Project Review Comments

Back to List


Project Name
Hallgren Amended Site Development Plan (Padmark)
Description
Amend an existing site development plan to change the location of the building and parking.
Location
The property is located in the Claremont Business Park off of Meadowbrook Parkway.
Parcels
5408102048 5408102048
Applicant
Hammers Construction
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
Lisa Peterson ( lpeterson@hammersconstruction.com )
(719) 570-1599 x105
File Number
PPR17023
Project Manager
Nina Ruiz
Status
Closed
Created
5/11/2017 5:52:33 AM

View: Project Documents



Review Comments (29)

Link Agency Comment
View EPC Code Enforcement
9/6/2017 9:39:07 AM
9/6/2017 9:39:07 AM
View EPC Code Enforcement
9/6/2017 9:38:54 AM
9/6/2017 9:38:54 AM
View EPC Code Enforcement
9/6/2017 9:38:40 AM
9/6/2017 9:38:40 AM
View EPC Code Enforcement
9/6/2017 9:38:25 AM
9/6/2017 9:38:25 AM
View EPC Code Enforcement
9/6/2017 9:38:13 AM
9/6/2017 9:38:13 AM
View EPC Code Enforcement
9/6/2017 9:37:59 AM
9/6/2017 9:37:59 AM
View EPC Code Enforcement
9/6/2017 9:37:45 AM
Only 20 marked parking spots 9/6/2017 9:37:45 AM
View EPC Code Enforcement
9/6/2017 9:36:17 AM
9/6/2017 9:36:17 AM
View EPC Code Enforcement
9/6/2017 9:36:03 AM
9/6/2017 9:36:03 AM
View EPC Code Enforcement
9/6/2017 9:35:49 AM
9/6/2017 9:35:49 AM
View EPC Code Enforcement
9/6/2017 9:35:38 AM
9/6/2017 9:35:38 AM
View EPC Code Enforcement
9/6/2017 9:35:26 AM
9/6/2017 9:35:26 AM
View EPC Code Enforcement
9/6/2017 9:35:09 AM
9/6/2017 9:35:09 AM
View EPC Code Enforcement
9/6/2017 9:34:57 AM
9/6/2017 9:34:57 AM
View EPC Code Enforcement
9/6/2017 9:34:45 AM
9/6/2017 9:34:45 AM
View EPC Code Enforcement
9/6/2017 9:34:34 AM
9/6/2017 9:34:34 AM
View EPC Code Enforcement
9/6/2017 9:34:21 AM
9/6/2017 9:34:21 AM
View EPC Code Enforcement
9/6/2017 9:34:05 AM
9/6/2017 9:34:05 AM
View EPC Code Enforcement
9/6/2017 9:33:49 AM
9/6/2017 9:33:49 AM
View EPC Code Enforcement
9/6/2017 9:33:30 AM
9/6/2017 9:33:30 AM
View EPC County Attorney's Office
8/3/2017 1:36:36 PM
This should be the final version. 8/3/2017 1:36:36 PM
View EPC County Attorney's Office
7/28/2017 2:25:03 PM
This is still the wrong template. I made the necessary changes. 7/28/2017 2:25:03 PM
EPC County Attorney's Office
7/14/2017 10:26:56 AM
Many changes to the Detention Pond Agreement are needed. Please have the developer use the correct template. Developer has used the Developer/HOA template; please use the Developer/Owner template 7/14/2017 10:26:56 AM
PCD Engineering Division
6/19/2017 12:42:33 PM
Engineering comments are resolved. 6/19/2017 12:42:33 PM
EPC County Attorney's Office
6/16/2017 8:46:56 AM
File to Lori Seago for review.
Edi Anderson
6/16/2017 8:46:56 AM
PCD Project Manager
6/15/2017 5:02:28 PM
comments resolved. Need engineering approval before ready for signature. Will need detention pond review by County attorney prior to recording the agreement. 6/15/2017 5:02:28 PM
View PCD Project Manager
6/13/2017 6:53:54 AM
1. One tree and island is required per 15 spaces. No islands are included.
2. An original pond agreement with all exhibits is required prior to approval. Please see below for the revised pond agreement signature giving the PCD director authority to sign.



Executed this ________ day of _______________________, 20___, by:

BOARD OF COUNTY COMMISSIONERS
OF EL PASO COUNTY, COLORADO

By: _____________________________
Craig Dossey, Executive Director
Planning and Community Development
Authorized signatory pursuant to LDC




The foregoing instrument was acknowledged before me this _______ day of ______________, 20___, by __________________, Executive Director of Planning and Community Development
of El Paso County, Colorado.
Witness my hand and official seal.
My commission expires: __________________________________

_________________________________________
Notary Public
6/13/2017 6:53:54 AM
PCD Engineering Division
5/31/2017 11:32:34 AM
On the Grading and Erosion Control Plan, the concrete cutoff wall at the overflow spillway was removed. Keep the original approved pond design. 5/31/2017 11:32:34 AM
PCD Engineering Division
5/31/2017 11:15:06 AM
The grading & erosion control plan was inserted in the FDR instead of the updated drainage map. Update accordingly. 5/31/2017 11:15:06 AM