Project Review Comments

Back to List


Project Name
WWSD Booster 2 Pump Station Replacement
Description
Location
Parcels
5519109008 5519109008
Applicant
JDS-Hydro Consultants, Inc.
Gina Mangino ( gmangino@jdshydro.com )
(719) 227-0072 x107
Gina Mangino ( gmangino@jdshydro.com )
(719) 227-0072 x107
File Number
PPR2169
Project Manager
Ryan Howser
Status
Closed
Created
10/18/2021 10:36:44 AM

View: Project Documents



Review Comments (32)

Link Agency Comment
PCD Project Manager
6/1/2022 4:25:11 PM
No comments. Approved documents will be uploaded when they are signed by the ECM administrator. 6/1/2022 4:25:11 PM
PCD Engineering Division
5/26/2022 1:58:03 PM
Comments have been resolved. Approved documents will be uploaded.

Reviewed By:
Lupe Packman
Review Engineer
Lupepackman@elpasoco.com
5/26/2022 1:58:03 PM
EPC Stormwater Review
5/26/2022 2:14:00 PM
Review 3: EPC Stormwater comments have been resolved on the following documents:
- Drainage Report
- GEC Plan
- GEC Checklist

EPC Stormwater has no further comments at this time. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
5/26/2022 2:14:00 PM
View PCD Project Manager
3/10/2022 8:32:11 AM
EPC Stormwater comments - GEC 3/10/2022 8:32:11 AM
View PCD Project Manager
3/10/2022 8:31:44 AM
PCD Engineering comments - FAE 3/10/2022 8:31:44 AM
View PCD Project Manager
3/10/2022 8:31:19 AM
PCD Engineering & EPC Stormwater comments - Drainage report 3/10/2022 8:31:19 AM
PCD Engineering Division
3/8/2022 9:45:09 AM
Review 2 comments will be submitted by the project manager. Please address comments on the following documents:

-Drainage Report
-Financial Assurance Estimate

Please sign and stamp all engineering documents since documents will be ready for signatures if all comments are resolved in the next submittal. Make sure to sign across PE seals per DORA regulations.

Note to the planner: please set next review cycle to 5 days.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
3/8/2022 9:45:09 AM
View EPC Stormwater Review
3/7/2022 7:25:44 PM
GEC Checklist 3/7/2022 7:25:44 PM
EPC Stormwater Review
3/7/2022 7:25:13 PM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report....(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist

EPC Stormwater comments have been resolved on the following documents:
- ESQCP
- FAE
- PBMP Applicability Form
- SWMP
- SWMP Checklist

Please sign and resubmit the following documents:
- GEC Checklist
- SWMP Checklist

Ryan --- please open up a slot on EDARP for the applicant to upload the Soils Report referenced on pg 5 of the SWMP.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
3/7/2022 7:25:13 PM
View Fountain
1/25/2022 1:20:16 PM
See attached. 1/25/2022 1:20:16 PM
View EPC Health Department
1/15/2022 12:31:03 PM
1/15/2022 12:31:03 PM
View PCD Project Manager
12/29/2021 12:48:43 PM
Site Development Plan_V1 redlines 12/29/2021 12:48:43 PM
View PCD Project Manager
12/29/2021 12:44:47 PM
Drainage Report_V1 redlines 12/29/2021 12:44:47 PM
View PCD Project Manager
12/29/2021 12:44:03 PM
ESQCP_V1 redlines 12/29/2021 12:44:03 PM
View PCD Project Manager
12/29/2021 12:43:34 PM
Financial Assurance Forms_V1 redlines 12/29/2021 12:43:34 PM
View PCD Project Manager
12/29/2021 12:43:04 PM
Grading & Erosion Control Plan_V1 redlines 12/29/2021 12:43:04 PM
View PCD Project Manager
12/29/2021 12:42:30 PM
Letter of Intent_V1 redlines 12/29/2021 12:42:30 PM
View PCD Project Manager
12/29/2021 12:41:50 PM
Vicinity Map_V1 redlines 12/29/2021 12:41:50 PM
PCD Engineering Division
12/29/2021 10:15:20 AM
Review 1 comments will be uploaded by the project manager. Please address comments on the following documents:

-Drainage report
-Financial assurance form
-Site development plan
-Grading and erosion control plan
-Letter of intent

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
12/29/2021 10:15:20 AM
View EPC Stormwater Review
12/21/2021 6:19:51 PM
SWMP Checklist 12/21/2021 6:19:51 PM
View EPC Stormwater Review
12/21/2021 6:19:32 PM
SWMP 12/21/2021 6:19:32 PM
View EPC Stormwater Review
12/21/2021 6:18:57 PM
PBMP Applicability Form 12/21/2021 6:18:57 PM
View EPC Stormwater Review
12/21/2021 6:16:58 PM
GEC Checklist 12/21/2021 6:16:58 PM
EPC Stormwater Review
12/21/2021 6:16:00 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...(to be uploaded by PM with PCD comments)
- ESQCP...................(to be uploaded by PM with PCD comments)
- FAE.......................(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- PBMP Applicability Form
- SWMP
- SWMP Checklist

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
12/21/2021 6:16:00 PM
Pikes Peak Regional Building Department
12/21/2021 10:06:50 AM
1. A wrecking permit will be required to remove the existing Booster Pump Station with Regional Building Department. That address is 7010 Metropolitan Street.
2. New address to be assigned to the new Booster Pump Station. Please use the address of 7002 Metropolitan Street. Use this address when submitting plans to RBD.

Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
12/21/2021 10:06:50 AM
View Colorado Springs Airport Advisory Commission
12/15/2021 3:37:50 PM
The attached summary with comments was presented at the Airport Advisory Commission meeting on 12/15/2021 with no objections. 12/15/2021 3:37:50 PM
View Widefield SD 3
12/14/2021 2:34:52 PM
12/14/2021 2:34:52 PM
Mountain View Electric Association, Inc.
12/13/2021 2:18:37 PM
This project is out of Mountain View Electric Association territory - the letter of intent states the City of Fountain will provide electric service. 12/13/2021 2:18:37 PM
911 Authority - El Paso/Teller County
12/6/2021 8:36:20 AM
No new street names requested.
No action for E911.
Thank you.
Justin
12/6/2021 8:36:20 AM
County Attorney - Development Review
12/3/2021 9:01:42 PM
No comments from County Attorney - Development Review at this time. 12/3/2021 9:01:42 PM
View El Paso County Conservation Dist
12/1/2021 8:12:25 AM
12/1/2021 8:12:25 AM
View El Paso County Conservation Dist
12/1/2021 8:11:55 AM
12/1/2021 8:11:55 AM