Project Review Comments

Back to List


Project Name
Monument Tank Site (Phase 1) and 5.6 miles of Water Line (Phase 2)
Description
FIRST PHASE -Construction of a new 2 MG tank provide redundancy, equalization, fire flow, and emergency storage to the current and future population of the Town of Monument-; Development Agreement required before issuance of building permit; SECOND PHASE- Two 12-inch water transmission pipelines, totaling approximately 5.6 miles, will be constructed to and from the new tank to supply water to the Town distribution system .
Location
Parcels
7102200004 7102200004 7102300001 7102300001 7116204006 7116204006
Applicant
Forsgren Associates Inc.
Claire Koch ( ckoch@forsgren.com )
(720) 214-5884 x7004
Claire Koch ( ckoch@forsgren.com )
(720) 214-5884 x7004
File Number
PPR2130
Project Manager
Kari Parsons
Status
Closed
Created
6/11/2021 1:29:50 PM

View: Project Documents



Review Comments (52)

Link Agency Comment
PCD Engineering Division
7/28/2022 10:27:53 AM
Comments have been resolved. The project manager will upload any approved documents.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
7/28/2022 10:27:53 AM
View PCD Engineering Division
6/30/2022 11:04:05 AM
Pipeline Construction drawings_v5 redlines 6/30/2022 11:04:05 AM
PCD Engineering Division
6/30/2022 1:58:27 PM
Please address comments on the following documents:

-Construction drawings

and submit signed documents for the following reports for approval assuming all comments are resolved on the next round:

-Construction drawings
-PBMP applicability form: please sign and stamp per DORA regulations. The stamp should be signed across.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
6/30/2022 1:58:27 PM
PCD Project Manager
4/15/2022 4:11:29 PM
Planning Division has no further comments 4/15/2022 4:11:29 PM
PCD Engineering Division
4/13/2022 2:18:04 PM
Please submit all engineering documents with appropriate stamps and signatures from design engineer and owner.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
4/13/2022 2:18:04 PM
View PCD Project Manager
3/22/2022 4:32:25 PM
Site Plan Redlines 3/22/2022 4:32:25 PM
PCD Project Manager
3/22/2022 4:30:53 PM
Separate tank and waterline grading and erosion control plans into two documents for approval. 3/22/2022 4:30:53 PM
PCD Engineering Division
3/22/2022 4:09:26 PM
Comments will be uploaded by the project manager. Please submit engineering documents signed by owner in addition to engineering stamps and signatures. Separate tank and waterline grading and erosion control plans into two documents for approval.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
3/22/2022 4:09:26 PM
EPC Stormwater Review
3/21/2022 4:06:30 PM
Review 3: EPC Stormwater comments have been resolved on the following documents:
- Drainage Report
- GEC Plan
- GEC Checklist
- PBMP Applicability Form
- SWMP Checklist
- SWMP

EPC Stormwater has no further comments at this time. Thanks.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
3/21/2022 4:06:30 PM
View EPC Health Department
2/25/2022 6:26:02 PM
2/25/2022 6:26:02 PM
View Colorado Department of Public Health and Environment
2/14/2022 11:45:43 AM
Standard Comments from CDPHE apply. Comments attached. 2/14/2022 11:45:43 AM
View EPC Stormwater Review
2/8/2022 8:07:50 AM
SWMP Checklist 2/8/2022 8:07:50 AM
View EPC Stormwater Review
2/8/2022 8:07:30 AM
SWMP 2/8/2022 8:07:30 AM
View EPC Stormwater Review
2/8/2022 8:06:34 AM
PBMP Form 2/8/2022 8:06:34 AM
View EPC Stormwater Review
2/8/2022 8:06:18 AM
GEC Checklist 2/8/2022 8:06:18 AM
View EPC Stormwater Review
2/8/2022 8:05:53 AM
GEC Plan 2/8/2022 8:05:53 AM
View EPC Stormwater Review
2/8/2022 8:05:00 AM
Drainage Report 2/8/2022 8:05:00 AM
EPC Stormwater Review
2/8/2022 8:03:55 AM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report
- GEC Plan
- GEC Checklist
- PBMP Applicability Form
- SWMP Checklist
- SWMP

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
2/8/2022 8:03:55 AM
Pikes Peak Regional Building Department
1/31/2022 10:18:00 AM
No further comments.

Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
1/31/2022 10:18:00 AM
View Mountain View Electric Association, Inc.
1/31/2022 10:08:29 AM
See attached comments 1/31/2022 10:08:29 AM
PCD Project Manager
1/27/2022 11:49:47 AM
Please address all comments. After you have made the revisions, please sign all docs and upload for approval. Staff will verify all comments are addressed before sending for approval. 1/27/2022 11:49:47 AM
View PCD Project Manager
1/27/2022 11:48:19 AM
Combined site development plan redlines with summary 1/27/2022 11:48:19 AM
View PCD Engineering Division
1/27/2022 11:40:23 AM
Deviation Request Template 1/27/2022 11:40:23 AM
View PCD Engineering Division
1/27/2022 11:39:51 AM
Site development plan PCD Engineering Redline v2 1/27/2022 11:39:51 AM
View PCD Engineering Division
1/27/2022 11:39:07 AM
Waterline CDs PCD Engineering Redline v2 1/27/2022 11:39:07 AM
View PCD Engineering Division
1/27/2022 11:37:07 AM
GEC plan PCD Engineering Redline v2 1/27/2022 11:37:07 AM
View PCD Engineering Division
1/27/2022 11:36:34 AM
Drainage PCD Engineering Redline v2 1/27/2022 11:36:34 AM
View PCD Engineering Division
1/27/2022 11:35:57 AM
FAE PCD Engineering Redline v2 1/27/2022 11:35:57 AM
PCD Project Manager
1/26/2022 3:39:52 PM
Please revise the lighting plan as commented on in the site dev plan set. Please review Code, for residential lighting standards. 1/26/2022 3:39:52 PM
View PCD Project Manager
1/27/2022 11:48:48 AM
FAE combined comments with summary attached 1/27/2022 11:48:48 AM
PCD Engineering Division
1/27/2022 8:07:25 AM
Please submit a deviation request for cutting into Red Ranch Road before the 3 year mark.

Please address comments on the following documents:

-Drainage report
-FAE
-Site development plan
-Waterline CDs
-GEC plan


Please submit all engineering documents signed/stamped with the appropriate signatures once PCD and EPC Stormwater comments have all been resolved.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
1/27/2022 8:07:25 AM
Tri-Lakes-Monument Fire Protection District
1/19/2022 3:24:07 PM
TLMFPD has no additional comments. 1/19/2022 3:24:07 PM
View PCD Project Manager
1/19/2022 7:16:05 AM
Planning Only- Comments pre -bid as requested by Wil; Please address and resubmit as soon as possible. If you can turn these around in 36 hours; I can swap the set out for review by others. 1/19/2022 7:16:05 AM
911 Authority - El Paso/Teller County
1/13/2022 8:50:27 AM
No new streetnames requested on this submittal.
No action for E911.
Thank you.
Justin
1/13/2022 8:50:27 AM
Tri-Lakes-Monument Fire Protection District
8/20/2021 7:28:52 AM
No comments. 8/20/2021 7:28:52 AM
View EPC Stormwater Review
8/18/2021 12:38:18 PM
PBMP Applicability Form V_1 8/18/2021 12:38:18 PM
View EPC Stormwater Review
8/18/2021 12:37:45 PM
GEC Checklist V_1 8/18/2021 12:37:45 PM
EPC Stormwater Review
8/18/2021 12:37:17 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- PBMP Applicability Form

Please provide the following documents:
- SWMP

For the SWMP Checklist, please verify that everything on it is included in the SWMP itself. And then check everything off of the Checklist accordingly. The SWMP Checklist that you submitted did not have everything checked. And note that all items in the SWMP Checklist must be addressed. If not applicable, explain in SWMP text and check box on SWMP Checklist. Do not use “N/A” on SWMP Checklist.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer II
glennreese@elpasoco.com
8/18/2021 12:37:17 PM
View PCD Project Manager
8/18/2021 1:58:20 PM
Drainage comments 8/18/2021 1:58:20 PM
View PCD Project Manager
8/17/2021 4:27:26 PM
Site Plan combined comments 8/17/2021 4:27:26 PM
View PCD Project Manager
8/18/2021 1:58:47 PM
Grading & Erosion Control Comments Engineering 8/18/2021 1:58:47 PM
View PCD Project Manager
8/17/2021 4:25:53 PM
FAE Redlines Engineering comments 8/17/2021 4:25:53 PM
View PCD Engineering Division
8/17/2021 4:10:00 PM
Review 1 comments will be uploaded by the project manager. Please address comments on the following documents:

-drainage report
-site plan
-gec plan
-fae

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
8/17/2021 4:10:00 PM
View EPC Environmental Services
8/16/2021 8:43:18 AM
8/16/2021 8:43:18 AM
Pikes Peak Regional Building Department
8/12/2021 10:11:28 AM
Any new plans for submittal would be pending in the Enumerations department for approval, pending the wrecking permit for the rectangular bldg. addressed 19895 Beacon Lite Road.

No further comments at this time.

Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org W: 719-327-2953
8/12/2021 10:11:28 AM
View Colorado Department of Public Health and Environment
8/11/2021 11:21:31 AM
8/11/2021 11:21:31 AM
View PCD Project Manager
8/4/2021 2:11:43 PM
Site plan package drawing redline planning comments. Please see checklists for site plan and landscape plan in addition to redlines. Please note: staff is aware of the minimal landscape requirements, but a plan does need to be provided that meets Code-see landscape checklist. Review approved tank site files PPR201 Forest Lakes Tank Site and
MERIDIAN SERVICE METRO DIST WATER TANK PPR07025 for samples. Please note this is reviewed under current Code, and checklists.
8/4/2021 2:11:43 PM
View PCD Project Manager
8/4/2021 1:56:56 PM
Site Development Plan checklist; Please add missing items to sheet 1.and other sheets where applicable. 8/4/2021 1:56:56 PM
View PCD Project Manager
8/4/2021 1:56:15 PM
Landscape plan Checklist (Sheet 4 of your plan set)- Please incorporate the checklist to your drawings... 8/4/2021 1:56:15 PM
Mountain View Electric Association, Inc.
8/4/2021 9:50:34 AM
See comment letter for AASI211 - no additional comments at this time. 8/4/2021 9:50:34 AM
County Attorney - Development Review
7/28/2021 1:39:34 PM
No comments from County Attorney's Office at this time. Please re-refer if it is determined that a Detention Maintenance Agreement is needed for this project. 7/28/2021 1:39:34 PM
911 Authority - El Paso/Teller County
7/28/2021 7:36:05 AM
No street names requested on this submittal.
No action for E911.
Thank you.
Justin
7/28/2021 7:36:05 AM