10/22/2019 8:06:23 AM
|
Project Closed
|
10/22/2019 8:06:23 AM
|
Project Approved: 10/22/2019
|
10/17/2019 8:35:38 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
10/2/2019 3:38:54 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/30/2019 9:35:18 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/18/2019 11:41:41 AM
|
Request for Review Comments returned by EPC Environmental Services
|
9/12/2019 10:40:57 AM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Bea Romero on behalf of CenturyLink
|
9/11/2019 5:19:54 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Stephanie Hale on behalf of Ellicott Metro
|
9/11/2019 5:19:54 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Michael Henley on behalf of Ellicott Fire Protection District
|
9/11/2019 5:19:48 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by on behalf of EPC Health Department
|
9/11/2019 5:19:47 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Kathy Andrew on behalf of EPC Environmental Services
|
9/11/2019 5:19:46 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Gabe Sevigny on behalf of PCD Project Manager
|
9/11/2019 5:19:45 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/11/2019 5:14:16 PM
|
Submission Triaged
|
9/11/2019 1:54:49 PM
|
Submission received from Applicant
|
9/11/2019 1:46:21 PM
|
Submission request sent to Applicant
|
8/21/2019 4:41:52 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/20/2019 8:54:07 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
8/14/2019 1:58:49 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
8/13/2019 3:56:09 PM
|
Request for Review Comments returned by PCD Engineering Division
|
8/2/2019 2:10:24 PM
|
Request for Review Comments returned by EPC Environmental Services
|
8/2/2019 11:02:24 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
7/31/2019 2:05:01 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
7/30/2019 3:12:53 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
7/30/2019 3:12:52 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Stephanie Hale on behalf of Ellicott Metro
|
7/30/2019 3:12:51 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Michael Henley on behalf of Ellicott Fire Protection District
|
7/30/2019 3:12:50 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Pamela Davison on behalf of El Paso County Conservation Dist
|
7/30/2019 3:12:49 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
7/30/2019 3:12:48 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
7/30/2019 3:12:47 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
7/30/2019 3:12:46 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
7/30/2019 3:12:43 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by on behalf of EPC Health Department
|
7/30/2019 3:12:42 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Kathy Andrew on behalf of EPC Environmental Services
|
7/30/2019 3:12:41 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Gabe Sevigny on behalf of PCD Project Manager
|
7/30/2019 3:12:40 PM
|
Request for Review Comments email sent for Project ANTELOPE ACRES, REPLAT OF LOT 13 AND PORTION OF LOT 14 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/30/2019 2:53:09 PM
|
Fees paid: 7/30/2019 (Receipt: 1001642)
|
7/29/2019 10:21:31 AM
|
Payment Request sent: 7/29/2019
|
7/29/2019 10:21:25 AM
|
File # Assigned: VR191
|
7/26/2019 4:13:37 PM
|
Submission Triaged
|
7/26/2019 4:08:29 PM
|
Project Manager Assigned: Gabe Sevigny
|
7/26/2019 4:02:26 PM
|
Submission received from Applicant
|
6/27/2019 1:17:35 PM
|
Submission request sent to Applicant
|
6/27/2019 1:15:58 PM
|
Submission request canceled
|
6/18/2019 2:00:52 PM
|
Submission request sent to Applicant
|
6/18/2019 1:43:59 PM
|
Project Manager Assigned: Len Kendall
|
6/18/2019 1:43:59 PM
|
EA Assigned: EA19105
|
6/18/2019 1:43:59 PM
|
Project Created
|