4/29/2020 12:39:15 PM
|
Project Closed
|
4/29/2020 12:39:15 PM
|
Project Approved: 4/29/2020
|
3/4/2020 4:14:08 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
2/4/2020 2:44:41 PM
|
Submission Triaged
|
2/4/2020 2:14:36 PM
|
Submission received from Applicant
|
2/3/2020 7:19:37 AM
|
Submission request sent to Applicant
|
2/3/2020 7:19:28 AM
|
Submission Triaged
|
1/30/2020 5:05:14 PM
|
Submission received from Applicant
|
1/30/2020 4:25:19 PM
|
Request for Review Comments returned by EPC Health Department
|
1/30/2020 2:20:47 PM
|
Submission request sent to Applicant
|
1/30/2020 2:19:37 PM
|
Submission Triaged
|
1/29/2020 6:46:11 PM
|
Submission received from Applicant
|
1/29/2020 4:36:19 PM
|
Submission request sent to Applicant
|
1/29/2020 4:31:59 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/15/2020 1:23:05 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Gabe Sevigny on behalf of PCD Project Manager
|
1/15/2020 1:22:16 PM
|
Submission Triaged
|
1/14/2020 4:56:26 PM
|
Submission received from Applicant
|
12/31/2019 7:40:45 AM
|
Submission request sent to Applicant
|
12/12/2019 9:19:02 AM
|
Submission request sent to Applicant
|
12/12/2019 9:17:50 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/11/2019 10:10:58 AM
|
Request for Review Comments returned by EPC Parks Department
|
12/3/2019 5:33:48 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/3/2019 3:00:31 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
12/3/2019 6:46:16 AM
|
Request for Review Comments returned by EPC Code Enforcement
|
11/26/2019 11:08:50 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/20/2019 12:35:36 PM
|
Request for Review Comments returned by EPC Environmental Services
|
11/20/2019 12:16:48 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Patrick Palacol on behalf of Peyton Fire Protection District
|
11/20/2019 12:16:47 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Maint Dir Greg Land on behalf of Peyton 23
|
11/20/2019 12:16:46 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
11/20/2019 12:16:45 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Jackie Evans on behalf of Kiowa Conservation Dist
|
11/20/2019 12:16:44 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
11/20/2019 12:16:43 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by on behalf of EPC Parks Department
|
11/20/2019 12:16:40 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by on behalf of EPC Health Department
|
11/20/2019 12:16:39 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/20/2019 12:16:38 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Edi Anderson on behalf of EPC County Attorney's Office
|
11/20/2019 12:16:38 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Mindy Madden on behalf of EPC Code Enforcement
|
11/20/2019 12:16:37 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Gabe Sevigny on behalf of PCD Project Manager
|
11/20/2019 12:16:36 PM
|
Request for Review Comments email sent for Project Pine View Estates Rezoning for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/20/2019 8:56:07 AM
|
Fees paid: 11/20/2019 (Receipt: 1002047)
|
11/7/2019 9:23:15 AM
|
Payment Request sent: 11/7/2019
|
11/7/2019 9:23:08 AM
|
File # Assigned: P192
|
11/7/2019 9:02:28 AM
|
Submission Triaged
|
11/6/2019 9:12:47 PM
|
Submission received from Applicant
|
8/14/2019 12:19:16 PM
|
Submission request sent to Applicant
|
8/14/2019 12:18:23 PM
|
Project Manager Assigned: Gabe Sevigny
|
8/1/2019 3:49:35 PM
|
Submission request sent to Applicant
|
8/1/2019 3:49:17 PM
|
Submission request canceled
|
8/1/2019 3:09:30 PM
|
Submission request sent to Applicant
|
9/6/2018 10:43:17 AM
|
Submission request sent to Applicant
|
8/22/2018 3:04:00 PM
|
Submission request sent to Applicant
|
8/22/2018 1:17:39 PM
|
Project Manager Assigned: Len Kendall
|
8/22/2018 1:17:39 PM
|
EA Assigned: EA18241
|
8/22/2018 1:17:39 PM
|
Project Created
|