View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Project Manager
12/29/2017 8:24:33 AM |
Multi-Discipline Comments Letter | 12/29/2017 8:24:33 AM |
PCD Engineering Division
12/26/2017 8:19:51 AM |
Engineering has no comments to the administrative relief request. A driveway permit is required for all driveways in the County. This permit can be obtained at the PCD front counter. | 12/26/2017 8:19:51 AM | |
Falcon Fire Protection District
12/20/2017 3:39:34 PM |
Falcon Fire Department has no objections to the request. | 12/20/2017 3:39:34 PM | |
PCD Project Manager
12/19/2017 10:12:24 AM |
You need to show on the site plan that the pad in the back is 10x10. The Certified Mail Receipts are not postmarked. |
12/19/2017 10:12:24 AM | |
View |
Mountain View Electric Association, Inc.
12/14/2017 1:27:32 PM |
12/14/2017 1:27:32 PM |