Project Review Comments

Back to List


Project Name
Woodmen Road Access Permit
Description
Applicant is requesting a right in off of Woodmen Road (expressway) on to a 40 acre parcel located at Woodmen Road and Meridian Road. Parcel No. 53000-00-589
Location
Northwest corner of Woodmen Road and Meridian Road
Applicant
DREXEL, BARRELL & CO.
Tim McConnell ( TMcConnell@drexelbarrell.com )
(719) 260-0887 x1219
Tim McConnell ( TMcConnell@drexelbarrell.com )
(719) 260-0887 x1219
EA Number
SP-17-001
File Number
AP17548
Project Manager
Kari Parsons
Status
Closed
Created
4/27/2017 1:25:16 PM

View: Project Documents



Review Comments (13)

Link Agency Comment
View PCD Engineering Division
12/5/2017 3:22:07 PM
See comment memo. 12/5/2017 3:22:07 PM
EPC County Attorney's Office
11/22/2017 9:56:16 AM
No comment from County Attorney at this time 11/22/2017 9:56:16 AM
PCD Project Manager
11/21/2017 8:22:10 AM
Staff will schedule your item for the Board of County Commissioners. Conditions of approval will be recommended. Staff will inform you of the hearing date shortly, and verify the date will work with your schedule. 11/21/2017 8:22:10 AM
EPC County Attorney's Office
8/31/2017 12:46:43 PM
No comment at this time. Please let me know if you need anything further. 8/31/2017 12:46:43 PM
View PCD Project Manager
8/28/2017 2:27:14 PM
Red lines of traffic study review 2 8/28/2017 2:27:14 PM
View PCD Project Manager
8/28/2017 2:24:29 PM
Multi-discipline letter review 2 8/28/2017 2:24:29 PM
PCD Project Manager
8/28/2017 2:11:28 PM
A minimum of two conditions of approval will be recommended to the Board of County Commissioners if the request is approved, (draft form below):
1. Applicant shall provide 90% percent complete construction drawings for the round-a-bout at Woodmen Road at the time of the next preliminary plan submittal prior to scheduling the preliminary plan for BoCC.
2. Applicant shall pay, at their sole expense, for the County to hire an outside consultant, at the County's discretion, to review and approve the round-a bout design and construction drawings at the time the CD's are submitted with the preliminary plan.
8/28/2017 2:11:28 PM
View PCD Engineering Division
8/24/2017 7:57:32 AM
See redlined TIS and comment letter to follow. 8/24/2017 7:57:32 AM
EPC County Attorney's Office
6/20/2017 10:52:07 AM
No comments at this time. Please contact County Attorney's Office if you have specific questions or issues. 6/20/2017 10:52:07 AM
EPC County Attorney's Office
5/31/2017 2:44:32 PM
Pending review by Lori Seago.
5/31/17
5/31/2017 2:44:32 PM
View PCD Project Manager
5/31/2017 10:44:25 AM
Combined comment letter 5/31/2017 10:44:25 AM
PCD Project Manager
5/30/2017 8:11:05 AM
Planning defers to the Engineering Division within the Planning and Community Development Department in addition to the comments provided by Public Works department. 5/30/2017 8:11:05 AM
Woodmen Road Metro
5/16/2017 4:34:12 PM
In response to the proposed project The Woodmen Road Metropolitan District supports this application. The reasons expressed in previous communications on this matter are still the Board’s position.

The Woodmen Road Metropolitan District was established in 2003 as a financing agent for the construction of Woodmen Road from Powers Boulevard to US 24. The expanded roadway was constructed and opened in 2008 funded by property taxes and fees paid by new development in the corridor. This has been a highly successful improvement for this part of the County and new and future development has and will continue to provide the funding to retire the bonds issued for Woodmen Road.

The Woodmen Road Metropolitan District is in favor of the County approving this proposed right in driveway improvement and the development that it will serve. We believe that this is a unique situation in the corridor and as such will not set a precedent for other access points. It is a logical improvement that will serve the property’s development and create additional fees and property tax revenue for the District to meet its obligations.

The Falcon Marketplace, located at the northwest corner of Woodmen Rd. and Meridian Rd., is within the District’s service area and if approved, will pay the fees and tax levies to the District once it is annexed to the District, platted and permitted. The District will coordinate the proper paperwork in accordance with the Intergovernmental Agreement between the District and the County. There are currently no funds budgeted or appropriated for any capital improvements in this corridor so the driveway will have to be funded through other sources.
5/16/2017 4:34:12 PM