12/6/2018 12:00:00 AM
|
Project Closed
|
12/5/2018 12:11:57 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/5/2018 7:43:07 AM
|
Project Approved: 12/5/2018
|
11/29/2018 7:05:15 AM
|
Submission Triaged
|
11/28/2018 4:19:05 PM
|
Submission received from Applicant
|
11/28/2018 10:26:05 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/28/2018 10:21:46 AM
|
Submission request sent to Applicant
|
11/26/2018 5:24:50 PM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Kari Parsons on behalf of PCD Project Manager
|
11/26/2018 5:24:43 PM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/26/2018 5:24:00 PM
|
Submission Triaged
|
11/26/2018 4:44:23 PM
|
Submission received from Applicant
|
11/26/2018 10:34:29 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/26/2018 9:47:05 AM
|
Submission request sent to Applicant
|
11/26/2018 9:46:34 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/26/2018 9:13:38 AM
|
Submission request sent to Applicant
|
11/19/2018 8:27:45 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Kari Parsons on behalf of PCD Project Manager
|
11/19/2018 8:27:43 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/15/2018 7:07:29 AM
|
Submission Triaged
|
11/14/2018 5:46:53 PM
|
Submission received from Applicant
|
11/14/2018 4:38:03 PM
|
Submission request sent to Applicant
|
11/9/2018 10:15:22 AM
|
Request for Review Comments returned by EPC Parks Department
|
11/5/2018 9:23:30 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by on behalf of EPC Parks Department
|
11/5/2018 9:23:29 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Kari Parsons on behalf of PCD Project Manager
|
11/5/2018 9:23:26 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/5/2018 9:22:34 AM
|
Submission Triaged
|
11/1/2018 1:03:01 PM
|
Submission received from Applicant
|
10/16/2018 12:22:06 PM
|
Submission request sent to Applicant
|
10/16/2018 11:56:46 AM
|
Request for Review Comments returned by PCD Engineering Division
|
10/16/2018 11:53:35 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/19/2018 11:15:47 AM
|
Request for Review Comments returned by Parks Advisory Board
|
9/19/2018 10:49:41 AM
|
Request for Review Comments returned by EPC Health Department
|
9/6/2018 4:29:57 PM
|
Submission request sent to Applicant
|
9/6/2018 4:29:00 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/6/2018 2:36:29 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/5/2018 5:38:52 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
9/5/2018 1:56:04 PM
|
Request for Review Comments returned by EPC Parks Department
|
9/4/2018 2:29:05 PM
|
Request for Review Comments returned by EPC Environmental Services
|
9/4/2018 1:25:03 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
8/30/2018 11:38:13 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
8/30/2018 9:30:13 AM
|
Request for Review Comments returned by Black Forest Land Use Committee
|
8/27/2018 11:54:04 AM
|
Request for Review Comments returned by Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
8/21/2018 9:20:01 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
8/20/2018 11:21:54 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
8/20/2018 9:36:52 AM
|
Request for Review Comments returned by Colorado State Forest Service
|
8/17/2018 10:08:45 AM
|
Request for Review Comments returned by Woodmen Hills Metro
|
8/14/2018 4:17:34 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
8/13/2018 1:14:15 PM
|
Request for Review Comments returned by EPC County Attorney's Office
|
8/13/2018 10:39:06 AM
|
Request for Review Comments returned by Mountain Metro Transit (City of COS)
|
8/13/2018 9:36:43 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Jerry Jacobson on behalf of Woodmen Hills Metro
|
8/13/2018 9:36:42 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Tom Vierzbea on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
8/13/2018 9:36:41 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Josh Braunschweig on behalf of Mountain View Electric Association, Inc.
|
8/13/2018 9:36:40 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Christoph Zurcher on behalf of Mountain Metro Transit (City of COS)
|
8/13/2018 9:36:40 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
|
8/13/2018 9:36:39 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Melissa Andrews on behalf of Falcon 49
|
8/13/2018 9:36:38 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Dave Munger on behalf of Council of Neighborhood Organizations (CONO)
|
8/13/2018 9:36:36 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Carl Schueler on behalf of Colorado Springs Planning & Community Development
|
8/13/2018 9:36:35 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
8/13/2018 9:36:34 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Cheryl Pixley on behalf of Black Forest Trails Association
|
8/13/2018 9:36:33 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Terry Stokka on behalf of Black Forest Land Use Committee
|
8/13/2018 9:36:32 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Bryan Jack on behalf of Black Forest Fire Protection District
|
8/13/2018 9:36:32 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Dr. Mark Hatchell on behalf of Academy SD 20 Building Fund
|
8/13/2018 9:36:30 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
8/13/2018 9:36:30 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
8/13/2018 9:36:29 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
8/13/2018 9:36:28 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Christopher Grosso on behalf of US Army Corps of Engineers-Pueblo
|
8/13/2018 9:36:27 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Larry Long on behalf of Colorado State Forest Service
|
8/13/2018 9:36:26 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Dan Prenzlow on behalf of Colorado Parks and Wildlife
|
8/13/2018 9:36:25 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
8/13/2018 9:36:24 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Ross Williams on behalf of Parks Advisory Board
|
8/13/2018 9:36:23 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
8/13/2018 9:36:22 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by on behalf of EPC Parks Department
|
8/13/2018 9:36:19 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by on behalf of EPC Health Department
|
8/13/2018 9:36:19 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Kathy Andrew on behalf of EPC Environmental Services
|
8/13/2018 9:36:18 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Edi Anderson on behalf of EPC County Attorney's Office
|
8/13/2018 9:36:17 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Kari Parsons on behalf of PCD Project Manager
|
8/13/2018 9:36:16 AM
|
Request for Review Comments email sent for Project Sterling Ranch Sketch Plan Amendment for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/1/2018 4:16:47 PM
|
Fees paid: 8/1/2018 (Receipt: 1000855)
|
8/1/2018 3:38:40 PM
|
Payment Request sent: 8/1/2018
|
8/1/2018 3:38:14 PM
|
File # Assigned: SKP183
|
8/1/2018 11:19:36 AM
|
Submission request canceled
|
7/31/2018 10:01:04 AM
|
Submission request sent to Applicant
|
7/31/2018 10:00:59 AM
|
Submission Triaged
|
7/30/2018 4:16:32 PM
|
Submission received from Applicant
|
7/26/2018 10:04:52 AM
|
Submission request sent to Applicant
|
6/4/2018 11:10:15 AM
|
Submission request sent to Applicant
|
5/7/2018 11:13:03 AM
|
Submission request sent to Applicant
|
5/7/2018 11:02:53 AM
|
Project Manager Assigned: Kari Parsons
|
5/7/2018 11:02:52 AM
|
EA Assigned: EA17-87
|
5/7/2018 11:02:52 AM
|
Project Created
|