View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Project Manager
5/25/2022 8:34:36 AM |
Attached is the site plan with additional comments from Engineering and Planning. | 5/25/2022 8:34:36 AM |
View |
PCD Project Manager
5/25/2022 8:27:31 AM |
please make sure the letter of intent and the site plan addresses all of the checkoff list requirements - see attached. | 5/25/2022 8:27:31 AM |
View |
PCD Project Manager
5/25/2022 8:25:12 AM |
Letter of intent redline v3 - engineering | 5/25/2022 8:25:12 AM |
PCD Engineering Division
5/19/2022 1:36:06 PM |
Review 3 comments will be uploaded by the project manager. Review comments on the following documents: - Letter of Intent - Site Plan Please contact engineer prior to next submittal. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
5/19/2022 1:36:06 PM | |
View |
PCD Project Manager
4/26/2022 3:40:44 PM |
Site Map Redlines | 4/26/2022 3:40:44 PM |
View |
PCD Project Manager
4/26/2022 3:40:27 PM |
Letter of Intent Redlines | 4/26/2022 3:40:27 PM |
PCD Engineering Division
4/6/2022 4:01:27 PM |
Review 2 comments will be uploaded by the project manager. Review comments on the following documents: - Unresolved comments on Letter of Intent - Site Plan There is no Driveway Access Waiver on file for existing driveway. A Driveway Access Waiver is required for all access points onto a private road within unincorporated El Paso County. Please apply for a driveway access waiver through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
4/6/2022 4:01:27 PM | |
View |
PCD Project Manager
3/31/2022 3:51:48 PM |
Site Plan Example | 3/31/2022 3:51:48 PM |
View |
PCD Project Manager
3/31/2022 3:45:04 PM |
Site Map Proposed Use Redlines | 3/31/2022 3:45:04 PM |
View |
PCD Project Manager
3/31/2022 3:44:21 PM |
Letter of Intent Redlines | 3/31/2022 3:44:21 PM |
Pikes Peak Regional Building Department
3/31/2022 10:55:19 AM |
Enumerations has no comment regarding this project at this time. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
3/31/2022 10:55:19 AM | |
PCD Engineering Division
3/29/2022 11:08:44 AM |
Review 1 comments will be uploaded by the project manager. Review comments on the following documents: - Letter of Intent - Site Plan There is no Driveway Access Waiver on file for existing driveway. A Driveway Access Waiver is required for all access points onto a private road within unincorporated El Paso County. Please apply for a driveway access waiver through EDARP, https://epcdevplanreview.com/ . Under "Getting Started" click on "Initiate a minor application", select Access Permit, and enter a valid email address. A verification code will be sent to the email provided. The verification code will be needed to access the application online. Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
3/29/2022 11:08:44 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/16/2022 10:00:03 AM |
We have no comments at this time. However, permanent structures, including foundation footings, are not allowed in the side lot easements. ____________________________________________________ Corey Masoumi | Engineering Support Coordinator Utilities Development Services | Colorado Springs Utilities 1521 S Hancock Expy Colorado Springs, CO 80903 O: 719-668-1856 | Main: 719-668-8259 cmasoumi@csu.org | www.csu.org |
3/16/2022 10:00:03 AM |