3/10/2020 8:06:04 AM
|
Project Closed
|
3/10/2020 8:06:04 AM
|
Project Approved: 3/10/2020
|
2/24/2020 10:10:58 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
2/24/2020 10:10:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/24/2020 9:31:53 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
2/10/2020 10:54:21 AM
|
Request for Review Comments email sent for Project Crystal Park Site S-334 for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
2/10/2020 10:54:17 AM
|
Request for Review Comments email sent for Project Crystal Park Site S-334 for review by Gabe Sevigny on behalf of PCD Project Manager
|
2/10/2020 10:52:48 AM
|
Fees paid: 2/10/2020 (Receipt: 1002352)
|
2/5/2020 11:37:39 AM
|
Payment Request sent: 2/5/2020
|
2/5/2020 11:37:33 AM
|
File # Assigned: SF205
|
2/5/2020 11:35:12 AM
|
Submission Triaged
|
2/4/2020 5:39:01 PM
|
Submission received from Applicant
|
12/17/2019 10:58:37 AM
|
Submission request sent to Applicant
|
10/3/2019 9:53:38 AM
|
Submission request sent to Applicant
|
10/3/2019 9:51:57 AM
|
Project Manager Assigned: Gabe Sevigny
|
10/3/2019 9:51:57 AM
|
Project Created
|