Project Review Comments

Back to List


Project Name
Legacy Church (Formerly Pearsons Ministries
Description
COM to make minor revisions to site plan and grading and landscaping.
Location
Parcels
8300000004 8300000004 8305400016 8305400016 8305400020 8305400020
Applicant
Jared Roberts - Kimley Horn
Jared Roberts ( jared.roberts@kimley-horn.com )
(719) 284-7273
Jared Roberts ( jared.roberts@kimley-horn.com )
(719) 284-7273
EA Number
EA1947
File Number
COM2030
Project Manager
Lindsay Darden
Status
Closed
Created
7/7/2020 10:55:56 AM

View: Project Documents



Review Comments (5)

Link Agency Comment
PCD Engineering Division
7/20/2020 5:16:08 PM
Engineering comments have been resolved. The project manager will upload the documents onto EDARP once approved by the ECM administrator.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
7/20/2020 5:16:08 PM
PCD Project Manager
7/17/2020 2:04:34 PM
No further planning comments. 7/17/2020 2:04:34 PM
View PCD Engineering Division
7/15/2020 8:18:31 AM
Drainage letter redlines 7/15/2020 8:18:31 AM
PCD Engineering Division
7/15/2020 8:15:58 AM
Review 1 comments will be uploaded onto EDARP
-Drainage letter

reviewed by
Daniel Torres
danieltorres@elpasoco.com
7/15/2020 8:15:58 AM
PCD Project Manager
7/14/2020 9:56:15 AM
On the coversheet, please provide an itemized list of the revisions from the previous plan to make it easy for anyone who looks at this revision in the future to see what changed.

Add PCD File Number COM-20-030 to the site plan coversheet.

Utility Sheet: Correct the number of parking spaces to 117 to match the other sheets.

Revise the lighting plan to match the new parking lot revisions. New lighting may not be needed but we need to see the photometrics cover the whole parking lot area.
7/14/2020 9:56:15 AM