PCD Engineering Division
8/31/2022 5:27:03 PM |
The traffic study has been accepted for file and will be uploaded by the project manager. The deviation request is pending determination by the ECM Administrator and will be uploaded as soon as a decision to either approve or deny has been made. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
8/31/2022 5:27:03 PM | |
PCD Engineering Division
8/9/2022 10:01:39 AM |
Review 3: Comments resolved. 1. Submit the Traffic Impact Study with signed Developer's Statement for final acceptance. 2. Submit the Deviation Request Form with Owner (or Authorized Representative) signature. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
8/9/2022 10:01:39 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/27/2022 4:12:09 PM |
If you have any queries about gas services, please contact Springs Utilities' field engineering. 719-668-4985. Corey Masoumi - cmasoumi@csu.org |
7/27/2022 4:12:09 PM | |
View |
PCD Project Manager
7/26/2022 12:57:50 PM |
Minor comment (typo) on the LOI is attached. Planning Division has no comments. | 7/26/2022 12:57:50 PM |
View |
PCD Engineering Division
7/26/2022 11:09:02 AM |
Review #2: 1. Update the deviation request as discussed with the Engineering Review Manager: - Proposed full movement intersection 1/2 mile north of Curtis/Falcon intersection. - Right-In/Right-Out between the full movement and Curtis/Falcon intersection. Approximately 1,295' north of Curtis/Falcon intersection - Revise the Falcon Hwy proposed access to full movement intersection. 2. Attached are redline comments to the Traffic impact Study. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
7/26/2022 11:09:02 AM |
County Attorney - Development Review
6/12/2022 9:41:40 AM |
No comments from County Attorney - Development Review at this time. | 6/12/2022 9:41:40 AM | |
Upper Black Squirrel Creek GWMD
6/8/2022 4:52:57 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. | 6/8/2022 4:52:57 PM | |
View |
PCD Project Manager
6/8/2022 4:25:44 PM |
Zoning map comments attached | 6/8/2022 4:25:44 PM |
View |
PCD Project Manager
6/8/2022 4:25:11 PM |
LOI comments attached | 6/8/2022 4:25:11 PM |
PCD Project Manager
6/8/2022 4:21:00 PM |
All three map amendment applications contain a list of uses that are proposed to be excluded because they are determined to be incompatible with the placetype in the Your El Paso Master Plan. However, the argument is being made that the proposed zoning districts are compatible with the placetype. Please provide further clarity in the letter of intent regarding compatibility of the proposals to the master plan components, despite the large number of uses that have been determined to be incompatible. | 6/8/2022 4:21:00 PM | |
PCD Project Manager
6/8/2022 4:22:39 PM |
Are you able to provide proof of water and sewer services? It will be more difficult to justify CS zoning without identified service providers. Letter of intent identifies that it is intended to connect to central services; however, identification of which providers have services available would benefit the application. Water Master Plan analysis does not address this. | 6/8/2022 4:22:39 PM | |
Mountain View Electric Association, Inc.
6/6/2022 10:44:14 AM |
Mountain View Electric Association has no objection to the rezone | 6/6/2022 10:44:14 AM | |
View |
PCD Engineering Division
6/6/2022 10:12:14 AM |
Review #1: Traffic Impact Study redline comments is attached. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
6/6/2022 10:12:14 AM |
View |
El Paso County Conservation Dist
6/2/2022 7:40:39 PM |
EPCCD grass seed native shotgun mix added as .jpg. | 6/2/2022 7:40:39 PM |
View |
El Paso County Conservation Dist
6/2/2022 7:33:06 PM |
EPCCD brief comments added as a .docx. | 6/2/2022 7:33:06 PM |
View |
Parks Advisory Board
6/1/2022 11:53:51 AM |
See Parks comments attached. | 6/1/2022 11:53:51 AM |
View |
EPC Parks Department
6/1/2022 11:51:58 AM |
Please see Parks comments attached. Thanks, Greg |
6/1/2022 11:51:58 AM |
View |
Colorado Parks and Wildlife
5/27/2022 12:04:26 AM |
5/27/2022 12:04:26 AM | |
View |
EPC Environmental Services
5/23/2022 1:40:18 PM |
5/23/2022 1:40:18 PM | |
RBD Floodplain
5/23/2022 10:48:19 AM |
The site has exposure to A zone floodplain. This floodplain would need to be studied via the FEMA CLOMR/LOMR process prior to any future re plat. Floodplain has no comment on zoning changes. | 5/23/2022 10:48:19 AM | |
View |
Meadow Lake Airport Association
5/18/2022 6:58:36 PM |
MLAA is strongly opposed to this request. Letter attached. | 5/18/2022 6:58:36 PM |
Falcon Fire Protection District
5/18/2022 10:09:44 AM |
Falcon Fire has no objections or concerns with this request> | 5/18/2022 10:09:44 AM | |
County Attorney - Water
5/18/2022 9:54:18 AM |
This appears to be a rezoning request and no water review is necessary. Please submit to County Attorney-Development Review for further review. Thank you. | 5/18/2022 9:54:18 AM |