View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
10/24/2018 4:08:51 PM |
No additional planning comments | 10/24/2018 4:08:51 PM | |
PCD Engineering Division
10/23/2018 2:15:28 PM |
Engineering comments have been resolved on the following documents: -Site Plan -Letter of Intent Engineering has no additional comments. |
10/23/2018 2:15:28 PM | |
View |
EPC Health Department
10/10/2018 11:52:00 AM |
10/10/2018 11:52:00 AM | |
EPC Code Enforcement
10/8/2018 2:16:42 PM |
No comment | 10/8/2018 2:16:42 PM | |
View |
PCD Project Manager
10/4/2018 10:57:12 AM |
Multi-Discipline Team Comment Letter | 10/4/2018 10:57:12 AM |
View |
PCD Project Manager
10/4/2018 10:50:03 AM |
Letter of Intent redlined document | 10/4/2018 10:50:03 AM |
View |
PCD Project Manager
10/4/2018 10:43:53 AM |
Site Plan Drawing redlined document | 10/4/2018 10:43:53 AM |
PCD Engineering Division
10/2/2018 3:59:37 PM |
Review 1: Engineering comments have been provided on the following documents and will uploaded by the project manager - Letter of Intent - Site Plan |
10/2/2018 3:59:37 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/18/2018 4:25:21 PM |
Len, CSU has no action items for the subject application and is recommending approval. Let me know if you need anything else from me. Thanks -- Ryne |
9/18/2018 4:25:21 PM | |
Falcon Fire Protection District
9/17/2018 10:29:48 AM |
Falcon Fire has reviewed the McAnally Extended Family Dwelling Special Use request and has no objections to this request. | 9/17/2018 10:29:48 AM | |
View |
Mountain View Electric Association, Inc.
9/13/2018 4:44:49 PM |
9/13/2018 4:44:49 PM | |
El Paso County Conservation Dist
9/12/2018 8:26:20 AM |
The Board of directors of the El Paso County Conservation District have no comments at this time | 9/12/2018 8:26:20 AM |