Project Name
WWSD Rolling Hills 2MG Potable Water Tank
Description
This project consists of a proposed 2.0-million gallon water storage tank that is on a tank site with a pending 1041 application. A pipeline to convey water to and from the tank was also included in the pending 1041 application. The new tank site will be located on a 3.472-acre easement located within the parcel referenced by schedule 5500000385. The purpose of the tank is to provide potable water service to new development and existing customers within Widefield Water and Sanitation District’s (WWSD) existing service area boundaries. No new water sources or water treatment facilities are proposed as part of this project. SUBJECT TO REVIEW AND APPROVAL OF PIPELINE PROJECT.
Location
Parcels
5500000385 5500000385
Applicant
JDS-Hydro Consultants, Inc.
Gwen Dall ( gwendolyn.dall@respec.com )
(719) 402-0014
Gwen Dall ( gwendolyn.dall@respec.com )
(719) 402-0014
EA Number
EA20180
File Number
PPR216
Project Manager
Ryan Howser
Status
Closed
Created
1/5/2021 8:03:39 AM

View: Project Documents



Review Comments (36)

Link Agency Comment
EPC Stormwater Review
2/23/2023 5:27:43 PM
All EPC DPW Stormwater comments have been addressed. 2/23/2023 5:27:43 PM
EPC Stormwater Review
11/29/2022 5:32:39 PM
As Built Review 1: Please submit a Pond Certification Letter, in accordance with ECM Chapter 5.10.6.B.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
ChristinaPrete@elpasoco.com
11/29/2022 5:32:39 PM
PCD Engineering Division
11/29/2022 5:07:46 PM
There are no comments relating to drainage or transportation.

Reviewed By:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
11/29/2022 5:07:46 PM
County Attorney - Development Review
6/29/2021 10:58:32 PM
No further comments from County Attorney's Office. 6/29/2021 10:58:32 PM
County Attorney - Development Review
6/21/2021 10:36:55 AM
County Attorney's Office and counsel for the District reached agreement on a Detention Maintenance Agreement, which was attached to an email from District's counsel dated June 16. 6/21/2021 10:36:55 AM
County Attorney - Development Review
5/27/2021 6:01:40 PM
County Attorney's Office is working with counsel for WWSD on the Detention Maintenance Agreement. A final version should be ready for the next review referral period. 5/27/2021 6:01:40 PM
PCD Project Manager
5/27/2021 4:01:09 PM
PCD Planning Division has no comments at this time. 5/27/2021 4:01:09 PM
PCD Engineering Division
5/26/2021 11:54:22 AM
Engineering comments have been resolved. The documents will be uploaded onto EDARP once approved by the ECM Administrator.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
5/26/2021 11:54:22 AM
EPC Stormwater Review
5/25/2021 10:10:18 AM
All EPC Stormwater comments have been addressed.

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
5/25/2021 10:10:18 AM
View PCD Project Manager
5/4/2021 4:48:45 PM
Site development plan - PCD Engineering & PCD Planning comments attached. 5/4/2021 4:48:45 PM
View PCD Project Manager
5/4/2021 4:47:51 PM
Grading & Erosion Control plan - PCD Stormwater comments attached. 5/4/2021 4:47:51 PM
View PCD Project Manager
5/4/2021 4:46:58 PM
Drainage report - PCD Engineering comments attached. 5/4/2021 4:46:58 PM
View EPC Stormwater Review
5/4/2021 11:54:27 AM
GEC Checklist_v2 5/4/2021 11:54:27 AM
County Attorney - Development Review
5/4/2021 10:24:17 AM
Please provide contact info for WWSD's attorney to the project manager, who will then pass it to the County Attorney's Office. El Paso County cannot agree to some of the revisions proposed by the District. 5/4/2021 10:24:17 AM
EPC Stormwater Review
5/4/2021 11:47:24 AM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- GEC Plan (to be uploaded by PM with PCD comments)
- GEC Checklist

EPC Stormwater comments have been resolved on the following documents:
- Drainage Report
- FAE
- ESQCP
- PBMP Applicability Form
- SWMP
- SWMP Checklist
- O&M Manual

Please sign/stamp, date and resubmit the follow documents:
- ESQCP

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
5/4/2021 11:47:24 AM
PCD Project Manager
4/29/2021 1:02:09 PM
Planning Division has minor comment on site development plan: Per comment also provided on pipeline plan, please also include reception numbers for recorded easements. 4/29/2021 1:02:09 PM
PCD Engineering Division
4/27/2021 3:38:27 PM
Review 2 comments on the following documents will be uploaded by the project manager:

-Site Development Plan (minor unresolved comments)
-Final Drainage Report (minor unresolved comments)

Please submit proof of submittal of the state non-jurisdictional water impoundment form.

Comments have been resolved on the following documents:

-GEC Plan
-FAE

Please submit engineering documents with appropriate stamps/ signatures after all EPC Stormwater comments have been resolved:

-GEC Plan
- Drainage report

Reviewed by:
Lupe Packman
Review Engineer
lupepackman@elpasoco.com
4/27/2021 3:38:27 PM
View PCD Project Manager
3/17/2021 5:10:56 PM
Site development plan comments attached. Also includes PCD Engineering comments. 3/17/2021 5:10:56 PM
View PCD Project Manager
3/17/2021 5:10:30 PM
Letter of intent comment attached. 3/17/2021 5:10:30 PM
View PCD Project Manager
3/17/2021 5:10:12 PM
Landscape plan comments attached. 3/17/2021 5:10:12 PM
View PCD Project Manager
3/17/2021 5:09:57 PM
Grading & erosion control plan comments attached. Includes PCD Engineering and EPC Stormwater comments. 3/17/2021 5:09:57 PM
View PCD Project Manager
3/17/2021 5:09:28 PM
Financial assurance form comments attached. Includes PCD Engineering and EPC Stormwater comments. 3/17/2021 5:09:28 PM
View PCD Project Manager
3/17/2021 5:08:51 PM
Drainage report comments attached Includes PCD Engineering and EPC Stormwater comments. 3/17/2021 5:08:51 PM
View EPC Stormwater Review
3/17/2021 2:48:00 PM
PBMP Applicability Form_v1 3/17/2021 2:48:00 PM
View EPC Stormwater Review
3/17/2021 2:47:38 PM
ESQCP_v1 3/17/2021 2:47:38 PM
View EPC Stormwater Review
3/17/2021 2:47:09 PM
SWMP Checklist_v1 3/17/2021 2:47:09 PM
View EPC Stormwater Review
3/17/2021 2:46:35 PM
SWMP_v1 3/17/2021 2:46:35 PM
View EPC Stormwater Review
3/17/2021 2:45:22 PM
GEC Checklist_v1 3/17/2021 2:45:22 PM
EPC Stormwater Review
3/17/2021 2:41:58 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report (to be uploaded by PM with PCD comments)
- FAE (to be uploaded by PM with PCD comments)
- GEC Plan (to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP
- SWMP Checklist
- ESQCP
- PBMP Applicability Form

Please provide the following documents:
- O&M Manual

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
3/17/2021 2:41:58 PM
PCD Engineering Division
3/16/2021 10:44:43 AM
Review 1 comments on the following documents will be uploaded by the project manager:
-Site Development Plan
-Grading and Erosion Control Plan
-Final drainage Report
-FAE

Please submit proof of submittal of the state non-jurisdictional water impoundment form

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
3/16/2021 10:44:43 AM
Mountain View Electric Association, Inc.
2/25/2021 2:19:58 PM
Mountain View Electric Association (MVEA) has no objections to current plan. If there is any removal, damage, or relocation of facilities it will be at the expense of the applicant and a review of easements will be required. 2/25/2021 2:19:58 PM
View Colorado Division of Water Resources
2/24/2021 5:09:20 PM
2/24/2021 5:09:20 PM
Pikes Peak Regional Building Department
2/24/2021 8:25:45 AM
1. Consult with El Paso/Teller County 9-1-1 Authority to see if they would like this access road named. Does not look like they were an added department for this review. Please send the site plan showing access form the main road way to 9-1-1. An email from that dept. stating weather the access road should be named or not needs to be sent to Enumerations. An address will be assigned from there. Contact Justin Annan jannan@elpasoteller911.org
No further comments.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
2/24/2021 8:25:45 AM
View County Attorney - Development Review
2/23/2021 4:58:20 PM
Proposed changes to Detention Maintenance Agreement are attached. 2/23/2021 4:58:20 PM
Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/17/2021 11:06:53 AM
Hey Ryan,

CSU has no action items with this proposal. Approval can be recommended.

Thanks,

Ryne Solberg
rsolberg@csu.org
2/17/2021 11:06:53 AM
RBD Floodplain
2/12/2021 12:16:20 PM
project area is not within the SFHA, no further comment 2/12/2021 12:16:20 PM