Mountain View Electric Association, Inc.
2/7/2023 12:28:35 PM |
Mountain View Electric Association has no objection to the rezone plan | 2/7/2023 12:28:35 PM | |
View |
Upper Black Squirrel Creek GWMD
1/31/2023 2:56:27 PM |
1/31/2023 2:56:27 PM | |
PCD Project Manager
1/26/2023 12:48:54 PM |
please upload a final plat with minor admin comments addressed. | 1/26/2023 12:48:54 PM | |
PCD Project Manager
1/26/2023 12:40:04 PM |
Comments have been met. Moving forward to the hearing process at this point. | 1/26/2023 12:40:04 PM | |
View |
PCD Engineering Division
1/11/2023 10:02:49 AM |
Rezone Map Extract only with ADMIN errors. | 1/11/2023 10:02:49 AM |
PCD Engineering Division
1/11/2023 10:01:38 AM |
Engineer Review Ver.2 Engineer comments have been addressed on the Letter of Intent and Rezone Map. Please note three engineer identified administrative errors on the rezone map to be corrected. Please see rezone map extract. Planner may have additional comments on the complete Rezone Map. Please correct rezone map for final submission and BoCC approval. No further engineer comments. Thank you. Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
1/11/2023 10:01:38 AM | |
View |
PCD Project Manager
1/4/2023 3:55:39 PM |
mineral rights comment | 1/4/2023 3:55:39 PM |
View |
PCD Project Manager
1/4/2023 3:55:17 PM |
Map drawing eng/planning comments | 1/4/2023 3:55:17 PM |
View |
PCD Project Manager
1/4/2023 3:54:54 PM |
Letter of intent eng/planning comments | 1/4/2023 3:54:54 PM |
PCD Engineering Division
1/3/2023 11:31:00 AM |
Engineering Review Ver.1 Please see redline comments on the following documents. -Letter of Intent (To be uploaded by PM) -Rezone Map Drawing (To be uploaded by PM) Thank you Edward B. Schoenheit Engineer I Reviewer El Paso County Planning & Community Development EdwardSchoenheit@elpasoco.com 719-520-6813 (O) 719-502-9659 (C) |
1/3/2023 11:31:00 AM | |
Pikes Peak Regional Building Department
1/3/2023 9:08:57 AM |
Enumerations has no comments regarding the rezone aspect of this project. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
1/3/2023 9:08:57 AM | |
View |
El Paso County Conservation Dist
12/29/2022 3:27:47 PM |
Brief comments attached as a .pdf. | 12/29/2022 3:27:47 PM |
Ellicott Fire Protection District
12/29/2022 8:49:06 AM |
There is a $100.00 Review fee payable to the Ellicott Fire Department at: 75 N Ellicott Hwy, Calhan, CO 80808. Please indicate the name of the project on the check. The site is located within 1 mile of a pressurized hydrant water supply. All new access routes shall meet the requirements of the 2015 International Fire Code Appendix D. The fire department has no objections to the rezoning as described. Mark Stanwood Fire Marshal Ellicott Fire Department 719-360-0578 |
12/29/2022 8:49:06 AM | |
View |
EPC Parks Department
12/12/2022 1:44:23 PM |
See final comments from County Parks attached. Thanks, Greg |
12/12/2022 1:44:23 PM |
View |
EPC Environmental Services
12/12/2022 1:37:25 PM |
12/12/2022 1:37:25 PM | |
Cherokee Metro Dist
12/12/2022 10:19:12 AM |
CMD has no comments | 12/12/2022 10:19:12 AM |