Colorado Springs Airport Advisory Commission
4/27/2023 8:36:48 AM |
This is outside the Commercial Airport Overlay District and jurisdiction for Colorado Springs Airport and the Airport Advisory Commission to review and comment. | 4/27/2023 8:36:48 AM | |
View |
PCD Project Manager
4/6/2023 9:47:56 AM |
minor comment letter of intent | 4/6/2023 9:47:56 AM |
PCD Engineering Division
3/28/2023 11:08:11 AM |
Previous review comments have been resolved. Engineering has no further comments relating to drainage or transportation at this time. Any approved documents will be uploaded by the project manager. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
3/28/2023 11:08:11 AM | |
View |
EPC Health Department
1/20/2023 12:06:23 PM |
1/20/2023 12:06:23 PM | |
Fountain Ft. Carson SD 8
1/19/2023 2:44:04 PM |
no comment | 1/19/2023 2:44:04 PM | |
PCD Engineering Division
1/9/2023 10:10:29 AM |
Review 2: Please upload a revised Letter of Intent with the comments from revision 1 addressed. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
1/9/2023 10:10:29 AM | |
View |
PCD Project Manager
12/28/2022 2:53:12 PM |
Site plan comments | 12/28/2022 2:53:12 PM |
View |
PCD Project Manager
12/28/2022 2:52:55 PM |
Letter of intent comments | 12/28/2022 2:52:55 PM |
EPC Stormwater Review
12/13/2022 9:11:48 AM |
Review 1: The proposed area of disturbance is less than 1 acre, therefore an ESQCP is not required. Stormwater has no comments. Planner: no re-review necessary Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
12/13/2022 9:11:48 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/12/2022 2:41:08 PM |
I have no review comments on this project Al | 12/12/2022 2:41:08 PM | |
View |
PCD Project Manager
12/12/2022 12:00:49 PM |
SDP | 12/12/2022 12:00:49 PM |
View |
PCD Project Manager
12/12/2022 12:00:33 PM |
letter of intent | 12/12/2022 12:00:33 PM |
PCD Engineering Division
12/6/2022 11:05:31 AM |
Review 1 comments will be uploaded by the project manager. Review comments on the following documents: -Letter of Intent -Site Plan There is no Driveway Access Waiver on file for the tower's driveway. A Driveway Access Waiver is required for access points onto a private road within unincorporated El Paso County. Please apply for a driveway access waiver through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
12/6/2022 11:05:31 AM | |
Pikes Peak Regional Building Department
12/5/2022 8:35:02 AM |
1. The existing tower address is not 2945 Little Turkey Creek Road. This is the address to the property, a Cell Tower always receives a separate address from the property prior to permit with Regional Building. Permit history shows the tower at 2424 Little Turkey Creek Road. 2424 is also the address for Verizon carrier. Each carrier is required to have a separate address with the new tower going up. 2. It will be required to pull a wrecking permit to remove the old tower at 2424 Little Turkey Creek Road, per RBD. There will be a new address assigned when the location of the new tower is determined. The same address will not be used to keep the old structure permit history separate from the new tower structure. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
12/5/2022 8:35:02 AM |