View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
8/1/2017 9:12:04 AM |
Comment has been addressed. | 8/1/2017 9:12:04 AM | |
PCD Engineering Division
7/31/2017 10:58:39 AM |
Comments Resolved. | 7/31/2017 10:58:39 AM | |
PCD Project Manager
7/20/2017 4:35:15 PM |
Change the "Proposed warehouse" label to "existing warehouse" on the Northern part of the site plan. | 7/20/2017 4:35:15 PM | |
View |
PCD Engineering Division
7/19/2017 1:49:46 PM |
See the attached pdf for redline comments to the site plan. | 7/19/2017 1:49:46 PM |