View: Project Documents
Agency | Comment | ||
---|---|---|---|
Pikes Peak Regional Building Department
1/18/2023 1:53:25 PM |
Enumerations has no comments regarding this project. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
1/18/2023 1:53:25 PM | |
EPC Stormwater Review
1/18/2023 9:26:21 AM |
Review 1: EPC Stormwater does not have any comments on the Approval of Location Application. Please note, an ESQCP (and all associated documents) will need to be provided for review and approval with any future Construction Applications. Reviewed by: Christina Prete, P.E. Stormwater Engineer III ChristinaPrete@elpasoco.com |
1/18/2023 9:26:21 AM | |
County Attorney - Development Review
1/12/2023 4:21:25 PM |
No comments from County Attorney - Development Review at this time. | 1/12/2023 4:21:25 PM | |
View |
Widefield SD 3
1/12/2023 9:16:40 AM |
1/12/2023 9:16:40 AM | |
PCD Engineering Division
1/12/2023 8:28:43 AM |
Engineering defers site specific review and comments to the subsequent application. The following documents may be required for different sections of the project: - Grading and Erosion Control Plan (inform the planner if the GEC plan is included with the Construction Drawings) - GEC Checklist - Financial Assurance Form - Stormwater Management Plan (SWMP) - SWMP Checklist - PBMP Applicability Form - Financial Assurance Estimate (FAE) - Erosion and Stormwater Quality Control Permit (ESQCP) A Work-in-the-ROW permit will be required for work in El Paso County Roads. Construction impacts on County transportation facilities will be addressed in these permits. Reviewed By: Lupe Packman Review Engineer lupepackman@elpasoco.com |
1/12/2023 8:28:43 AM | |
Lewis Palmer 38
1/11/2023 3:05:03 PM |
Lewis-Palmer School District 38 has no comment regarding this request for approval of the CSU fiber optic broadband installation. (2023.01.11) | 1/11/2023 3:05:03 PM | |
View |
EPC Environmental Services
1/11/2023 12:19:47 PM |
1/11/2023 12:19:47 PM | |
Black Forest Fire Protection District
1/10/2023 7:29:52 AM |
Black Forest Fire has no comments at this time. | 1/10/2023 7:29:52 AM | |
Academy SD 20 Building Fund
1/10/2023 7:26:25 AM |
Academy District 20 is in receipt of File# U224 for approval of the CSU Approval of Location-Broadband. It is noted that the installation of fiber will be in existing right-of ways and easements. The District requests that the District be notified in advance of any construction on or near District property so that the necessary precautions may be taken by District Security personnel to protect students, parents and staff. If you need additional information, please contact me. Don Smith Planning Consultant |
1/10/2023 7:26:25 AM | |
View |
EPC Parks Department
1/9/2023 7:56:42 AM |
See Parks comments attached. | 1/9/2023 7:56:42 AM |
Mountain View Electric Association, Inc.
1/5/2023 3:15:42 PM |
This project is not within MVEA's territory | 1/5/2023 3:15:42 PM | |
Falcon Fire Protection District
1/5/2023 2:33:01 PM |
Falcon Fire has no concerns or further comments on this project. | 1/5/2023 2:33:01 PM | |
911 Authority - El Paso/Teller County
1/5/2023 7:15:19 AM |
No action for E911 on this submittal. Thank you. Justin |
1/5/2023 7:15:19 AM | |
Meadow Lake Airport Association
1/4/2023 3:16:11 PM |
The docs attached are not very definitive, but this project appears to be well to the west of the Meadow Lake AIA and all underground. It should therefore have no effect on Meadow Lake operations. If there are above ground level facilities within the 5-mile radius of the airport, we will need to see the FAA 7460-1 for review. | 1/4/2023 3:16:11 PM |