View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
11/17/2021 2:42:06 PM |
Prepping item for approval. | 11/17/2021 2:42:06 PM | |
PCD Engineering Division
11/17/2021 11:46:55 AM |
The engineering documents have been approved/accepted by the ECM administrator on 11/16/21. The approved documents will be uploaded onto EDARP by the project manager. reviewed by: Daniel Torres danieltorres@elpasoco.com |
11/17/2021 11:46:55 AM | |
View |
PCD Engineering Division
10/7/2021 4:52:13 PM |
Please sign and submit the following engineering documents: -Drainage Letter -Financial Assurance -GEC Plan -ESQCP -SWMP Please also sign the attached PBMP Applicability Form that has been filled out. Daniel Torres danieltorres@elpasoco.com |
10/7/2021 4:52:13 PM |
PCD Project Manager
7/8/2021 2:44:34 PM |
Planning has no additional comments at this time. Approval is pending the special use application approval. |
7/8/2021 2:44:34 PM | |
EPC Stormwater Review
7/6/2021 5:14:08 PM |
All Stormwater comments have been addressed. | 7/6/2021 5:14:08 PM | |
PCD Engineering Division
6/29/2021 2:58:18 PM |
PCD Engineering comments have been resolved. Signed (by engineer & owner) engineering documents may be submitted for approval by the ECM administrator once all comments from the DPW stormwater engineer are addressed. reviewed by: Daniel Torres danieltorres@elpasoco.com |
6/29/2021 2:58:18 PM | |
PCD Project Manager
6/29/2021 2:27:31 PM |
Planner will provide comments once storm water has received requested documents. | 6/29/2021 2:27:31 PM | |
View |
PCD Project Manager
1/20/2021 2:59:00 PM |
Please see attached note to Letter of Intent. | 1/20/2021 2:59:00 PM |
View |
PCD Project Manager
1/20/2021 2:58:36 PM |
Please see attached comments to ESQCP. | 1/20/2021 2:58:36 PM |
View |
PCD Project Manager
1/20/2021 2:57:24 PM |
Please see attached comments to GEC Plan. | 1/20/2021 2:57:24 PM |
View |
PCD Project Manager
1/20/2021 2:56:39 PM |
Please see attached comments to Landscape Plan. | 1/20/2021 2:56:39 PM |
View |
PCD Project Manager
1/20/2021 2:55:58 PM |
Please see attached comments to Storm Water Management Plan. | 1/20/2021 2:55:58 PM |
View |
PCD Project Manager
1/20/2021 2:51:04 PM |
Please see attached comments to Site Development Plan. | 1/20/2021 2:51:04 PM |
PCD Engineering Division
1/19/2021 2:41:04 PM |
Review 2 comments on the following documents will be uploaded by the project manager: -Site Development Plan -Landscape Plan -GEC: See comments from stormwater engineer -ESQCP: See comments from stormwater engineer Engineering comments on the following documents have been resolved. -Drainage Letter -FAE reviewed by: Daniel Torres danieltorres@elpasoco.com |
1/19/2021 2:41:04 PM | |
View |
EPC Stormwater Review
1/20/2021 7:43:59 AM |
SWMP_v2 | 1/20/2021 7:43:59 AM |
EPC Stormwater Review
1/20/2021 7:43:22 AM |
Review 2: Stormwater comments have been provided on the following uploaded documents: - ESQCP (to be uploaded by Project Manager) - GEC (to be uploaded by Project Manager) - SWMP Please include the following uploaded documents on resubmittal: - GEC Checklist - SWMP Checklist Stormwater comments have been resolved on the following documents: - Application Form Reviewed by: Christina Furchak Stormwater Engineer III christinafurchak@elpasoco.com |
1/20/2021 7:43:22 AM | |
Ellicott Fire Protection District
12/16/2020 8:11:17 AM |
All of the Fire Department concerns have been addressed. There are no objections to this plan as submitted. THANK YOU | 12/16/2020 8:11:17 AM | |
View |
EPC Health Department
5/2/2020 3:43:06 PM |
5/2/2020 3:43:06 PM | |
View |
PCD Project Manager
4/24/2020 8:13:15 AM |
Redline vicinity map attached. | 4/24/2020 8:13:15 AM |
View |
PCD Project Manager
4/24/2020 8:12:58 AM |
Redline site development plan attached. | 4/24/2020 8:12:58 AM |
View |
PCD Project Manager
4/24/2020 8:12:40 AM |
Redline lighting plan attached. | 4/24/2020 8:12:40 AM |
View |
PCD Project Manager
4/24/2020 8:12:21 AM |
Redline letter of intent attached. | 4/24/2020 8:12:21 AM |
View |
PCD Project Manager
4/24/2020 8:12:04 AM |
Redline landscape plan attached. | 4/24/2020 8:12:04 AM |
View |
PCD Project Manager
4/24/2020 8:10:23 AM |
Redline GEC Plan attached. | 4/24/2020 8:10:23 AM |
View |
PCD Project Manager
4/24/2020 8:10:00 AM |
Redline financial assurance attached. | 4/24/2020 8:10:00 AM |
View |
PCD Project Manager
4/24/2020 8:09:42 AM |
Redline drainage letter attached. | 4/24/2020 8:09:42 AM |
View |
EPC Stormwater Review
4/23/2020 3:48:10 PM |
SWMP Checklist | 4/23/2020 3:48:10 PM |
View |
EPC Stormwater Review
4/23/2020 3:44:28 PM |
GEC Checklist | 4/23/2020 3:44:28 PM |
View |
EPC Stormwater Review
4/23/2020 3:43:07 PM |
SWMP_V1 | 4/23/2020 3:43:07 PM |
View |
EPC Stormwater Review
4/23/2020 3:42:24 PM |
GEC Plan_V1 | 4/23/2020 3:42:24 PM |
View |
EPC Stormwater Review
4/23/2020 3:41:38 PM |
ESQCP_V1 | 4/23/2020 3:41:38 PM |
View |
EPC Stormwater Review
4/23/2020 3:41:11 PM |
Application_V1 | 4/23/2020 3:41:11 PM |
PCD Engineering Division
4/23/2020 3:57:27 PM |
Review 1 comments on the following documents will be uploaded by the project manager: -Site Development Plan -GEC -Drainage Letter -Landscape Plan -FAE See the redline comments provided by the EPC Stormwater Review Engineer Note that there may be additional comments with the re-submittal as the rezone and final plat applications that include this lot are still in the review process. reviewed by: Daniel Torres danieltorres@elpasoco.com |
4/23/2020 3:57:27 PM | |
Pikes Peak Regional Building Department
4/23/2020 8:21:38 AM |
Regarding a request for approval of a site development plan for an office/manufacturing building, Enumerations has the following comments: 1. The current building on the site addressed as 22325 Hwy 94 will need to have a finalized demolition permit prior to Enumerations approving any building plans for the new structure. 2. This location is supposed to be platted as part of the Ellicott Town Center Filing No. 2 project. Since this lot will not have direct access to Hwy 94, an address will be assigned for this parcel from Cattlemen Run or Springs Rd., or both, one of which should be used as the address for this building. 3. The trash enclosure shown in this plan will require a separate address and building permit. This address will be assigned at the time of plan review. Brent Johnson Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2888 E: brent@pprbd.org W: pprbd.org |
4/23/2020 8:21:38 AM | |
PCD Project Manager
4/23/2020 7:56:38 AM |
After property is platted, the parcel number will change. You will need to update each document with the correct parcel number at that time. | 4/23/2020 7:56:38 AM | |
EPC Stormwater Review
4/23/2020 3:40:26 PM |
Review 1: Stormwater comments have been provided on the following uploaded documents: - Application Form - ESQCP - GEC - SWMP Please include the following uploaded documents on resubmittal: - GEC Checklist - SWMP Checklist Reviewed by: Christina Furchak Stormwater Engineer III christinafurchak@elpasoco.com |
4/23/2020 3:40:26 PM | |
County Attorney - Development Review
4/21/2020 9:09:08 AM |
No comments from County Attorney's Office at this time. | 4/21/2020 9:09:08 AM | |
Ellicott Fire Protection District
4/14/2020 6:11:24 PM |
2015 IFC Table B105.1(2) Type IIB 18,401 to 21,800 sq ft = 3000 GPM Table B105.2 allows a reduction of 25% = 2250 GPM 2 hour Duration Table C102.1 requires 3 hydrants Average spacing 450 ft Access all weather surfaces capable of sup675,00 lbs shall be in place prior to combustible materials being stored on site. Fire hydrants shall be operational prior to vertical construction with combustible materials. |
4/14/2020 6:11:24 PM | |
View |
Mountain View Electric Association, Inc.
4/14/2020 11:14:19 AM |
4/14/2020 11:14:19 AM | |
Upper Black Squirrel Creek GWMD
4/2/2020 1:11:04 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but reserves the right to comment in the future. | 4/2/2020 1:11:04 PM |