View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
5/28/2019 12:50:44 PM |
Please et up a precon after CDs are signed and uploaded. | 5/28/2019 12:50:44 PM | |
PCD Engineering Division
5/28/2019 9:32:06 AM |
Review 2: The utility construction plans are pending approval. Approved plans will be uploaded by the project manager. Gilbert LaForce, P.E. gilbertlaforce@elpasoco.com |
5/28/2019 9:32:06 AM | |
View |
PCD Engineering Division
5/7/2019 12:42:58 PM |
Review 1 comments: - Replace the FAE with the approved version from PUDSP185 - Submit signed Sanitary Sewer and Watermain construction plans for signature. The following documents were reviewed and approved with the PUDSP185, no additional comments: SWMP, Pre-Development Site Grading Acknowledgement and ROA Form, Preliminary Drainage Report, ESQCP. |