Project Review Comments

Back to List


Project Name
Peaceful Ridge EGP
Description
Ref SF05044 - application to update construction drawings and SIA to meet current standards
Location
Parcels
5515400002 5515400002
Applicant
Widefield Investment Group
Ryan Watson ( ryan@widefieldinvestmentgroup.com )
(719) 392-0194
Ryan Watson ( ryan@widefieldinvestmentgroup.com )
(719) 392-0194
File Number
EGP213
Project Manager
Ryan Howser
Status
Closed
Created
6/3/2021 5:17:55 PM

View: Project Documents



Review Comments (33)

Link Agency Comment
View County Attorney - Development Review
8/2/2022 10:34:58 AM
Signature to license agreement attached. 8/2/2022 10:34:58 AM
View County Attorney - Development Review
8/2/2022 10:32:07 AM
Signature to Detention Maintenance Agreement attached. 8/2/2022 10:32:07 AM
EPC Stormwater Review
8/1/2022 2:22:08 PM
All Stormwater comments have been addressed.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
8/1/2022 2:22:08 PM
View County Attorney - Development Review
7/26/2022 11:49:39 AM
A few minor edits to Detention Maintenance Agreement were not addressed. Please see attached. 7/26/2022 11:49:39 AM
View County Attorney - Development Review
7/26/2022 11:48:47 AM
A couple of minor edits in the Recitals are attached. Please check on the status of Marksheffel Road at this location. Conveyance to the City of Colorado Springs may have already occurred. If that's the case, or if such conveyance occurs prior to approval of this project or before the ROW license agreement is recorded, applicant will need to work with the City to obtain approval for improvements in the ROW. 7/26/2022 11:48:47 AM
PCD Engineering Division
7/12/2022 11:09:05 AM
Comments have been resolved and the project manager will upload approved documents.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
7/12/2022 11:09:05 AM
PCD Project Manager
7/5/2022 10:16:37 AM
Planning Division has no comments 7/5/2022 10:16:37 AM
View PCD Engineering Division
7/5/2022 7:26:39 AM
PBMP Applicability Form_v4 redlines 7/5/2022 7:26:39 AM
View EPC Stormwater Review
6/30/2022 2:46:57 PM
Review 4: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded document:
- Drainage Report (minor comment as discussed with engineer)

Please refer to PCD Engineer for any additional comments.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
6/30/2022 2:46:57 PM
PCD Engineering Division
7/5/2022 7:27:13 AM
Address minor comments in the following documents:

-PBMP app form

Please submit the following engineering documents signed by both the engineer and the owner for approval. Please make sure all comments have been resolved so the project can move towards approval.

-FAE: FYI: as built/pond certification will be required with subsequent CDR application.
-Drainage report
-GEC Plan

Note to the planner: Please set the review cycle to 5 days.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
7/5/2022 7:27:13 AM
View County Attorney - Development Review
6/28/2022 3:45:28 PM
The License Agreement appears to be an older template. Please use the attached template. 6/28/2022 3:45:28 PM
View County Attorney - Development Review
6/28/2022 3:43:23 PM
Proposed edits to Detention Maintenance Agreement attached. 6/28/2022 3:43:23 PM
View PCD Project Manager
3/1/2022 4:23:44 PM
PCD Engineering and EPC Stormwater comments - GEC plan 3/1/2022 4:23:44 PM
View PCD Project Manager
3/1/2022 4:23:19 PM
PCD Engineering comments - FAE 3/1/2022 4:23:19 PM
View PCD Project Manager
3/1/2022 4:23:01 PM
PCD Engineering and EPC Stormwater comments - drainage report 3/1/2022 4:23:01 PM
PCD Engineering Division
3/1/2022 12:11:27 PM
Review comments will be uploaded by the project manager. Please address comments on the following documents:

-Drainage report
-FAE
-GEC plan

Please upload the Detention Maintenance Agreement and the O&M Manual as discussed in the meeting on February 10th. Also submit a license agreement for the infrastructure in the ROW.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
3/1/2022 12:11:27 PM
View EPC Stormwater Review
2/17/2022 2:19:09 PM
PBMP_v3 2/17/2022 2:19:09 PM
EPC Stormwater Review
2/17/2022 2:16:24 PM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...............(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- PBMP Applicability Form

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
2/17/2022 2:16:24 PM
View PCD Project Manager
12/17/2021 3:24:17 PM
EPC Stormwater & PCD Engineering comments - GEC plan 12/17/2021 3:24:17 PM
View PCD Project Manager
12/17/2021 3:23:48 PM
EPC Stormwater & PCD Engineering comments - drainage report 12/17/2021 3:23:48 PM
PCD Engineering Division
12/15/2021 7:33:03 AM
Review 2 comments will be uploaded by the project manager. Please address comments on the following documents:

-Drainage report
-GEC plan

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
12/15/2021 7:33:03 AM
View EPC Stormwater Review
12/13/2021 9:00:52 AM
ESQCP_v2 12/13/2021 9:00:52 AM
View EPC Stormwater Review
12/13/2021 9:00:25 AM
SWMP Checklist_v2 12/13/2021 9:00:25 AM
View EPC Stormwater Review
12/13/2021 9:00:08 AM
GEC Checklist_v2 12/13/2021 9:00:08 AM
EPC Stormwater Review
12/13/2021 8:59:45 AM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report...............(to be uploaded by PM with PCD comments)
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP Checklist
- ESQCP

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
12/13/2021 8:59:45 AM
View PCD Project Manager
11/4/2021 10:28:02 AM
PCD Engineering and EPC Stormwater comments - GEC plan 11/4/2021 10:28:02 AM
View EPC Stormwater Review
11/1/2021 8:12:22 AM
ESQCP_v1 11/1/2021 8:12:22 AM
View EPC Stormwater Review
11/1/2021 8:11:56 AM
SWMP Checklist_v1 11/1/2021 8:11:56 AM
View EPC Stormwater Review
11/1/2021 8:11:11 AM
SWMP_v1 11/1/2021 8:11:11 AM
View EPC Stormwater Review
11/1/2021 8:10:51 AM
GEC Checklist_v1 11/1/2021 8:10:51 AM
PCD Project Manager
11/4/2021 10:28:14 AM
Planning Division has no comments. 11/4/2021 10:28:14 AM
EPC Stormwater Review
10/29/2021 1:13:35 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- GEC Plan...............(to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP
- SWMP Checklist
- ESQCP

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
10/29/2021 1:13:35 PM
PCD Engineering Division
10/27/2021 10:03:13 AM
The project manager will upload review comments. Please address comments on the following documents:

-Grading and erosion control plan

Note to the planner: Please open up a submittal slot for a drainage report on EDARP.

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
10/27/2021 10:03:13 AM