View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
7/20/2020 5:16:08 PM |
Engineering comments have been resolved. The project manager will upload the documents onto EDARP once approved by the ECM administrator. reviewed by: Daniel Torres danieltorres@elpasoco.com |
7/20/2020 5:16:08 PM | |
PCD Project Manager
7/17/2020 2:04:34 PM |
No further planning comments. | 7/17/2020 2:04:34 PM | |
View |
PCD Engineering Division
7/15/2020 8:18:31 AM |
Drainage letter redlines | 7/15/2020 8:18:31 AM |
PCD Engineering Division
7/15/2020 8:15:58 AM |
Review 1 comments will be uploaded onto EDARP -Drainage letter reviewed by Daniel Torres danieltorres@elpasoco.com |
7/15/2020 8:15:58 AM | |
PCD Project Manager
7/14/2020 9:56:15 AM |
On the coversheet, please provide an itemized list of the revisions from the previous plan to make it easy for anyone who looks at this revision in the future to see what changed. Add PCD File Number COM-20-030 to the site plan coversheet. Utility Sheet: Correct the number of parking spaces to 117 to match the other sheets. Revise the lighting plan to match the new parking lot revisions. New lighting may not be needed but we need to see the photometrics cover the whole parking lot area. |
7/14/2020 9:56:15 AM |