PCD Engineering Division
2/20/2019 11:03:37 AM |
GEC Plan Redlines. Note: The FDR will need some minor cleanup on the drainage plans to match the GEC Plan for final approvals. |
2/20/2019 11:03:37 AM |
PCD Engineering Division
2/20/2019 10:38:37 AM |
The latest submitted documents Drainage, Grading and Erosion Control are accepted for the purposes of the 1041 submittal, They are stamped as such. Redlines were made on the Grading and Erosion Control plans for the purposes of the Site Development Plan Submittal; they have been uploaded. (The Grading and Erosion Control & Drainage Report will be signed by the County Engineer/ECM Administrator as part of finalizing the Site Development Plan. | 2/20/2019 10:38:37 AM | |
Woodmoor Water and Sanitation District
2/19/2019 9:52:22 AM |
No Comments | 2/19/2019 9:52:22 AM | |
View |
PCD Project Manager
2/4/2019 8:17:38 AM |
Drainage Report Summary V_2 | 2/4/2019 8:17:38 AM |
View |
PCD Project Manager
2/4/2019 8:17:04 AM |
Drainage Redlines V_2. Please contact Jeff Rice if you have questions. 719-520-7877. | 2/4/2019 8:17:04 AM |
View |
PCD Project Manager
2/4/2019 8:16:15 AM |
GEC Comment Summary sheet V_2 | 2/4/2019 8:16:15 AM |
View |
PCD Project Manager
2/4/2019 8:15:41 AM |
Staff awaits trail easement resolution which shall be depicted on the1041 map (as appropriate). After resolution please upload the revised 1041 map. Please see redlines for the Grading & erosion control plan uploaded with this comment. Please see drainage comments to be addressed with the site development plan (SDP). | 2/4/2019 8:15:41 AM |
View |
PCD Engineering Division
1/31/2019 10:59:45 PM |
See comment letter and redlines. | 1/31/2019 10:59:45 PM |
View |
EPC Parks Department
1/17/2019 6:55:58 AM |
The attached comments are being provided administratively | 1/17/2019 6:55:58 AM |
View |
Colorado Department of Transportation - Pueblo Office
1/11/2019 3:25:11 PM |
1/11/2019 3:25:11 PM | |
View |
EPC Health Department
1/11/2019 12:06:06 PM |
1/11/2019 12:06:06 PM | |
View |
EPC Environmental Services
1/11/2019 9:28:00 AM |
1/11/2019 9:28:00 AM | |
View |
Colorado Springs Airport Advisory Commission
1/10/2019 9:31:55 AM |
The attached summary with comments will be presented to the Airport Advisory Commission at the meeting on January 23, 2019. | 1/10/2019 9:31:55 AM |
View |
PCD Project Manager
1/9/2019 11:26:42 AM |
Grading Redlines | 1/9/2019 11:26:42 AM |
View |
PCD Project Manager
1/9/2019 11:26:05 AM |
Fire Protection Redlines | 1/9/2019 11:26:05 AM |
View |
PCD Project Manager
1/9/2019 11:25:44 AM |
1041 Map redlines | 1/9/2019 11:25:44 AM |
View |
PCD Project Manager
1/9/2019 11:25:15 AM |
1041 Section 5 redlines | 1/9/2019 11:25:15 AM |
View |
PCD Project Manager
1/9/2019 11:24:54 AM |
1041 Section 2 Redlines | 1/9/2019 11:24:54 AM |
View |
PCD Engineering Division
1/9/2019 10:38:07 AM |
See comment letter and GEC Plan redlines. | 1/9/2019 10:38:07 AM |
View |
EPC Environmental Services
1/8/2019 10:30:42 AM |
1/8/2019 10:30:42 AM | |
Fountain
1/8/2019 9:36:45 AM |
No comments or concerns. | 1/8/2019 9:36:45 AM | |
View |
Mountain View Electric Association, Inc.
1/7/2019 1:46:45 PM |
1/7/2019 1:46:45 PM | |
Pikes Peak Regional Building Department
1/2/2019 2:44:19 PM |
Enumerations/Floodplain has the following comments: 1. An access road should be named from north of Birdsall Road and beyond. Access roads need to be named. Communication with El Paso County 9-1-1 Authority for names. 2. The number of addresses per area will depend on the amount of meters. Each meter will receive a separate address. Electric plan review has agreed to look at your ONELINE drawing prior to plan submittal for permit to Regional Building. Also included a site plan showing locations of meters on the access roads proposed to be named to determine the amount of meters for addressing. Email Amy Vanderbeek amy@pprbd.org for clarification. 3. Any standalone building will also receive a separate address. 4. What is the address to the existing Palmer Solar & Williams Creek solar project that are proposed to be decommissioned, as stated in Exhibit B; intent letter page 2-2. Proposed Development paragraphs 1 & 2?(Is this a typo)? |
1/2/2019 2:44:19 PM | |
View |
El Paso County Conservation Dist
12/27/2018 10:25:49 AM |
Please see the attached comments from the El Paso County Conservation District. Thank you, Pamela Davison EPCCD District Manager |
12/27/2018 10:25:49 AM |
El Paso County Conservation Dist
12/27/2018 10:25:04 AM |
Please see the attached comments from the El Paso County Conservation District. Thank you, Pamela Davison EPCCD District Manager |
12/27/2018 10:25:04 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/20/2018 2:26:18 PM |
Hey Kari, The only recommendation is to contact Warren Seese at (719)668-8390 regarding any emergency response plans. Other than that approval is recommended. Let me know if you need anything else from me. Thanks, Ryne |
12/20/2018 2:26:18 PM | |
PCD Project Manager
12/20/2018 12:25:15 PM |
Please provide the corresponding Appendix letter for each document in the comment when uploading. | 12/20/2018 12:25:15 PM | |
PCD Project Manager
12/20/2018 12:21:20 PM |
Planning Commission concerns that shall be addressed with the 1041 permit application: As indicated in the WSE-O application; the decommissioning plan is to become more detailed as the project progresses. Please provide the details within the plan as the PPA is final. Please provide a Emergency Response Plan that addresses the solar array operator's procedure and CSU's procedure including time lines for the entire overlay (substations, transmissions lines, and solar panels). Please provide documentation from the US FWS regarding the clearance; wetlands have been identified within the boundary. |
12/20/2018 12:21:20 PM | |
View |
911 Authority - El Paso/Teller County
12/18/2018 11:36:36 AM |
See Attached. Note: Contractor has provided no internal street names for this project. |
12/18/2018 11:36:36 AM |
View |
911 Authority - El Paso/Teller County
12/18/2018 11:35:16 AM |
See Attached. Note: contractor has provided no proposed street name for internal development for this project. |
12/18/2018 11:35:16 AM |
Woodmoor Water and Sanitation District
12/17/2018 11:22:17 AM |
No comments on the following as of 12-17-18: Elevation Plans (24" x 36") Fire Commitment Letter Legal Description (MS WORD Version required) Noise Study Noxious Weed Management Plan Visual Impact Analysis Operations Plan Determination of No Hazard from FAA Phase 1 ESA Wetland Deliniation Report & USACE Wildlife, Wetlands, Cultural Report Site Map (Existing Use) Electromagnetic Interference Report 1041 Documents Related to 2.303 (Items 1-23) 1041 Documents Related to 5.201 (Items 1 - 11) Safe Work Practices and Emergency Response Plan Per PCD request. Soils & Geology Report Please see Page 190-274 for added section on geo-hazards. Clearance Letter - Colorado Parks and Wildlife WSEO Overlay Map |
12/17/2018 11:22:17 AM |