Project Review Comments

Back to List


Project Name
Retreat at TimberRidge Filing No. 2
Description
90 single-family detached lots 78 lots to be served by Central water, 12 lots to be served by Well, 78 lots to be served by central sewer, and 12 lots by OWTS.
Location
Applicant
Classic Consulting Engineers & Surveyors, LLC
PM Marc Whorton ( Mwhorton@classicconsulting.net )
(719) 785-2802
PM Marc Whorton ( Mwhorton@classicconsulting.net )
(719) 785-2802
EA Number
EA1895
File Number
SF2121
Project Manager
Kari Parsons
Status
Closed
Created
12/19/2018 3:15:08 PM

View: Project Documents



Review Comments (117)

Link Agency Comment
PCD Project Manager
9/15/2022 12:27:36 PM
All docs have been received and signed. 9/15/2022 12:27:36 PM
View County Attorney - Development Review
9/15/2022 11:26:07 AM
Signature to SIA attached. Please ensure that collateral amount in paragraph 1 is filled out before recording. 9/15/2022 11:26:07 AM
View County Attorney - Development Review
9/15/2022 11:21:44 AM
Signature to ROW License Agreement attached. 9/15/2022 11:21:44 AM
County Attorney - Development Review
8/25/2022 11:57:29 AM
No further comments from County Attorney - Development Review. 8/25/2022 11:57:29 AM
View PCD Engineering Division
8/22/2022 10:01:06 AM
(Wetland mitigation plans redlines) 8/22/2022 10:01:06 AM
View PCD Engineering Division
8/22/2022 9:59:17 AM
(Drainage plan redlines summary) 8/22/2022 9:59:17 AM
View PCD Engineering Division
8/22/2022 9:58:18 AM
See comment letter (link at left) and redlines.

The following items need to be submitted:
- Updated drainage plan
- Exhibit C wetlands mitigation area description and exhibit for channel maintenance agreement
- Wetlands mitigation plan/permit
- License agreement for lights/mail kiosks with exhibit

Ensure that all items highlighted in blue on the Engineering Final Submittal checklist are provided, signed and stamped where needed, including the following:
- Floodplain development permit (when available)
- Dewatering permit (when available)


-- Jeff Rice - 719-520-7877
8/22/2022 9:58:18 AM
View County Attorney - Development Review
7/14/2022 11:26:31 AM
Signature to Channel Maintenance Agreement attached. DO NOT RECORD until Exhibit C has been added. 7/14/2022 11:26:31 AM
View County Attorney - Development Review
7/14/2022 11:26:00 AM
Signature to Detention Maintenance Agreement attached. 7/14/2022 11:26:00 AM
PCD Project Manager
7/6/2022 2:17:31 PM
Recording pending the contracts being finalized at the revisions to wetlands mitigation plan 7/6/2022 2:17:31 PM
View PCD Engineering Division
7/6/2022 1:48:21 PM
(NEPE form if needed) 7/6/2022 1:48:21 PM
View PCD Engineering Division
7/6/2022 1:45:45 PM
(Channel mitigation plan redlines) 7/6/2022 1:45:45 PM
View PCD Engineering Division
7/6/2022 1:44:57 PM
See comment letter (link at left) and redlines.

The following items need to be submitted:
- Exhibit C wetlands mitigation area description and exhibit for channel maintenance agreement
- Wetlands mitigation plan/permit
- License agreement for lights with exhibit

Ensure that all items highlighted in blue on the Engineering Final Submittal checklist are provided, signed and stamped where needed, including the following:
- Floodplain development permit (when available)
- Dewatering permit (when available)


-- Jeff Rice - 719-520-7877
7/6/2022 1:44:57 PM
View County Attorney - Development Review
6/28/2022 3:01:02 PM
1. County signature block on SIA amended to reflect administrative plat approval.
2. There are multiple drafts of the Detention Maintenance Agreement uploaded, causing confusion. The correct draft is the Channel Maintenance Agreement uploaded 6-8-22. It is missing an Exhibit C, however. Also, please ensure that Exhibit B is correct. Previous drafts of this agreement identified Tract A and Lots 4, 5, 7, 10, and 11 as having drainage improvements. I will sign once all exhibits are attached.
6/28/2022 3:01:02 PM
PCD Project Manager
6/20/2022 5:40:48 PM
no comments from planning 6/20/2022 5:40:48 PM
View PCD Engineering Division
6/17/2022 12:35:49 PM
(Stormwater Facility Maintenance Agreement previously emailed on 6/1) 6/17/2022 12:35:49 PM
View PCD Engineering Division
6/17/2022 12:36:26 PM
See comment letter (link at left) and redlines.

The following items need to be submitted:
- Channel maintenance agreement for Filing 2 including Exhibit C wetlands mitigation area description and exhibit
(An old version was submitted - see email dated 6/1, agreement attached below.)
- Utility CDs - Delete extra sheet 7 and provide all signatures.
- Wetlands mitigation plan/permit
- License agreement for lights with exhibit
- CAD base drawing

The following items need to be provided prior to approval of CDs or added as conditions prior to NTP:
- Offsite easements
- Geotechnical recommendations per comment letter

Ensure that all items highlighted in blue on the Engineering Final Submittal checklist are provided, signed and stamped where needed, including the following:
- Floodplain development permit (when available)
- Dewatering permit (when available)


-- Jeff Rice - 719-520-7877
6/17/2022 12:36:26 PM
PCD Project Manager
6/1/2022 10:09:03 AM
Please change the resolution for the Traffic Fee program note to 19-471. 6/1/2022 10:09:03 AM
View PCD Engineering Division
5/27/2022 12:34:52 PM
See comment letter (link at left) and redlines.

The following items need to be submitted:
- Channel maintenance agreement for Filing 2 including wetlands mitigation area exhibit
- TIS (signed)
- Utility CDs
- Wetlands mitigation plan/permit
- License agreement for lights with exhibit
- CAD base drawing

The following items need to be provided prior to approval of CDs or added as conditions prior to NTP:
- Offsite easements
- Response or approved permit from State Engineer for pond embankment
- Geotechnical recommendations per comment letter

Ensure that all items highlighted in blue on the Engineering Final Submittal checklist are provided, signed and stamped where needed, including the following:
- Floodplain development permit (when available)
- Dewatering permit (when available)


-- Jeff Rice - 719-520-7877
5/27/2022 12:34:52 PM
EPC Stormwater Review
6/3/2022 1:14:33 PM
All Stormwater comments have been resolved.

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
6/3/2022 1:14:33 PM
View PCD Project Manager
5/17/2022 10:22:50 AM
Plat comments - Now administrative 5/17/2022 10:22:50 AM
View PCD Administrative Notice
5/16/2022 11:03:09 AM
Notification letter 5/16/2022 11:03:09 AM
View PCD Administrative Notice
5/16/2022 11:02:17 AM
Mailing labels 5/16/2022 11:02:17 AM
View PCD Administrative Notice
5/16/2022 11:01:56 AM
Vicinity map 5/16/2022 11:01:56 AM
View PCD Engineering Division
4/26/2022 3:35:13 PM
(O&M Manual redlines) 4/26/2022 3:35:13 PM
View PCD Engineering Division
4/26/2022 2:53:26 PM
(PDB-BMP Agreement from Filing 1 - this may not have been the final version and needs to be edited for Filing 2. We need corresponding exhibits to be attached) 4/26/2022 2:53:26 PM
View PCD Engineering Division
4/26/2022 2:51:11 PM
(CDs redlines summary) 4/26/2022 2:51:11 PM
View PCD Engineering Division
4/26/2022 2:50:26 PM
(CDs redlines) 4/26/2022 2:50:26 PM
View PCD Engineering Division
4/26/2022 2:47:48 PM
(Deviation request redlines) 4/26/2022 2:47:48 PM
View PCD Engineering Division
4/26/2022 2:46:57 PM
(FDR redlined page) 4/26/2022 2:46:57 PM
View PCD Engineering Division
4/26/2022 2:46:07 PM
(Plat redlines) 4/26/2022 2:46:07 PM
View PCD Engineering Division
4/27/2022 10:51:20 AM
See comment letter (link at left) and redlines.

The following items need to be revised and resubmitted:
- Final Plat (addition to note #18)
- FDR (add sentence to page 23)
- CDs (including GEC Plan)
- Deviation request
- O&M Manual (minor revisions)
- Channel maintenance agreement for Filing 2 (new)
- SWMP Checklist (sign)

The following items need to be provided prior to approval of CDs or added as conditions prior to NTP:
- Offsite easements
- Wetlands mitigation plan/permit
- Response or approved permit from State Engineer for pond embankment

Ensure that all items highlighted in blue on the Engineering Final Submittal checklist are provided, signed and stamped where needed, including the following:
- TIS
- Floodplain development permit (when available)
- Dewatering permit (when available)


-- Jeff Rice - 719-520-7877
4/27/2022 10:51:20 AM
View PCD Engineering Division
3/8/2022 7:23:39 PM
(FAE redlines) 3/8/2022 7:23:39 PM
View PCD Engineering Division
3/8/2022 7:22:24 PM
(CD redlines summary) 3/8/2022 7:22:24 PM
View PCD Engineering Division
3/8/2022 7:21:45 PM
(CD redlines) 3/8/2022 7:21:45 PM
View PCD Engineering Division
3/8/2022 7:20:32 PM
(FDR redlines summary) 3/8/2022 7:20:32 PM
View PCD Engineering Division
3/8/2022 7:17:34 PM
(FDR redlines) 3/8/2022 7:17:34 PM
View PCD Engineering Division
3/8/2022 7:16:34 PM
(Final Plat redlines) 3/8/2022 7:16:34 PM
View PCD Engineering Division
3/8/2022 7:15:50 PM
See comment letter (link at left) and redlines.

The following items need to be revised and resubmitted:
- Final Plat
- FDR
- GEC Plan / CDs
- FAE
- Items with Stormwater comments

Ensure that all items highlighted in blue on the Engineering Final Submittal checklist are provided, signed and stamped where needed.

-- Jeff Rice - 719-520-7877
3/8/2022 7:15:50 PM
Upper Black Squirrel Creek GWMD
3/2/2022 1:51:48 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals. 3/2/2022 1:51:48 PM
View EPC Stormwater Review
2/16/2022 5:13:23 PM
PBMP 2/16/2022 5:13:23 PM
EPC County Attorney's Office
2/11/2022 1:53:43 PM
County Attorney's Office submitted review of water sufficiency on 12/15/21 - please advise if anything further is needed. Applicant will need to satisfy all requirements of water review (see page 4, et al. of water review). Thank you. 2/11/2022 1:53:43 PM
EPC Stormwater Review
2/16/2022 3:59:00 PM
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report (to be uploaded by PM with PCD comments)
- CD (to be uploaded by PM with PCD comments)
- PBMP Applicability Form

Please provide revised documents for review (see Review 2 comments):
- GEC Checklist
- SWMP
- SWMP Checklist
- Maintenance Agreement
- Operations and Maintenance Manual

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
2/16/2022 3:59:00 PM
County Attorney - Development Review
2/10/2022 3:12:21 PM
No further comments from County Attorney - Development Review at this time. 2/10/2022 3:12:21 PM
View EPC County Attorney's Office
12/15/2021 2:03:15 PM
Attached please find County Attorney's Office water review. 12/15/2021 2:03:15 PM
View EPC Health Department
12/10/2021 5:35:38 PM
12/10/2021 5:35:38 PM
View PCD Engineering Division
12/10/2021 3:26:00 PM
(PDB-BMP redlines) 12/10/2021 3:26:00 PM
View PCD Engineering Division
12/10/2021 3:25:22 PM
(FAE redlines) 12/10/2021 3:25:22 PM
View PCD Engineering Division
12/10/2021 3:24:41 PM
(Utility CD redlines) 12/10/2021 3:24:41 PM
View PCD Engineering Division
12/10/2021 3:24:10 PM
(CD redlines summary) 12/10/2021 3:24:10 PM
View PCD Engineering Division
12/10/2021 3:23:47 PM
(CD redlines) 12/10/2021 3:23:47 PM
View PCD Engineering Division
12/10/2021 3:23:15 PM
(FDR redlines summary) 12/10/2021 3:23:15 PM
View PCD Engineering Division
12/10/2021 3:22:45 PM
(FDR redlines) 12/10/2021 3:22:45 PM
View PCD Engineering Division
12/10/2021 3:22:12 PM
(Plat redlines summary) 12/10/2021 3:22:12 PM
View PCD Engineering Division
12/10/2021 3:21:39 PM
(Plat redlines) 12/10/2021 3:21:39 PM
View PCD Engineering Division
12/10/2021 3:21:00 PM
See comment letter (link at left) and redlines.

The following items need to be revised and resubmitted:
- Final Plat
- FDR
- GEC Plan / CDs
- Utility CDs
- FAE
- Items with Stormwater comments


-- Jeff Rice - 719-520-7877
12/10/2021 3:21:00 PM
County Attorney - Development Review
12/3/2021 1:37:56 PM
No further comments from County Attorney - Development Review at this time. 12/3/2021 1:37:56 PM
View EPC Stormwater Review
12/2/2021 4:16:49 PM
PBMP_v2 12/2/2021 4:16:49 PM
View EPC Stormwater Review
12/2/2021 4:16:27 PM
Maintenance Agreement_v2 12/2/2021 4:16:27 PM
View EPC Stormwater Review
12/2/2021 4:16:00 PM
SWMP Checklist_v2 12/2/2021 4:16:00 PM
View EPC Stormwater Review
12/2/2021 4:14:01 PM
SWMP_v2 12/2/2021 4:14:01 PM
View EPC Stormwater Review
12/2/2021 4:13:22 PM
GEC Checklist_v2 12/2/2021 4:13:22 PM
PCD Project Manager
11/30/2021 1:37:31 PM
Planning Staff has no further comments. Planning awaits a water finding from CAO and resolution of engineering comments before scheduling the item for PC and BOCC. 11/30/2021 1:37:31 PM
View Upper Black Squirrel Creek GWMD
11/29/2021 6:42:19 PM
11/29/2021 6:42:19 PM
EPC Stormwater Review
12/2/2021 4:20:31 PM
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- Drainage Report (to be uploaded by PM with PCD comments)
- CD (to be uploaded by PM with PCD comments)
- FAE (to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP
- SWMP Checklist
- Maintenance Agreement
- PBMP Applicability Form

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
12/2/2021 4:20:31 PM
View Parks Advisory Board
11/23/2021 3:41:08 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents for Revised Recommendations (PAB Endorsed June 2021) 11/23/2021 3:41:08 PM
View EPC Parks Department
11/23/2021 3:39:18 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents for Revised Recommendations (PAB Endorsed June 2021) 11/23/2021 3:39:18 PM
Pikes Peak Regional Building Department
11/22/2021 12:33:19 PM
Regarding a request for approval of a final plat for Retreat at Timberridge Filign No. 2, Enumerations has no further comments. Previous comments still apply.


Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
11/22/2021 12:33:19 PM
View Colorado Division of Water Resources
11/22/2021 11:12:08 AM
11/22/2021 11:12:08 AM
Mountain View Electric Association, Inc.
11/22/2021 9:33:35 AM
Please reference comment letters dated February 28, 2021 and June 7, 2021. No additional comments at this time. 11/22/2021 9:33:35 AM
US Postal Service
11/17/2021 12:46:10 PM
Standard comment for Post Office
Contact Elaine Kelly – elaine.f.kelly@usps.gov and Rita Minnard oreta.j.minnard@usps.gov / 719-570-5592 to review development for mail service.
Confirm all pad location prior to final plat or it may be disapproved due to current Postal Regulations.
11/17/2021 12:46:10 PM
View El Paso County Conservation Dist
11/10/2021 11:54:09 AM
11/10/2021 11:54:09 AM
View El Paso County Conservation Dist
11/10/2021 11:53:28 AM
11/10/2021 11:53:28 AM
911 Authority - El Paso/Teller County
11/8/2021 8:42:57 AM
Streetnames previously approved.
No action for E911.
Thank you.
Justin
11/8/2021 8:42:57 AM
Colorado Parks and Wildlife
11/4/2021 5:15:05 PM
Colorado Parks and Wildlife appreciates the opportunity to comment. CPW has commented with previous iterations of this project area, and would reference previous comments submitted. CPW understands that the Sand Creek drainage runs though the project area and recommends that the drainage be altered to the least extent possible and that the Army Corp of Engineers is consulted about any proposed changes to the drainage.

Please feel free to contact District Wildlife Manager, Aaron Berscheid, should you have any questions or require additional information at 719-227-5231 or via email at aaron.berscheid@state.co.us
11/4/2021 5:15:05 PM
View EPC Environmental Services
11/4/2021 1:29:55 PM
11/4/2021 1:29:55 PM
EPC County Attorney's Office
9/2/2021 11:52:13 AM
Applicant:
1. Please upload the augmentation plan (18CW3002) to EDARP. (17CW3002 - the decree - is included but not the augmentation plan)
2. Please upload the referenced Ex. A to the District’s commitment letter.
3. Please update documentation for the water demand for the rural lots so all documents are consistent (ie. clarify if the demand is .29 AF/lot or .32 AF/lot and clarify the overall water demand for the subdivision) and ensure documentation is consistent with the augmentation plan. Thank you.
9/2/2021 11:52:13 AM
View PCD Engineering Division
7/7/2021 10:13:16 AM
(ESQCP redlines) 7/7/2021 10:13:16 AM
View PCD Engineering Division
7/7/2021 10:12:50 AM
(CD/GEC redlines summary) 7/7/2021 10:12:50 AM
View PCD Engineering Division
7/7/2021 10:12:29 AM
(CD/GEC redlines) 7/7/2021 10:12:29 AM
View PCD Engineering Division
7/7/2021 10:11:52 AM
(FAE redlines) 7/7/2021 10:11:52 AM
View PCD Engineering Division
7/7/2021 10:11:26 AM
(FDR redlines summary) 7/7/2021 10:11:26 AM
View PCD Engineering Division
7/7/2021 10:10:59 AM
(FDR redlines) 7/7/2021 10:10:59 AM
View PCD Engineering Division
7/6/2021 9:55:02 PM
(Wetlands permit redlines) 7/6/2021 9:55:02 PM
View PCD Engineering Division
7/6/2021 9:54:15 PM
(TIS redlines summary) 7/6/2021 9:54:15 PM
View PCD Engineering Division
7/6/2021 9:53:45 PM
(TIS redlines) 7/6/2021 9:53:45 PM
View PCD Engineering Division
7/6/2021 9:52:04 PM
(Plat redlines summary) 7/6/2021 9:52:04 PM
View PCD Engineering Division
7/6/2021 9:51:25 PM
(Plat redlines) 7/6/2021 9:51:25 PM
View PCD Engineering Division
7/6/2021 9:49:59 PM
See comment letter and redlines.

The following items need to be revised and resubmitted:
- Final Plat
- FDR
- TIS
- GEC Plan / CDs
- FAE
- Items with Stormwater comments


-- Jeff Rice - 719-520-7877
7/6/2021 9:49:59 PM
View EPC Stormwater Review
7/6/2021 4:32:03 PM
O&M_v1 7/6/2021 4:32:03 PM
View EPC Stormwater Review
7/6/2021 4:28:11 PM
MS4_v1 7/6/2021 4:28:11 PM
View EPC Stormwater Review
7/6/2021 4:22:26 PM
SWMP_v1 7/6/2021 4:22:26 PM
View PCD Project Manager
6/24/2021 3:53:01 PM
Letter of Intent Planning comments:
Please address Section 7.2.1 approval criteria which does include Master plan and Water Master Plan compliance.
See redlines for excerpts from each Plan.
6/24/2021 3:53:01 PM
View PCD Project Manager
6/24/2021 3:42:16 PM
FAE Planning only comments 6/24/2021 3:42:16 PM
View PCD Project Manager
6/24/2021 3:41:53 PM
Plat Planning only comments 6/24/2021 3:41:53 PM
PCD Project Manager
6/24/2021 3:38:06 PM
Add and address in LOI
7.2.1 Criteria for Approval. In approving a final plat, the approving authority shall find that:
• The subdivision is in conformance with the goals, objectives, and policies of the Master Plan;

• The subdivision is in substantial conformance with the approved preliminary plan;

• The subdivision is consistent with the subdivision design standards and regulations and meets all planning, engineering, and surveying requirements of the County for maps, data, surveys, analyses, studies, reports, plans, designs, documents, and other supporting materials;

• Either a sufficient water supply has been acquired in terms of quantity, quality, and dependability for the type of subdivision proposed, as determined in accordance with the standards set forth in the water supply standards [C.R.S. § 30-28-133(6)(a)] and the requirements of Chapter 8 of this Code, or, with respect to applications for administrative final plat approval, such finding was previously made by the BoCC at the time of preliminary plan approval;

• A public sewage disposal system has been established and, if other methods of sewage disposal are proposed, the system complies with State and local laws and regulations, [C.R.S. § 30-28-133(6)(b)] and the requirements of Chapter 8 of this Code;

• All areas of the proposed subdivision which may involve soil or topographical conditions presenting hazards or requiring special precautions have been identified and that the proposed subdivision is compatible with such conditions [C.R.S. § 30-28-133(6)(c)];

• Adequate drainage improvements are proposed that comply with State Statute [C.R.S. § 30-28-133(3)(c)(VIII)] and the requirements of this Code and the ECM;

• Legal and physical access is provided to all parcels by public rights-of-way or recorded easement, acceptable to the County in compliance with this Code and the ECM;

• Necessary services, including police and fire protection, recreation, utilities, and transportation systems, are or will be made available to serve the proposed subdivision;

• The final plans provide evidence to show that the proposed methods for fire protection comply with Chapter 6 of this Code;

• Off-site impacts were evaluated and related off-site improvements are roughly proportional and will mitigate the impacts of the subdivision in accordance with applicable requirements of Chapter 8;

• Adequate public facilities or infrastructure, or cash-in-lieu, for impacts reasonably related to the proposed subdivision have been constructed or are financially guaranteed through the SIA so the impacts of the subdivision will be adequately mitigated;

• The subdivision meets other applicable sections of Chapter 6 and 8; and

• The extraction of any known commercial mining deposit shall not be impeded by this subdivision [C.R.S. §§ 34-1-302(1), et seq.]
6/24/2021 3:38:06 PM
PCD Project Manager
6/24/2021 10:34:09 AM
Gas Commitment Letter is only for 12 lots and it also states within City of Colorado Springs. Please provide an more accurate letter for the entire subdivision. 6/24/2021 10:34:09 AM
PCD Project Manager
6/24/2021 10:26:35 AM
Please provide a draft copy with exhibits of the easements for the offsite construction, and drainage. 6/24/2021 10:26:35 AM
PCD Project Manager
6/24/2021 10:25:04 AM
Based on the comments provided by the EPCPHE, engineered septic systems would be required for this area of development. Please provide the notes on the plat stating which lots will require the engineered septic systems. 6/24/2021 10:25:04 AM
PCD Project Manager
6/24/2021 9:53:42 AM
The Subdivision Summary forms states something different the the commitment letter and the application. It states 90 lots are proposed and of that 90, 12 are to be on well and septic....all documentation shall match throughout the application please. 6/24/2021 9:53:42 AM
PCD Project Manager
6/24/2021 10:20:34 AM
Please provide a stand alone wastewater disposal report for the on-site wastewater treatment system lots, and a report that addresses the lots to be served by central sewer provider. The report provided does not meet the standards identified in Chapter 8 of the Code, section 8.4.8. The OWTS and Central Provider for Sewer reports (OWTS and Central provider report if combined) should address the criteria in chapter 8.4.8. Reports can not be combined with the geology and soils report as of 9/2019; however the EPCHD has provided a finding that septic systems can be provided with the information provided. It is not stated in the report how many lots will be served by OWRS in this filing. Please provide a report addressing the central services for sewer and update the OWTS w/ a supplement.
Per the water/wastewater commitment provided with the application,"164 lots are to be served by Sterling Ranch Metro for wastewater, an 3 lots to be served by OWTS per the commitment letter. ...All lots are proposed to be served by Central water."

This conflicts with other docs in application.
Please revise the commitment letter to be clear for what is being provided in this filing and what number of lots are to be served by central services verses on-site service.

The application says only 90 lots are proposed. Are 12 lots to be served by well and septic?
6/24/2021 10:20:34 AM
PCD Project Manager
6/22/2021 4:01:08 PM
Staff understands applicant has submitted a wetland mitigation plan for approval to the Army Corps of Engineers. Please provide a copy of that mitigation plan. Staff acknowledged the plan is under review. 6/22/2021 4:01:08 PM
EPC Stormwater Review
7/6/2021 4:18:38 PM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CD (to be uploaded by PM with PCD comments)
- Drainage Report (to be uploaded by PM with PCD comments)
- ESQCP (to be uploaded by PM with PCD comments)
- SWMP
- MS4 Post Construction Form
- O&M Manual

Please provide the following documents for review with resubmittal:
- GEC Checklist
- SWMP Checklist
- PBMP Applicability Form
https://publicworks.elpasoco.com/stormwater/

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
7/6/2021 4:18:38 PM
View EPC Health Department
6/20/2021 4:38:44 PM
6/20/2021 4:38:44 PM
View County Attorney - Development Review
6/18/2021 2:55:16 PM
Proposed amendments to SIA attached. 6/18/2021 2:55:16 PM
View County Attorney - Development Review
6/18/2021 2:54:52 PM
Proposed amendment to Detention Maintenance Agreement attached. 6/18/2021 2:54:52 PM
View EPC Parks Department
6/17/2021 1:45:54 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (PAB Endorsed 06/08/2021) 6/17/2021 1:45:54 PM
View Parks Advisory Board
6/17/2021 1:43:47 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (PAB Endorsed 06/09/2021) 6/17/2021 1:43:47 PM
Woodmen Hills Metro
6/15/2021 9:12:38 AM
Woodmen Hills Metropolitan District has no comment. 6/15/2021 9:12:38 AM
View Colorado Division of Water Resources
6/9/2021 8:34:35 AM
6/9/2021 8:34:35 AM
Pikes Peak Regional Building Department
6/8/2021 8:45:53 AM
Regarding a request for approval of a final plat for Retreat at Timberridge Filing No. 2, Enumerations has the following comments:

1. Per Regional Building Code, section RBC312.8 addresses must appear on plats. Submit a 100 scale copy of the plat to our office for addressing. Place an (xxxx) on all lots and tracts which will require an address, in the location the address will be needed. Once addressing is completed, the addresses will be returned so that they may be placed on the mylar prior to recording.
2. Prior to recording, Enumerations will review the mylar for addressing, title block, street names and floodplain statement. A fee of $10 per lot/tract addressed, payable to Pikes Peak Regional Building Department will be due at the time of mylar review.
3. Provide a copy of the final recorded plat to Enumerations. Approval of any plans submitted for this development will be pending receipt in our office of a copy of the final recorded plat.




Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
6/8/2021 8:45:53 AM
View Mountain View Electric Association, Inc.
6/7/2021 4:34:38 PM
See attached comments 6/7/2021 4:34:38 PM
Upper Black Squirrel Creek GWMD
6/2/2021 1:15:59 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but reserves the right to comment in the future. 6/2/2021 1:15:59 PM
911 Authority - El Paso/Teller County
6/2/2021 11:48:25 AM
All names on this submittal have been previously approved.
No action for E911

Bison Valley Trl – Previously approved
Owl Perch Loop – Previously approved
Elk Antler Ln – Previously approved
Falcon Nest Ct – Previously approved
Aspen Valley Rd – Previously approved

Thank you
Justin
6/2/2021 11:48:25 AM
View El Paso County Conservation Dist
6/1/2021 9:54:15 AM
6/1/2021 9:54:15 AM
View El Paso County Conservation Dist
6/1/2021 9:53:25 AM
6/1/2021 9:53:25 AM
View EPC Environmental Services
5/27/2021 3:02:21 PM
5/27/2021 3:02:21 PM