Project Details

Search


File Number
PPR1954
Project Name
Frontier Sportsman Site Development
Parcels
4330000017 4330000017
Applicant
Dirt Solutions
Keith Moore ( kmoore@rmg-engineers.com )
(719) 394-3087
Keith Moore ( kmoore@rmg-engineers.com )
(719) 394-3087
File Prefix
PPR - Plot Plan Review
Year
2019
Project Manager
Nina Ruiz
Status
Closed
Created
8/26/2019 9:04:49 AM

View: Review Comments


Approved Documents (8)

Link Document
View Erosion and Stormwater Quality Control Permit (ESQCP)
View Grading & Erosion Control checklist
View PBMP Applicability Form
View SWMP checklist
View Grading & Erosion Control Plan (24 x 36)
View Site Development Plan (24" x 36")
View Drainage Report - Final
View Financial Assurance Forms


Additional Documents (1)

Link Document Comment
View Administrative Final Release


Review Documents (16)

Link Document Date
View Application/Petition Form 11/6/2020 8:42:51 AM
View Legal Description (MS WORD Version required) 9/18/2019 3:04:25 PM
View Letter of Intent 5/6/2020 12:37:01 PM
View Title Commitment (Current within 30 days of submittal) 12/19/2019 1:50:11 PM
View Vicinity/Location Map 9/19/2019 1:14:43 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 2/9/2021 10:43:51 AM
View Grading & Erosion Control checklist 2/9/2021 10:43:52 AM
View PBMP Applicability Form 1/25/2021 3:57:57 PM
View SWMP checklist 1/25/2021 3:57:57 PM
View Grading & Erosion Control Plan (24 x 36) 2/9/2021 10:43:50 AM
View Landscape Plan drawings (24" x 36") 5/6/2020 12:37:00 PM
View Sign Plan 11/11/2019 12:48:12 PM
View Site Development Plan (24" x 36") 5/6/2020 12:37:01 PM
View Drainage Report - Final 11/6/2020 8:42:52 AM
View Financial Assurance Forms 1/25/2021 3:57:54 PM
View RMG Response Letter 1/25/2021 3:59:03 PM



Events (75)

Date Comment
3/22/2021 12:51:31 PM Project Closed
3/22/2021 12:51:31 PM Project Approved: 3/22/2021
3/10/2021 9:08:31 AM Request for Review Comments returned by PCD Engineering Division
3/9/2021 8:15:16 PM Request for Review Comments email resent for Project Frontier Sportsman Site Development for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
3/9/2021 3:47:17 PM Request for Review Comments returned by PCD Engineering Division
2/28/2021 2:47:33 PM Request for Review Comments returned by PCD Project Manager
2/16/2021 2:19:07 PM Request for Review Comments returned by EPC Stormwater Review
2/10/2021 9:00:05 PM Submission Triaged
2/9/2021 10:44:07 AM Submission received from Applicant
2/9/2021 10:35:58 AM Submission request sent to Applicant
2/9/2021 10:26:32 AM Submission request sent to Applicant
2/4/2021 12:32:21 PM Request for Review Comments returned by EPC Environmental Services
2/4/2021 6:08:57 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
2/4/2021 6:08:55 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
2/4/2021 6:08:53 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Kathy Andrew on behalf of EPC Environmental Services
2/4/2021 6:08:51 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Nina Ruiz on behalf of PCD Project Manager
2/4/2021 6:08:46 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
2/4/2021 6:06:33 AM Submission Triaged
2/3/2021 10:34:16 AM Submission received from Applicant
11/25/2020 2:31:36 PM Submission request sent to Applicant
11/25/2020 2:31:17 PM Request for Review Comments returned by PCD Project Manager
11/25/2020 2:26:44 PM Request for Review Comments email resent for Project Frontier Sportsman Site Development for review by Nina Ruiz on behalf of PCD Project Manager
11/24/2020 3:09:13 PM Request for Review Comments returned by PCD Engineering Division
11/24/2020 4:56:05 AM Request for Review Comments returned by PCD Project Manager
11/23/2020 1:48:01 PM Request for Review Comments returned by EPC Stormwater Review
11/9/2020 12:08:47 PM Request for Review Comments returned by Falcon Fire Protection District
11/9/2020 4:43:32 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
11/9/2020 4:43:29 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
11/9/2020 4:43:27 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Nina Ruiz on behalf of PCD Project Manager
11/9/2020 4:43:23 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
11/9/2020 4:41:09 AM Submission Triaged
11/6/2020 8:43:14 AM Submission received from Applicant
11/6/2020 7:19:37 AM Submission request sent to Applicant
11/6/2020 7:18:51 AM Submission Triaged
11/5/2020 1:21:27 PM Submission received from Applicant
5/7/2020 10:34:13 AM Submission request sent to Applicant
5/7/2020 10:33:53 AM Submission Triaged
5/6/2020 12:44:55 PM Submission received from Applicant
4/1/2020 12:31:51 PM Request for Review Comments returned by Falcon Fire Protection District
2/18/2020 9:53:45 AM Request for Review Comments returned by EPC Health Department
2/11/2020 5:17:56 PM Submission request sent to Applicant
2/11/2020 5:16:38 PM Request for Review Comments returned by PCD Project Manager
2/11/2020 5:11:58 PM Request for Review Comments email resent for Project Frontier Sportsman Site Development for review by Nina Ruiz on behalf of PCD Project Manager
2/11/2020 1:24:20 PM Request for Review Comments returned by PCD Engineering Division
2/10/2020 8:54:30 AM Request for Review Comments returned by PCD Project Manager
1/8/2020 2:20:47 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
1/6/2020 10:46:44 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
1/2/2020 12:48:49 PM Request for Review Comments returned by EPC Environmental Services
1/2/2020 12:38:44 PM Request for Review Comments returned by Pikes Peak Regional Building Department
12/30/2019 9:50:28 AM Request for Review Comments returned by El Paso County Conservation Dist
12/26/2019 8:20:09 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
12/26/2019 8:20:05 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
12/26/2019 8:20:01 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by John Paget on behalf of El Paso County Fire Marshall
12/26/2019 8:19:57 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Pamela Davison on behalf of El Paso County Conservation Dist
12/26/2019 8:19:54 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
12/26/2019 8:19:50 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
12/26/2019 8:19:46 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Commander John Padgett on behalf of EPC Sheriff's Department
12/26/2019 8:19:42 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
12/26/2019 8:19:32 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by on behalf of EPC Health Department
12/26/2019 8:19:28 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Kathy Andrew on behalf of EPC Environmental Services
12/26/2019 8:19:24 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Nina Ruiz on behalf of PCD Project Manager
12/26/2019 8:19:20 AM Request for Review Comments email sent for Project Frontier Sportsman Site Development for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
12/24/2019 10:09:21 AM Fees paid: 12/24/2019 (Receipt: 1002188)
12/23/2019 6:50:01 AM Payment Request sent: 12/23/2019
12/23/2019 6:49:55 AM File # Assigned: PPR1954
12/19/2019 2:17:49 PM Submission Triaged
12/19/2019 1:50:30 PM Submission received from Applicant
12/2/2019 5:09:36 PM Submission request sent to Applicant
12/2/2019 5:09:21 PM Submission Triaged
12/2/2019 2:52:37 PM Submission received from Applicant
9/19/2019 12:42:07 PM Submission request sent to Applicant
9/12/2019 8:42:21 AM Submission request sent to Applicant
8/26/2019 9:08:34 AM Submission request sent to Applicant
8/26/2019 9:04:57 AM Project Manager Assigned: Nina Ruiz
8/26/2019 9:04:57 AM Project Created