4/4/2018 12:00:00 AM
|
Project Closed
|
4/3/2018 6:57:44 AM
|
Project Approved: 3/27/2018
|
3/23/2018 3:35:47 PM
|
Request for Review Comments sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Edi Anderson on behalf of EPC County Attorney's Office
|
3/23/2018 1:24:50 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
3/7/2018 7:17:03 AM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Melissa Peterson on behalf of Colorado Division of Water Resources
|
3/7/2018 7:13:19 AM
|
Submission Triaged
|
3/7/2018 7:12:38 AM
|
Submission received from Applicant
|
3/7/2018 7:09:23 AM
|
Submission request sent to Applicant
|
2/28/2018 10:37:28 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
2/26/2018 4:27:26 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
2/13/2018 4:15:18 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
2/13/2018 4:14:18 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
2/5/2018 3:25:18 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/5/2018 3:19:50 PM
|
Request for Review Comments returned by PCD Project Manager
|
2/5/2018 2:05:59 PM
|
Request for Review Comments email resent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/5/2018 1:02:53 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/17/2018 2:07:11 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Raimere Fitzpatrick on behalf of PCD Project Manager
|
1/17/2018 2:07:09 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
1/17/2018 2:06:40 PM
|
Submission Triaged
|
1/17/2018 1:42:46 PM
|
Submission received from Applicant
|
1/4/2018 9:47:51 AM
|
Request for Review Comments returned by Lewis Palmer 38
|
12/5/2017 5:37:48 PM
|
Submission request sent to Applicant
|
12/5/2017 5:28:06 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/27/2017 4:37:14 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/22/2017 4:31:19 PM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
11/7/2017 7:44:40 AM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
11/7/2017 7:44:40 AM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Raimere Fitzpatrick on behalf of PCD Project Manager
|
11/7/2017 7:44:39 AM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
11/6/2017 12:28:09 PM
|
Submission Triaged
|
11/3/2017 7:37:53 AM
|
Submission received from Applicant
|
10/31/2017 4:20:07 PM
|
Submission request sent to Applicant
|
10/31/2017 4:19:10 PM
|
Submission request canceled
|
10/31/2017 12:46:26 PM
|
Submission request sent to Applicant
|
10/11/2017 5:11:19 PM
|
Request for Review Comments returned by Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
6/29/2017 5:30:38 PM
|
Submission request sent to Applicant
|
6/29/2017 5:30:22 PM
|
Submission request canceled
|
6/29/2017 3:23:41 PM
|
Submission request sent to Applicant
|
6/29/2017 2:11:09 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/29/2017 10:47:17 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/29/2017 9:33:02 AM
|
Submission request canceled
|
6/29/2017 9:14:46 AM
|
Submission request sent to Applicant
|
6/27/2017 4:42:58 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/22/2017 11:59:13 AM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
6/22/2017 8:56:04 AM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
6/21/2017 9:59:51 PM
|
Request for Review Comments returned by EPC Health Department
|
6/20/2017 6:04:32 PM
|
Request for Review Comments returned by Colorado Geological Survey
|
6/19/2017 8:39:41 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/16/2017 9:22:27 AM
|
Request for Review Comments returned by EPC Parks Department
|
6/16/2017 8:18:54 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
6/15/2017 10:43:51 AM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
6/8/2017 12:03:50 PM
|
Request for Review Comments returned by EPC Environmental Services
|
6/6/2017 1:29:13 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/5/2017 1:54:36 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Kathy Andrew on behalf of EPC Environmental Services
|
6/5/2017 1:54:35 PM
|
Request for Review Comments sent to EPC Environmental Services
|
6/5/2017 1:42:18 PM
|
Request for Review Comments returned by EPC Environmental Services
|
5/31/2017 3:11:21 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Tom Vierzbea on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)
|
5/30/2017 1:35:12 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
5/30/2017 1:35:11 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
5/30/2017 1:35:10 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Jerry Hannigan on behalf of Tri Lakes Land Use Committee
|
5/30/2017 1:35:09 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
|
5/30/2017 1:35:08 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Cheryl Wangeman on behalf of Lewis Palmer 38
|
5/30/2017 1:35:07 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Sebastian Schwender on behalf of Black Hills Energy-Aquila
|
5/30/2017 1:35:06 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
5/30/2017 1:35:05 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by DeBerry Drew on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
5/30/2017 1:35:04 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Dan Prenzlow on behalf of Colorado Parks and Wildlife
|
5/30/2017 1:35:04 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Jill M. Carlson on behalf of Colorado Geological Survey
|
5/30/2017 1:35:03 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Melissa Peterson on behalf of Colorado Division of Water Resources
|
5/30/2017 1:35:01 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Dan Ausec on behalf of EPC Sheriff's Department
|
5/30/2017 1:35:01 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
5/30/2017 1:35:00 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by on behalf of EPC Parks Department
|
5/30/2017 1:34:59 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by on behalf of EPC Health Department
|
5/30/2017 1:34:58 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Kathy Andrew on behalf of EPC Environmental Services
|
5/30/2017 1:34:57 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Edi Anderson on behalf of EPC County Attorney's Office
|
5/30/2017 1:34:56 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Raimere Fitzpatrick on behalf of PCD Project Manager
|
5/30/2017 1:34:55 PM
|
Request for Review Comments email sent for Project The Beach at Woodmoor PUD/Preliminary Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/30/2017 1:31:19 PM
|
Fees paid: 5/30/2017 (Receipt: 1000098)
|
5/30/2017 7:52:48 AM
|
File # Assigned: PUDSP-17-003
|
5/26/2017 12:49:21 PM
|
Submission Triaged
|
5/26/2017 12:28:01 PM
|
Submission received from Applicant
|
5/9/2017 4:31:09 PM
|
Submission request sent to Applicant
|
5/8/2017 2:36:54 PM
|
Submission request sent to Applicant
|
5/8/2017 10:09:16 AM
|
Submission request sent to Applicant
|
5/8/2017 8:40:27 AM
|
Submission request sent to Applicant
|
5/8/2017 8:37:37 AM
|
Submission request sent to Applicant
|
5/8/2017 8:04:23 AM
|
Submission request sent to Applicant
|
5/2/2017 4:51:33 PM
|
Project Manager Assigned: Raimere Fitzpatrick
|
5/2/2017 4:51:33 PM
|
EA Assigned: EA-16-106
|
5/2/2017 4:51:33 PM
|
Project Created
|