Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
2/22/2018 11:33:00 AM |
Condition for drainage report: all back yard flow will need to have WQ provided. This set of documents are ready for approval, please submit signed copies for approval. |
2/22/2018 11:33:00 AM | |
View |
PCD Engineering Division
2/21/2018 5:03:19 PM |
2/21/2018 5:03:19 PM | |
View |
PCD Engineering Division
2/21/2018 5:02:31 PM |
comments provided on the attached GEC plan and FDR, also emailed on 2/16/2018 to Tom Kerby. | 2/21/2018 5:02:31 PM |
View |
PCD Engineering Division
1/8/2018 2:49:23 PM |
Drainage Report redline comments attached. | 1/8/2018 2:49:23 PM |
View |
PCD Engineering Division
1/8/2018 2:48:50 PM |
Grading and Erosion Control Plan redline comments attached. | 1/8/2018 2:48:50 PM |
View |
PCD Engineering Division
1/4/2018 5:08:48 PM |
Geotech Report redline comments attached. | 1/4/2018 5:08:48 PM |
View |
PCD Engineering Division
1/4/2018 5:08:05 PM |
Financial Assurance Estimate redline comments attached. | 1/4/2018 5:08:05 PM |
View |
PCD Engineering Division
1/4/2018 9:54:12 AM |
Complete the attached Pre-Development Site Grading Acknowledgement and Right of Access Form. | 1/4/2018 9:54:12 AM |
PCD Engineering Division
11/28/2017 9:45:16 AM |
Redline documents were uploaded by the Project Manager on 11/20/17. | 11/28/2017 9:45:16 AM | |
PCD Project Manager
11/14/2017 1:00:11 PM |
Planning has no comment for this application. PCD Engineering division has until 11/22 to submit comment. Once comment has been received you will receive either a request for resubmittal or be notified of the anticipated hearing date before the BoCC. | 11/14/2017 1:00:11 PM |