Project Details

Search


File Number
P192
Project Name
Pine View Estates Rezoning
Parcels
4100000428 4100000428
Applicant
Alice Jolene Owens
Alice Owens ( joleneowens@hotmail.com )
(719) 596-7447
Alice Owens ( joleneowens@hotmail.com )
(719) 596-7447
EA Number
EA18241
File Prefix
P - Rezoning to A-5; A-35; F-5; RR.5; RR2,5; and RR-2
Year
2019
Project Manager
Gabe Sevigny
Status
Closed
Created
8/22/2018 1:17:30 PM

View: Review Comments



Additional Documents (14)

Link Document Comment
View neighbor notification of hearing
View Property Posting ID card
View Property Posting
View neighbor response 1
View hearing presentation
View PC Staff Report
View PC Approval Letter
View Neighbor Notification of New Hearing
View Opposition 1
View Opposition 2
View Recorded BOCC Resolution
View PC Resolution
View BoCC Hearing Presentation
View New temp public hearing procedures


Review Documents (7)

Link Document Date
View Adjacent Property Owner Notification (Includes letter and certified mailing receipts) 2/4/2020 2:13:55 PM
View Application/Petition Form 11/6/2019 11:43:43 AM
View Legal Description (MS WORD Version required) 11/6/2019 9:09:25 PM
View Letter of Intent 12/31/2019 9:17:32 AM
View Title Commitment (Current within 30 days of submittal) 12/31/2019 10:00:27 AM
View Vicinity/Location Map 11/5/2019 9:52:02 AM
View Zoning Map 1/14/2020 4:46:30 PM



Events (53)

Date Comment
4/29/2020 12:39:15 PM Project Closed
4/29/2020 12:39:15 PM Project Approved: 4/29/2020
3/4/2020 4:14:08 PM Project Ready for Approval requests. Review Comment period is complete.
2/4/2020 2:44:41 PM Submission Triaged
2/4/2020 2:14:36 PM Submission received from Applicant
2/3/2020 7:19:37 AM Submission request sent to Applicant
2/3/2020 7:19:28 AM Submission Triaged
1/30/2020 5:05:14 PM Submission received from Applicant
1/30/2020 4:25:19 PM Request for Review Comments returned by EPC Health Department
1/30/2020 2:20:47 PM Submission request sent to Applicant
1/30/2020 2:19:37 PM Submission Triaged
1/29/2020 6:46:11 PM Submission received from Applicant
1/29/2020 4:36:19 PM Submission request sent to Applicant
1/29/2020 4:31:59 PM Request for Review Comments returned by PCD Project Manager
1/15/2020 1:23:05 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Gabe Sevigny on behalf of PCD Project Manager
1/15/2020 1:22:16 PM Submission Triaged
1/14/2020 4:56:26 PM Submission received from Applicant
12/31/2019 7:40:45 AM Submission request sent to Applicant
12/12/2019 9:19:02 AM Submission request sent to Applicant
12/12/2019 9:17:50 AM Request for Review Comments returned by PCD Project Manager
12/11/2019 10:10:58 AM Request for Review Comments returned by EPC Parks Department
12/3/2019 5:33:48 PM Request for Review Comments returned by PCD Engineering Division
12/3/2019 3:00:31 PM Request for Review Comments returned by EPC County Attorney's Office
12/3/2019 6:46:16 AM Request for Review Comments returned by EPC Code Enforcement
11/26/2019 11:08:50 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
11/20/2019 12:35:36 PM Request for Review Comments returned by EPC Environmental Services
11/20/2019 12:16:48 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Patrick Palacol on behalf of Peyton Fire Protection District
11/20/2019 12:16:47 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Maint Dir Greg Land on behalf of Peyton 23
11/20/2019 12:16:46 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
11/20/2019 12:16:45 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Jackie Evans on behalf of Kiowa Conservation Dist
11/20/2019 12:16:44 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Joe Valdez on behalf of Black Hills Energy-Aquila
11/20/2019 12:16:43 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by on behalf of EPC Parks Department
11/20/2019 12:16:40 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by on behalf of EPC Health Department
11/20/2019 12:16:39 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Kathy Andrew on behalf of EPC Environmental Services
11/20/2019 12:16:38 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Edi Anderson on behalf of EPC County Attorney's Office
11/20/2019 12:16:38 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Mindy Madden on behalf of EPC Code Enforcement
11/20/2019 12:16:37 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Gabe Sevigny on behalf of PCD Project Manager
11/20/2019 12:16:36 PM Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
11/20/2019 8:56:07 AM Fees paid: 11/20/2019 (Receipt: 1002047)
11/7/2019 9:23:15 AM Payment Request sent: 11/7/2019
11/7/2019 9:23:08 AM File # Assigned: P192
11/7/2019 9:02:28 AM Submission Triaged
11/6/2019 9:12:47 PM Submission received from Applicant
8/14/2019 12:19:16 PM Submission request sent to Applicant
8/14/2019 12:18:23 PM Project Manager Assigned: Gabe Sevigny
8/1/2019 3:49:35 PM Submission request sent to Applicant
8/1/2019 3:49:17 PM Submission request canceled
8/1/2019 3:09:30 PM Submission request sent to Applicant
9/6/2018 10:43:17 AM Submission request sent to Applicant
8/22/2018 3:04:00 PM Submission request sent to Applicant
8/22/2018 1:17:39 PM Project Manager Assigned: Len Kendall
8/22/2018 1:17:39 PM EA Assigned: EA18241
8/22/2018 1:17:39 PM Project Created