11:22:09 AM Request for Review Comments returned by PCD Project Manager
2/4/2020 10:55:41 AM Request for Review Comments returned by PCD Engineering Division
1/23/2020 1:31:30 PM Request for Review Comments email sent for Project Templeton Gap Townhomes PUD for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
1/23/2020 1:31:29 PM Request for Review Comments email sent for Project Templeton Gap Townhomes PUD for review by Ryan Howser on behalf of PCD Project Manager
1/23/2020 1:31:28 PM Request for Review Comments email sent for Project Templeton Gap Townhomes PUD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
1/23/2020 11:23:04 AM No Fees
1/23/2020 11:23:04 AM File # Assigned: OAR207
1/23/2020 11:23:03 AM Project Manager Assigned: Ryan Howser
1/23/2020 11:23:02 AM Project Created