View: Project Documents
Agency | Comment | ||
---|---|---|---|
EPC Stormwater Review
5/14/2021 5:20:42 PM |
All EPC Stormwater comments have been resolved. Reviewed by: Christina Furchak Stormwater Engineer III christinafurchak@elpasoco.com |
5/14/2021 5:20:42 PM | |
PCD Project Manager
5/12/2021 5:14:57 PM |
Planning Division has no further comments at this time. | 5/12/2021 5:14:57 PM | |
View |
PCD Project Manager
4/28/2021 11:25:59 AM |
EPC Stormwater comments on construction drawings attached. | 4/28/2021 11:25:59 AM |
View |
EPC Stormwater Review
4/28/2021 9:07:30 AM |
GEC Checklist_v2 | 4/28/2021 9:07:30 AM |
PCD Project Manager
4/28/2021 11:26:36 AM |
Per previous comment, please include the reception number for the recorded easements on the plan set. | 4/28/2021 11:26:36 AM | |
EPC Stormwater Review
4/28/2021 9:06:57 AM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Construction Drawings (to be uploaded by PM with PCD comments) - GEC Checklist Please sign, date and resubmit the following documents: - PBMP Applicability Form - ESQCP EPC Stormwater comments have been resolved on the following documents: - FAE - SWMP Reviewed by: Christina Furchak Stormwater Engineer III christinafurchak@elpasoco.com |
4/28/2021 9:06:57 AM | |
Colorado Division of Water Resources
4/26/2021 2:14:16 PM |
Given the nature of the project/referral - The Division of water Resources has no substantive comments at this time. | 4/26/2021 2:14:16 PM | |
Mountain View Electric Association, Inc.
4/21/2021 4:22:43 PM |
Please reference the comment letter dated 3/25/21 - no additional comments at this time | 4/21/2021 4:22:43 PM | |
PCD Engineering Division
4/27/2021 7:23:38 AM |
There are no additional engineering comments relating to drainage and transportation. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
4/27/2021 7:23:38 AM | |
Colorado Springs Planning & Community Development
4/16/2021 7:06:16 AM |
City Stormwater Enterprise has no comments on this item Anna Bergmark, P.E. Stormwater Development Review Manager City of Colorado Springs 30 S. Nevada Ave., Suite 401 Colorado Springs, CO 80901 (719) 385-5613 office (719) 619-9427 Cell Anna.Bergmark@coloradosprings.gov |
4/16/2021 7:06:16 AM | |
View |
PCD Project Manager
3/30/2021 10:16:20 AM |
FAE comment attached. Includes comments from EPC Stormwater. | 3/30/2021 10:16:20 AM |
View |
PCD Project Manager
3/30/2021 10:16:00 AM |
Construction drawing comment attached. Includes comments from PCD Engineering and EPC Stormwater. | 3/30/2021 10:16:00 AM |
PCD Engineering Division
3/30/2021 8:56:22 AM |
Review 1 comment on the following documents will be uploaded by the project manager: -CD: minor comment reviewed by: Daniel Torres danieltorres@elpasoco.com |
3/30/2021 8:56:22 AM | |
PCD Project Manager
3/26/2021 12:15:44 PM |
This comment will apply to both PPR-21-006 and this project. Please provide a copy of the easement and reference the reception number for the recorded easement on both sets of plans. Easement needs to be established prior to approval of any site work. | 3/26/2021 12:15:44 PM | |
View |
Mountain View Electric Association, Inc.
3/25/2021 4:32:43 PM |
See MVEA Comments | 3/25/2021 4:32:43 PM |
View |
EPC Stormwater Review
3/22/2021 1:18:09 PM |
PBMP Applicability Form_v1 | 3/22/2021 1:18:09 PM |
View |
EPC Stormwater Review
3/22/2021 1:17:42 PM |
ESQCP_v1 | 3/22/2021 1:17:42 PM |
View |
EPC Stormwater Review
3/22/2021 1:17:16 PM |
SWMP Checklist_v1 | 3/22/2021 1:17:16 PM |
View |
EPC Stormwater Review
3/22/2021 1:13:44 PM |
SWMP_v1 | 3/22/2021 1:13:44 PM |
View |
EPC Stormwater Review
3/22/2021 1:12:31 PM |
GEC Checklist_v1 | 3/22/2021 1:12:31 PM |
EPC Stormwater Review
3/22/2021 1:11:55 PM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - FAE (to be uploaded by PM with PCD comments) - Construction Drawings (to be uploaded by PM with PCD comments) - GEC Checklist - SWMP - SWMP Checklist - ESQCP - PBMP Applicability Form Reviewed by: Christina Furchak Stormwater Engineer III christinafurchak@elpasoco.com |
3/22/2021 1:11:55 PM | |
Pikes Peak Regional Building Department
3/17/2021 9:07:00 AM |
Based on information known at this time Enumerations believes that the pipeline connection is to both water tanks therefore, there should be 1 address to both tanks. Once the plans are submitted to RBD and Plumbing Plan Review this may change. Based on El Paso/Teller County 9-1-1 Authorities comments regarding the access to this site not needing the access road named the site will be addressed from Drennan Road. When submitting plans to RBD please use the address of 10957 Drennan Road. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
3/17/2021 9:07:00 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/11/2021 8:54:03 AM |
Hey Ryan, I have finished with the review for the proposed installation. CSU has no action items and approval can be recommended. Thanks, Ryne Solberg rsolberg@csu.org |
3/11/2021 8:54:03 AM | |
RBD Floodplain
3/4/2021 10:28:27 AM |
no comment | 3/4/2021 10:28:27 AM |