View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
10/1/2020 10:13:29 AM |
PCD Planning Division has no further comments at this time. Project Manager will schedule a meeting to discuss approval with PCD Director. | 10/1/2020 10:13:29 AM | |
County Attorney - Development Review
9/26/2020 5:35:02 PM |
No comment from County Attorney's Office at this time. | 9/26/2020 5:35:02 PM | |
PCD Engineering Division
9/22/2020 12:43:21 PM |
PCD Engineering has no comment on this item. (the site has an access permit AP20825) Steve Kuehster PCD Engineering 719-520-6813 |
9/22/2020 12:43:21 PM | |
PCD Project Manager
9/22/2020 9:13:00 AM |
Per PPRBD comment, please resubmit site plan with correct address for site shown. | 9/22/2020 9:13:00 AM | |
Pikes Peak Regional Building Department
9/22/2020 8:35:56 AM |
The applicant was advised to correct all pages of the plan set with RBD to the new address of 7113 Marshbern Court. This has been done and should be submitted into the next review. In future submittals to the El Paso County Development Services the new address should be used. No further comment. |
9/22/2020 8:35:56 AM | |
PCD Project Manager
9/16/2020 10:31:28 AM |
Pursuant to CFR Sec. 1.40001, Planning Division has no comments on this request, as the request does not constitute a substantial change to the physical dimensions of the structure. | 9/16/2020 10:31:28 AM | |
View |
Mountain View Electric Association, Inc.
9/10/2020 3:01:50 PM |
9/10/2020 3:01:50 PM |