Project Review Comments

Back to List


Project Name
Crystal Park Site S-346(R) Site Plan
Description
Location
Parcels
7408000100 7408000100
Applicant
Palace Homes Inc
Gordon Stegner ( Gordon@palacehomesinc.com )
(719) 632-9635
Gordon Stegner ( Gordon@palacehomesinc.com )
(719) 632-9635
File Number
CP188
Project Manager
Gabe Sevigny
Status
Closed
Created
8/17/2018 9:13:38 AM

View: Project Documents



Review Comments (5)

Link Agency Comment
View EPC Health Department
1/25/2019 2:08:24 PM
1/25/2019 2:08:24 PM
PCD Project Manager
1/22/2019 11:32:21 AM
No additional comments 1/22/2019 11:32:21 AM
Colorado Geological Survey
1/8/2019 9:52:55 AM
The site is surrounded by relatively steep slopes, but is located outside of mapped landslide areas. RMG notes (pages 2-3, Geologic Hazard Report, 975 Oak Ridge Road, December 10, 2018) evidence of minor slope creep and surficial soil erosion. Provided RMG's and Entech's (Subsurface Soil Investigation, Site #346, Crystal Park Filing 2, June 6, 2018) recommendations are strictly adhered to, CGS has no objection to site plan approval. 1/8/2019 9:52:55 AM
View PCD Project Manager
1/4/2019 12:25:10 PM
Elevation Plan_V1, partial structure is above 30 feet, please provide average grade to determine height restrictions. See last project, CP-18-007, for example. 1/4/2019 12:25:10 PM
View El Paso County Conservation Dist
12/27/2018 10:23:21 AM
Please see the attached comments from the El Paso County Conservation District.
Thank you,
Pamela Davison
EPCCD District Manager