7/19/2022 1:51:46 PM
|
Project Closed
|
7/19/2022 1:51:46 PM
|
Project Approved: 7/19/2022
|
7/13/2022 7:15:23 AM
|
Submission Triaged
|
7/12/2022 10:18:15 PM
|
Submission received from Applicant
|
7/12/2022 3:07:41 PM
|
Submission request sent to Applicant
|
7/12/2022 3:01:53 PM
|
Submission request sent to Applicant
|
6/13/2022 12:19:10 PM
|
Project reopened for Approval requests
|
6/13/2022 12:18:59 PM
|
Project Closed
|
6/13/2022 12:18:59 PM
|
Project Approved: 6/13/2022
|
4/21/2022 1:47:21 PM
|
Project reopened for Approval requests
|
4/21/2022 1:47:03 PM
|
Project Closed
|
4/21/2022 1:47:03 PM
|
Project Approved: 4/21/2022
|
4/20/2022 7:40:29 PM
|
Submission Triaged
|
4/20/2022 4:41:40 PM
|
Submission received from Applicant
|
4/20/2022 3:54:08 PM
|
Submission request sent to Applicant
|
4/20/2022 3:52:15 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/20/2022 10:04:16 AM
|
Submission request sent to Applicant
|
4/20/2022 8:27:05 AM
|
Submission request sent to Applicant
|
4/13/2022 4:43:29 PM
|
Request for Review Comments email sent for Project Mose rezone for review by Kari Parsons on behalf of PCD Project Manager
|
4/13/2022 4:42:38 PM
|
Submission Triaged
|
4/13/2022 2:37:51 PM
|
Submission received from Applicant
|
4/13/2022 1:07:07 PM
|
Submission request sent to Applicant
|
4/13/2022 1:06:54 PM
|
Submission request sent to Applicant
|
4/13/2022 1:06:46 PM
|
Submission Triaged
|
4/13/2022 1:05:01 PM
|
Submission received from Applicant
|
4/13/2022 12:32:01 PM
|
Submission request sent to Applicant
|
4/13/2022 12:31:44 PM
|
Request for Review Comments returned by PCD Project Manager
|
4/12/2022 11:58:07 AM
|
Project Manager Assigned: Kari Parsons
|
4/6/2022 8:58:41 AM
|
Request for Review Comments email sent for Project Mose rezone for review by John Green on behalf of PCD Project Manager
|
3/31/2022 1:36:43 PM
|
Submission Triaged
|
3/30/2022 2:22:54 PM
|
Submission received from Applicant
|
2/24/2022 7:19:32 AM
|
Submission request sent to Applicant
|
2/24/2022 7:19:13 AM
|
Submission Triaged
|
2/23/2022 9:00:31 PM
|
Submission received from Applicant
|
2/23/2022 2:13:36 PM
|
Submission request sent to Applicant
|
11/18/2021 7:20:00 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/26/2021 10:57:23 AM
|
Request for Review Comments email sent for Project Mose rezone for review by John Green on behalf of PCD Project Manager
|
10/26/2021 10:56:59 AM
|
Submission Triaged
|
10/22/2021 2:07:14 PM
|
Submission received from Applicant
|
9/7/2021 10:19:35 AM
|
Submission request sent to Applicant
|
9/7/2021 10:18:50 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/19/2021 2:17:59 PM
|
Request for Review Comments email sent for Project Mose rezone for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
8/19/2021 2:17:57 PM
|
Request for Review Comments email sent for Project Mose rezone for review by Melissa Andrews on behalf of Falcon School District 49
|
8/19/2021 2:17:55 PM
|
Request for Review Comments email sent for Project Mose rezone for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
8/19/2021 2:17:53 PM
|
Request for Review Comments email sent for Project Mose rezone for review by John Green on behalf of PCD Project Manager
|
8/19/2021 2:17:18 PM
|
Submission Triaged
|
8/19/2021 12:08:00 PM
|
Submission received from Applicant
|
6/15/2021 5:38:09 PM
|
Fees paid: 6/15/2021 (Receipt: 1004583)
|
5/27/2021 4:22:09 PM
|
Payment Request sent: 5/27/2021
|
2/17/2021 5:48:12 PM
|
Submission request sent to Applicant
|
2/17/2021 5:47:42 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/2/2021 10:46:10 AM
|
Request for Review Comments email sent for Project Mose rezone for review by John Green on behalf of PCD Project Manager
|
1/14/2021 1:57:42 PM
|
Submission Triaged
|
1/14/2021 1:07:13 PM
|
Submission received from Applicant
|
1/10/2021 10:33:17 AM
|
Request for Review Comments returned by EPC Health Department
|
1/4/2021 1:04:04 PM
|
Submission request sent to Applicant
|
12/30/2020 8:21:46 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/14/2020 7:25:31 AM
|
Request for Review Comments email sent for Project Mose rezone for review by John Green on behalf of PCD Project Manager
|
12/9/2020 7:28:54 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/8/2020 10:56:49 AM
|
Request for Review Comments returned by EPC Parks Department
|
12/7/2020 9:03:04 PM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
12/3/2020 8:57:02 AM
|
Project Manager Assigned: John Green
|
12/1/2020 5:07:21 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/30/2020 5:11:17 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/30/2020 10:12:03 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
11/30/2020 8:19:09 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
11/25/2020 10:45:48 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/24/2020 1:40:31 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
11/19/2020 1:24:17 PM
|
Request for Review Comments returned by EPC Environmental Services
|
11/18/2020 11:07:28 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
11/18/2020 9:39:15 AM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
11/18/2020 8:48:10 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
11/18/2020 7:27:38 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Garrett Markus on behalf of Southeastern Colorado Water Conservancy
|
11/18/2020 7:27:36 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Administrative Assistant Cathy Hansen-Lee on behalf of Mountain View Electric Association, Inc.
|
11/18/2020 7:27:34 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Melissa Andrews on behalf of Falcon School District 49
|
11/18/2020 7:27:32 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
11/18/2020 7:27:30 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Pamela Davis on behalf of El Paso County Conservation Dist
|
11/18/2020 7:27:26 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
11/18/2020 7:27:23 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
11/18/2020 7:27:21 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
11/18/2020 7:27:19 AM
|
Request for Review Comments email sent for Project Mose rezone for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
11/18/2020 7:27:17 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
11/18/2020 7:27:15 AM
|
Request for Review Comments email sent for Project Mose rezone for review by on behalf of EPC Parks Department
|
11/18/2020 7:27:13 AM
|
Request for Review Comments email sent for Project Mose rezone for review by on behalf of EPC Health Department
|
11/18/2020 7:27:07 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/18/2020 7:27:05 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Edi Anderson on behalf of EPC County Attorney's Office
|
11/18/2020 7:27:02 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Lori Seago on behalf of County Attorney - Development Review
|
11/18/2020 7:27:00 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Rad Dickson on behalf of PCD Project Manager
|
11/18/2020 7:26:58 AM
|
Request for Review Comments email sent for Project Mose rezone for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/12/2020 10:32:30 AM
|
File # Assigned: P206
|
11/12/2020 10:31:38 AM
|
Submission Triaged
|
11/11/2020 10:10:57 AM
|
Submission received from Applicant
|
11/4/2020 1:34:42 PM
|
Submission request sent to Applicant
|
11/4/2020 1:33:18 PM
|
Submission Triaged
|
11/4/2020 1:28:07 PM
|
Project Manager Assigned: Rad Dickson
|
10/16/2020 12:29:30 PM
|
Submission received from Applicant
|
10/6/2020 5:33:11 AM
|
Submission request sent to Applicant
|
10/6/2020 5:32:42 AM
|
Project reopened for Review Comments
|
6/17/2020 12:00:00 AM
|
Project Closed
|
6/17/2020 12:00:00 AM
|
Project Expired one year after 06/17/2019 Submission Request 06/17/2020
|
6/17/2019 10:24:00 AM
|
Submission request sent to Applicant
|
6/17/2019 9:40:42 AM
|
Project Manager Assigned: Gabe Sevigny
|
6/17/2019 9:40:42 AM
|
EA Assigned: EA19106
|
6/17/2019 9:40:42 AM
|
Project Created
|