Project Name
6145 Vessey Rd., Garage shop addition
Description
Needs BOA for the following: -setbacks -lot size -variance from width (at front setback line)
Location
Parcels
5206000051 5206000051
Applicant
Vincent Pirrone
Vincent Pirrone ( my_cousinvinny@yahoo.com )
(775) 742-0475
Vincent Pirrone ( my_cousinvinny@yahoo.com )
(775) 742-0475
EA Number
EA21196
File Number
BOA2215
Project Manager
Ashlyn Mathy
Status
Closed
Created
10/12/2021 11:00:26 AM

View: Project Documents



Review Comments (13)

Link Agency Comment
View PCD Project Manager
2/6/2023 11:04:23 AM
site plan proposed minor comments, once these are revised we can pick a date to go to the board of adjustment! 2/6/2023 11:04:23 AM
PCD Engineering Division
1/23/2023 3:05:02 PM
Review 2:

- Comments on the Letter of Intent from Review 1 have been resolved.
- Comments on the Site Plan from Review 1 are unresolved:
- The parcel does not meet open-ditch secondary access requirements. The parcel should be 2.5 acres or greater
and have a minimum lot frontage of 250 feet.
- The driveway access spacing is not met per ECM 2.4.1B

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
1/23/2023 3:05:02 PM
View PCD Project Manager
1/5/2023 8:41:48 AM
vicinity map 1/5/2023 8:41:48 AM
View PCD Project Manager
1/5/2023 8:41:32 AM
neighbor notifications 1/5/2023 8:41:32 AM
View PCD Project Manager
1/5/2023 8:41:15 AM
site plan 1/5/2023 8:41:15 AM
View PCD Project Manager
1/5/2023 8:41:02 AM
Letter of intent 1/5/2023 8:41:02 AM
PCD Engineering Division
11/14/2022 9:47:26 AM
Review 1 comments will be uploaded by the project manager. Review comments on the following documents:

- Letter of Intent
- Site Plan (Proposed Use)

There is no Driveway Access Permit on file for main residential driveway. A Driveway Access Permit is required for all access points onto a county or private road within unincorporated El Paso County. Please apply for a driveway access permit through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online.

Note:
- The fee for the main residential driveway access is waived due to the home being built prior to 1973.
- The parcel does not meet standards for a secondary driveway access.

Reviewed by:
Carlos Hernandez
Review Engineer
carloshernandez@elpasoco.com
11/14/2022 9:47:26 AM
View PCD Project Manager
11/10/2022 11:41:32 AM
Recommend including north-facing arrow to meet the intent of the checklist. All other data present. 11/10/2022 11:41:32 AM
View PCD Project Manager
11/10/2022 11:40:11 AM
Checklist for site plans (existing and proposed). Recommend including north-facing arrow. All other relevant data is present. 11/10/2022 11:40:11 AM
View PCD Project Manager
11/10/2022 11:38:33 AM
Checklist governing LOI. 11/10/2022 11:38:33 AM
View PCD Project Manager
11/10/2022 11:38:06 AM
Letter of intent is generally in conformance with the requirements of the checklist. I do recommended an expanded discussion with specific reference and citation of the Land Development Code. This will provide further clarity to decision authorities. 11/10/2022 11:38:06 AM
Mountain View Electric Association, Inc.
11/8/2022 10:11:01 AM
Mountain View Electric Association has no objection to the current plan 11/8/2022 10:11:01 AM
Academy SD 20 Building Fund
11/3/2022 7:12:15 AM
Academy District 20 is in receipt of File# BOA2215 for approval of the 6145 Vessey Road Garage/Shop Addition.

The District has no comment regarding the requested approval for this project.

Don Smith
Planning Consultant
11/3/2022 7:12:15 AM