12/7/2021 4:29:46 PM
|
Project Closed
|
|
12/7/2021 4:29:46 PM
|
Project Approved: 12/7/2021
|
|
11/24/2021 2:49:40 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
11/24/2021 2:40:21 PM
|
Request for Review Comments email resent for Project Mt. States Pipe and Supply Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
11/24/2021 1:34:44 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
11/24/2021 7:34:37 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
11/17/2021 1:23:11 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by John Green on behalf of PCD Project Manager
|
|
11/17/2021 1:23:07 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
11/17/2021 1:21:23 PM
|
Submission Triaged
|
|
11/17/2021 9:36:35 AM
|
Submission received from Applicant
|
|
11/2/2021 10:49:21 AM
|
Submission request sent to Applicant
|
|
11/2/2021 9:55:10 AM
|
Submission request sent to Applicant
|
|
10/13/2021 4:58:49 PM
|
Submission Triaged
|
|
10/12/2021 11:33:32 AM
|
Submission received from Applicant
|
|
10/6/2021 4:49:04 PM
|
Submission request sent to Applicant
|
|
10/5/2021 7:28:29 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
9/28/2021 9:40:44 PM
|
Request for Review Comments returned by PCD Engineering Division
|
|
9/20/2021 1:07:41 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
9/16/2021 7:40:13 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
9/16/2021 7:40:09 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by John Green on behalf of PCD Project Manager
|
|
9/16/2021 7:40:05 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
9/16/2021 7:38:13 AM
|
Submission Triaged
|
|
9/15/2021 2:19:11 PM
|
Submission received from Applicant
|
|
9/15/2021 7:39:48 AM
|
Submission request sent to Applicant
|
|
6/10/2021 5:08:05 PM
|
Project Manager Assigned: John Green
|
|
3/8/2021 11:22:12 AM
|
Submission request sent to Applicant
|
|
3/8/2021 10:41:47 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
3/4/2021 4:01:14 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
2/23/2021 3:52:14 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
2/4/2021 3:49:01 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
2/4/2021 3:47:09 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
|
2/4/2021 3:47:07 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Sophie Kiepe on behalf of PCD Project Manager
|
|
2/4/2021 3:47:03 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
2/4/2021 3:01:40 PM
|
Submission Triaged
|
|
2/4/2021 10:25:59 AM
|
Submission received from Applicant
|
|
1/8/2021 8:25:11 AM
|
Submission request sent to Applicant
|
|
12/30/2020 10:45:26 AM
|
Submission request sent to Applicant
|
|
12/27/2020 2:10:08 PM
|
Project Manager Assigned: Sophie Kiepe
|
|
12/10/2020 2:36:56 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
12/7/2020 8:00:07 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
12/4/2020 5:30:15 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
11/24/2020 7:58:36 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
11/20/2020 2:25:20 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
11/20/2020 2:25:17 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
11/20/2020 2:25:15 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lindsay Darden on behalf of PCD Project Manager
|
|
11/20/2020 2:25:11 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
11/20/2020 2:18:29 PM
|
Submission Triaged
|
|
11/20/2020 1:20:25 PM
|
Submission received from Applicant
|
|
11/9/2020 10:35:26 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
11/9/2020 10:21:28 AM
|
Request for Review Comments email resent for Project Mt. States Pipe and Supply Site Development Plan for review by Lindsay Darden on behalf of PCD Project Manager
|
|
10/16/2020 2:55:14 PM
|
Submission request sent to Applicant
|
|
10/13/2020 12:07:42 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
10/8/2020 9:53:10 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
|
10/7/2020 11:38:24 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
10/6/2020 10:00:37 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
10/6/2020 9:22:46 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
9/29/2020 1:02:09 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
9/25/2020 3:31:15 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
9/25/2020 3:31:13 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
|
|
9/25/2020 3:31:09 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
9/25/2020 3:31:07 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
9/25/2020 3:31:05 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lindsay Darden on behalf of PCD Project Manager
|
|
9/25/2020 3:31:01 PM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
9/25/2020 3:05:42 PM
|
Submission Triaged
|
|
9/25/2020 11:24:35 AM
|
Submission received from Applicant
|
|
9/25/2020 10:22:45 AM
|
Submission request sent to Applicant
|
|
9/25/2020 9:32:16 AM
|
Submission request sent to Applicant
|
|
9/25/2020 9:31:37 AM
|
Submission Triaged
|
|
9/24/2020 3:50:13 PM
|
Submission received from Applicant
|
|
8/15/2020 6:16:28 PM
|
Request for Review Comments returned by EPC Health Department
|
|
8/11/2020 3:55:04 PM
|
Submission request sent to Applicant
|
|
8/11/2020 3:47:01 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
8/11/2020 3:37:13 PM
|
Request for Review Comments email resent for Project Mt. States Pipe and Supply Site Development Plan for review by Lindsay Darden on behalf of PCD Project Manager
|
|
8/11/2020 10:44:01 AM
|
Request for Review Comments returned by PCD Engineering Division
|
|
8/6/2020 2:48:52 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
|
8/6/2020 9:04:55 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
|
8/5/2020 9:43:29 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
8/5/2020 11:18:07 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
8/4/2020 3:20:56 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
|
7/28/2020 4:38:16 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
7/28/2020 2:45:11 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
7/28/2020 12:11:20 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
|
7/23/2020 9:04:19 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
|
7/23/2020 9:04:18 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
7/23/2020 9:04:16 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
|
7/23/2020 9:04:15 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
|
|
7/23/2020 9:04:14 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
|
7/23/2020 9:04:13 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
|
7/23/2020 9:04:12 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
|
7/23/2020 9:04:11 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by on behalf of EPC Health Department
|
|
7/23/2020 9:04:08 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
|
7/23/2020 9:04:07 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Lindsay Darden on behalf of PCD Project Manager
|
|
7/23/2020 9:04:06 AM
|
Request for Review Comments email sent for Project Mt. States Pipe and Supply Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
|
7/21/2020 11:38:19 AM
|
Fees paid: 7/21/2020 (Receipt: 1003011)
|
|
7/21/2020 10:51:43 AM
|
Payment Request sent: 7/21/2020
|
|
7/21/2020 10:51:36 AM
|
Payment Request canceled: 7/21/2020
|
|
5/26/2020 3:46:31 PM
|
Payment Request sent: 5/26/2020
|
|
5/26/2020 3:46:29 PM
|
File # Assigned: PPR2020
|
|
5/26/2020 3:46:10 PM
|
Submission Triaged
|
|
5/26/2020 3:24:24 PM
|
Submission received from Applicant
|
|
5/19/2020 7:58:14 AM
|
Submission request sent to Applicant
|
|
5/19/2020 7:57:56 AM
|
Submission Triaged
|
|
5/18/2020 3:37:01 PM
|
Submission received from Applicant
|
|
5/3/2020 7:40:52 PM
|
Submission request sent to Applicant
|
|
5/3/2020 7:40:42 PM
|
Submission Triaged
|
|
5/3/2020 7:30:01 PM
|
Project Manager Assigned: Lindsay Darden
|
|
5/1/2020 9:59:11 AM
|
Submission received from Applicant
|
|
10/9/2019 7:20:37 AM
|
Submission request sent to Applicant
|
|
9/26/2019 1:25:14 PM
|
Submission request sent to Applicant
|
|
9/26/2019 1:24:19 PM
|
Project Manager Assigned: Nina Ruiz
|
|
9/26/2019 1:24:19 PM
|
EA Assigned: EA18269
|
|
9/26/2019 1:24:19 PM
|
Project Created
|