7/16/2019 9:57:13 AM
|
Project Closed
|
7/16/2019 9:57:13 AM
|
Project Approved: 7/16/2019
|
7/15/2019 5:06:07 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/9/2019 4:49:30 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kari Parsons on behalf of PCD Project Manager
|
7/9/2019 4:49:28 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/9/2019 4:48:45 PM
|
Submission Triaged
|
7/9/2019 3:45:10 PM
|
Submission received from Applicant
|
7/1/2019 7:04:01 AM
|
Submission request sent to Applicant
|
6/27/2019 12:39:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/25/2019 4:52:48 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kari Parsons on behalf of PCD Project Manager
|
6/25/2019 4:52:46 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/25/2019 4:47:46 PM
|
Submission Triaged
|
6/25/2019 10:38:24 AM
|
Submission received from Applicant
|
6/24/2019 7:10:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/19/2019 1:16:48 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/19/2019 10:41:51 AM
|
Submission request sent to Applicant
|
6/19/2019 10:39:38 AM
|
Submission request sent to Applicant
|
6/19/2019 10:37:38 AM
|
Submission request sent to Applicant
|
6/12/2019 7:02:12 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kari Parsons on behalf of PCD Project Manager
|
6/12/2019 7:02:10 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/12/2019 7:01:46 AM
|
Submission Triaged
|
6/11/2019 3:00:38 PM
|
Submission received from Applicant
|
5/20/2019 7:48:49 AM
|
Submission request sent to Applicant
|
4/15/2019 4:46:43 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
4/15/2019 4:37:54 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Edi Anderson on behalf of EPC County Attorney's Office
|
4/15/2019 4:22:59 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
4/15/2019 10:15:24 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Edi Anderson on behalf of EPC County Attorney's Office
|
4/11/2019 7:37:49 AM
|
Submission request sent to Applicant
|
4/9/2019 4:50:26 PM
|
Submission request sent to Applicant
|
4/4/2019 9:48:57 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
4/1/2019 7:46:12 AM
|
Request for Review Comments sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
3/20/2019 7:45:05 AM
|
Submission request sent to Applicant
|
3/20/2019 7:40:54 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/19/2019 1:56:04 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/18/2019 12:16:53 PM
|
Submission Triaged
|
3/18/2019 11:05:22 AM
|
Submission received from Applicant
|
3/18/2019 10:38:22 AM
|
Submission request sent to Applicant
|
2/26/2019 8:14:13 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kari Parsons on behalf of PCD Project Manager
|
2/26/2019 8:14:07 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/26/2019 8:07:10 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kari Parsons on behalf of PCD Project Manager
|
2/26/2019 8:07:03 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
2/26/2019 8:05:19 AM
|
Submission Triaged
|
2/26/2019 7:59:32 AM
|
Submission received from Applicant
|
2/14/2019 12:26:06 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
2/14/2019 10:12:10 AM
|
Request for Review Comments sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
1/17/2019 3:31:32 PM
|
Submission request sent to Applicant
|
1/17/2019 3:30:02 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/17/2019 1:50:19 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/10/2019 3:43:51 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/4/2019 9:15:29 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
1/2/2019 7:53:22 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
1/2/2019 7:53:20 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Edi Anderson on behalf of EPC County Attorney's Office
|
1/2/2019 7:53:19 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kari Parsons on behalf of PCD Project Manager
|
1/2/2019 7:53:18 AM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/2/2019 7:50:53 AM
|
Submission Triaged
|
12/27/2018 1:43:42 PM
|
Request for Review Comments returned by US Postal Service
|
12/20/2018 5:23:37 PM
|
Submission received from Applicant
|
11/29/2018 8:36:10 PM
|
Request for Review Comments returned by Cherokee Metro Dist
|
11/25/2018 5:55:42 PM
|
Request for Review Comments returned by EPC Health Department
|
11/21/2018 1:11:57 PM
|
Submission request sent to Applicant
|
11/21/2018 1:09:20 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/21/2018 12:04:43 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/19/2018 3:26:42 PM
|
Request for Review Comments returned by Parks Advisory Board
|
11/19/2018 11:52:40 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
11/19/2018 11:14:41 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
11/14/2018 5:59:53 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/13/2018 11:12:27 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
11/8/2018 4:20:28 PM
|
Request for Review Comments returned by EPC Environmental Services
|
11/8/2018 11:04:39 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/7/2018 3:25:38 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/6/2018 2:24:13 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
11/6/2018 2:17:19 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
11/5/2018 1:41:24 PM
|
Request for Review Comments returned by Mountain Metro Transit (City of COS)
|
11/5/2018 9:59:58 AM
|
Request for Review Comments returned by EPC Parks Department
|
11/1/2018 1:54:07 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
10/30/2018 12:31:34 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Josh Braunschweig on behalf of Mountain View Electric Association, Inc.
|
10/30/2018 12:31:31 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Christoph Zurcher on behalf of Mountain Metro Transit (City of COS)
|
10/30/2018 12:31:29 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
10/30/2018 12:31:28 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Melissa Andrews on behalf of Falcon 49
|
10/30/2018 12:31:27 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Pamela Davidson on behalf of El Paso County Conservation Dist
|
10/30/2018 12:31:26 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Dave Munger on behalf of Council of Neighborhood Organizations (CONO)
|
10/30/2018 12:31:25 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Peter Susemilh on behalf of Constitution Heights Metro
|
10/30/2018 12:31:24 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/30/2018 12:31:23 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Terry Johns on behalf of Colorado Springs SD 11
|
10/30/2018 12:31:22 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Carl Schueler on behalf of Colorado Springs Planning & Community Development
|
10/30/2018 12:31:21 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
|
10/30/2018 12:31:20 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Water & Wastewater Collections Manager Jonathon Smith on behalf of Cherokee Metro Dist
|
10/30/2018 12:31:19 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
10/30/2018 12:31:18 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
10/30/2018 12:31:17 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elaine Kelly on behalf of US Postal Service
|
10/30/2018 12:31:16 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
10/30/2018 12:31:15 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Ross Williams on behalf of Parks Advisory Board
|
10/30/2018 12:31:14 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
10/30/2018 12:31:13 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by on behalf of EPC Parks Department
|
10/30/2018 12:31:10 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by on behalf of EPC Health Department
|
10/30/2018 12:31:09 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kathy Andrew on behalf of EPC Environmental Services
|
10/30/2018 12:31:08 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Edi Anderson on behalf of EPC County Attorney's Office
|
10/30/2018 12:31:07 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Kari Parsons on behalf of PCD Project Manager
|
10/30/2018 12:31:06 PM
|
Request for Review Comments email sent for Project Hannah Ridge at Feathergrass Filing No. 7 for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/30/2018 12:27:25 PM
|
Fees paid: 10/30/2018 (Receipt: 1001056)
|
10/29/2018 7:14:24 AM
|
Payment Request sent: 10/29/2018
|
10/29/2018 7:14:16 AM
|
File # Assigned: SF1840
|
10/26/2018 2:27:45 PM
|
Submission Triaged
|
10/26/2018 12:56:15 PM
|
Submission received from Applicant
|
10/26/2018 7:50:40 AM
|
Submission request sent to Applicant
|
10/26/2018 7:50:35 AM
|
Submission Triaged
|
10/24/2018 1:28:54 PM
|
Submission received from Applicant
|
7/10/2018 8:18:58 AM
|
Submission request sent to Applicant
|
7/10/2018 8:16:41 AM
|
Project Manager Assigned: Kari Parsons
|
7/10/2018 8:16:41 AM
|
EA Assigned: 18160
|
7/10/2018 8:16:41 AM
|
Project Created
|