Agency | Comment | ||
---|---|---|---|
PCD Project Manager
10/21/2021 4:16:11 PM |
No additional Planning comments at this time. Pending approval. | 10/21/2021 4:16:11 PM | |
PCD Engineering Division
10/18/2021 11:24:21 AM |
There are no further engineering comments relating to drainage or transportation. Any approved documents will be uploaded by the project manager. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
10/18/2021 11:24:21 AM | |
View |
PCD Project Manager
10/8/2021 4:23:51 PM |
Please see redline comments on Drainage Report | 10/8/2021 4:23:51 PM |
PCD Engineering Division
10/4/2021 4:50:32 PM |
The project manager will upload comments. Please address comments to get approval started. Submit the signed and stamped documents for approval: -Drainage report -GEC plan Comments have been resolved in the Letter of Intent. Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
10/4/2021 4:50:32 PM | |
View |
Mountain View Electric Association, Inc.
9/29/2021 8:52:10 AM |
See attached comments | 9/29/2021 8:52:10 AM |
EPC Stormwater Review
9/23/2021 2:35:14 PM |
Review 3: EPC Stormwater comments have been resolved on the following documents: - Drainage Report - GEC Checklist - SWMP Checklist - SWMP EPC Stormwater has no further comments at this time. Thanks. Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
9/23/2021 2:35:14 PM | |
View |
PCD Project Manager
8/26/2021 2:32:32 PM |
Please see redline comments on soils report | 8/26/2021 2:32:32 PM |
View |
PCD Project Manager
8/26/2021 2:31:03 PM |
Please see redline comments on Site Development Plan | 8/26/2021 2:31:03 PM |
View |
PCD Project Manager
8/26/2021 2:30:21 PM |
Please see redline comments on Letter of Intent | 8/26/2021 2:30:21 PM |
View |
PCD Project Manager
8/26/2021 2:29:48 PM |
Please see redline comments on Landscape Plan Drawings | 8/26/2021 2:29:48 PM |
View |
PCD Project Manager
8/26/2021 2:29:18 PM |
Please see redline comments on Drainage Report | 8/26/2021 2:29:18 PM |
View |
PCD Project Manager
8/26/2021 2:28:50 PM |
Please see redline comments on Application Form | 8/26/2021 2:28:50 PM |
PCD Engineering Division
8/25/2021 10:29:40 AM |
Review 2 comments will be uploaded by the project manager. Please address comments on the following documents: -Letter of Intent -Drainage Report Comments have been resolved on the following documents, please submit documents with appropriate stamps/signatures once PCD Engineering comments and EPC Stormwater comments have been completely resolved. -FAE -GEC plans -Site Plan Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
8/25/2021 10:29:40 AM | |
View |
EPC Stormwater Review
8/25/2021 8:12:20 AM |
SWMP_v2 | 8/25/2021 8:12:20 AM |
View |
EPC Stormwater Review
8/25/2021 8:12:06 AM |
SWMP Checklist_v2 | 8/25/2021 8:12:06 AM |
View |
EPC Stormwater Review
8/25/2021 8:11:49 AM |
GEC Checklist_v2 | 8/25/2021 8:11:49 AM |
Mountain View Electric Association, Inc.
8/23/2021 11:41:25 AM |
Please reference the letter dated February 1, 2021 for AL215 - no additional comments at this time. | 8/23/2021 11:41:25 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/10/2021 11:50:15 AM |
No further comments. Approval is recommended. Caleb Savage cjsavage@csu.org 719-668-1855 |
8/10/2021 11:50:15 AM | |
EPC Stormwater Review
8/9/2021 1:57:14 PM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments) - GEC Checklist - SWMP Checklist - SWMP EPC Stormwater comments have been resolved on the following documents: - FAE - GEC Plan - PBMP Applicability Form Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
8/9/2021 1:57:14 PM | |
View |
PCD Project Manager
5/31/2021 10:23:54 AM |
Please see redline comments for Site Development Plan | 5/31/2021 10:23:54 AM |
View |
PCD Project Manager
5/31/2021 10:23:14 AM |
Please see redline comments for Letter of Intent | 5/31/2021 10:23:14 AM |
View |
PCD Project Manager
5/31/2021 10:22:40 AM |
Please see redline comments for Landscape Plans | 5/31/2021 10:22:40 AM |
View |
PCD Project Manager
5/31/2021 10:22:05 AM |
Please see redline comments for GEC Plan | 5/31/2021 10:22:05 AM |
View |
PCD Project Manager
5/31/2021 10:21:25 AM |
Please see redline comments for FAE | 5/31/2021 10:21:25 AM |
View |
PCD Project Manager
5/31/2021 10:20:55 AM |
Please see redline comments for Drainage Report | 5/31/2021 10:20:55 AM |
View |
PCD Project Manager
5/31/2021 10:20:03 AM |
Please see redline comments for application form | 5/31/2021 10:20:03 AM |
PCD Engineering Division
5/25/2021 8:50:38 AM |
Review 1 comments will be uploaded by the project manager. Please address comments on the following documents: -Drainage letter -Site development plan -GEC plan -Letter of intent -Financial assurance form Reviewed by: Lupe Packman Review Engineer lupepackman@elpasoco.com |
5/25/2021 8:50:38 AM | |
View |
EPC Stormwater Review
5/24/2021 10:43:31 AM |
PBMP Applicability Form_v1 | 5/24/2021 10:43:31 AM |
View |
EPC Stormwater Review
5/24/2021 10:43:18 AM |
Grading & Erosion Control checklist_v1 | 5/24/2021 10:43:18 AM |
EPC Stormwater Review
5/24/2021 9:46:34 AM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments) - FAE........................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - PBMP Applicability Form Please include the following documents on resubmittal: - ESQCP - SWMP John - please open an EDARP submittal request for the ESQCP, SWMP, and Geotech Report (which was attached to the GEC Plan). Reviewed by: Glenn Reese, P.E. Stormwater Engineer I glennreese@elpasoco.com |
5/24/2021 9:46:34 AM | |
Pikes Peak Regional Building Department
5/20/2021 4:06:57 PM |
7105 Meridian Ranch Road address should be used for this building. Old Meridian Way is not correct. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
5/20/2021 4:06:57 PM | |
View |
Mountain View Electric Association, Inc.
5/18/2021 2:55:53 PM |
See attached comments | 5/18/2021 2:55:53 PM |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/11/2021 9:06:43 AM |
5/11/2021 9:06:43 AM | |
Upper Black Squirrel Creek GWMD
5/5/2021 2:43:32 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment later if need be. | 5/5/2021 2:43:32 PM | |
County Attorney - Development Review
5/5/2021 1:45:30 PM |
No comments at this time. | 5/5/2021 1:45:30 PM | |
911 Authority - El Paso/Teller County
4/29/2021 8:40:13 AM |
No new street names requested. No action for E911. Thank you. Justin |
4/29/2021 8:40:13 AM | |
View |
Falcon Fire Protection District
4/28/2021 12:38:09 PM |
4/28/2021 12:38:09 PM |