View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
3/6/2023 10:59:03 AM |
Project is ready for the BOA hearing for April 26th | 3/6/2023 10:59:03 AM | |
Black Forest Fire Protection District
3/2/2023 4:16:31 PM |
As a commercial project any fire protection review shall be completed by the Colorado Springs Fire Department per an MOU between CSFD and BFFR. | 3/2/2023 4:16:31 PM | |
View |
PCD Project Manager
2/24/2023 8:57:56 AM |
LOI comments | 2/24/2023 8:57:56 AM |
View |
PCD Project Manager
2/24/2023 8:57:33 AM |
Site plan comments | 2/24/2023 8:57:33 AM |
PCD Engineering Division
2/22/2023 5:28:50 PM |
Engineer Review Ver1. No major engineering comments with the reduced setback. Drainage and grading will need to be addressed during SDP phase submission for transfer site and the new ramp entrance areas where the existing storm inlet and swale area is located. Road Impact fees will be addressed at SDP phase. Thank you. Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
2/22/2023 5:28:50 PM | |
EPC Stormwater Review
2/22/2023 3:30:45 PM |
EPC DPW Stormwater has no comments. Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
2/22/2023 3:30:45 PM | |
Pikes Peak Regional Building Department
2/16/2023 11:12:26 AM |
Enumerations has no comment or objection to this setback variance request. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
2/16/2023 11:12:26 AM | |
Academy SD 20 Building Fund
2/13/2023 7:53:06 AM |
Academy District 20 is in receipt of File#BOA232 for approval of the Barbarick Transfer Station-BOA setback request. The District has no comment regarding this request. If you need additional information, please contact me. Don Smith Planning Consultant |
2/13/2023 7:53:06 AM | |
Mountain View Electric Association, Inc.
1/30/2023 1:43:51 PM |
Mountain View Electric Association has no objection with the current plan | 1/30/2023 1:43:51 PM | |
View |
EPC Environmental Services
1/27/2023 1:16:54 PM |
1/27/2023 1:16:54 PM |