Project Review Comments

Back to List


Project Name
Winding Walk Filing 2 Final Plat
Description
Final Plat for residential lots.
Location
Parcels
4200000413 4200000413 4200000415 4200000415
Applicant
N.E.S.
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073
EA Number
EA-17-147
File Number
SF1822
Project Manager
Nina Ruiz
Status
Closed
Created
6/25/2018 8:18:27 AM

View: Project Documents



Review Comments (27)

Link Agency Comment
Upper Black Squirrel Creek GWMD
11/20/2019 10:27:19 AM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but reserves the right to comment in the future. 11/20/2019 10:27:19 AM
Pikes Peak Regional Building Department
9/20/2018 2:37:27 PM
Enumerations has the following comments:
1. Plat should have all addressing applied for Enumerations review.
2. Standard Final Plat comments:

ENUMERATIONS/FLOODPLAIN WILL REVIEW THE MYLAR PRIOR TO PLAT FOR ADDRESS PLACEMENT, ROAD NAMING, TITLE BLOCK, & FLOODPLAIN STATEMENT.

$10.00 PER LOT & TRACT FEE WILL BE DUE AT THE TIME OF THE REVIEW OF THE MYLAR. IF AN ADDRESS IS NOT NEEDED ON A TRACT THEN NO FEE APPLIES. CHECK SHOULD BE MADE OUT TO PIKES PEAK REGIONAL BUILDING DEPARTMENT. PAID DIRECTLY TO ENUMERATIONS DEPARTMENT.

A COPY OF THE FINAL RECORDED PLAT IS REQUIRED PRIOR TO PLAN SUBMITTAL FOR RESIDENTAL. A COPY OF THE FINAL RECORDED PLAT IS REQUIRED PRIOR TO APPROVAL IN ENUMERATIONS DEPARTMENT ON ANY COMMERCIAL PLANS SUBMITTAL.

Floodplain has the following comments:
1. Remove the LOMR number and the effective date. This area does not apply the this LOMR.
9/20/2018 2:37:27 PM
View EPC Parks Department
9/19/2018 11:23:59 AM
El Paso County Community Services/Parks Final Comments (PAB Endorsed 09/12/2018) 9/19/2018 11:23:59 AM
View Parks Advisory Board
9/19/2018 11:19:35 AM
El Paso County Community Services/Parks Final Comments (PAB Endorsed 09/12/2018) 9/19/2018 11:19:35 AM
View EPC Health Department
9/17/2018 6:23:46 PM
9/17/2018 6:23:46 PM
PCD Engineering Division
9/17/2018 9:38:40 AM
Review 2: Comments resolved. 9/17/2018 9:38:40 AM
Colorado Geological Survey
8/30/2018 12:54:50 PM
June 18, 2018 letter from Tech contractors addresses CGS concerns. Assuming county will review and approve under drain design, no further review needed by CGS. 8/30/2018 12:54:50 PM
EPC County Attorney's Office
8/30/2018 12:50:14 PM
No further change to SIA needed. 8/30/2018 12:50:14 PM
View EPC Parks Department
8/28/2018 3:04:13 PM
El Paso County Community Services/Parks Preliminary Comments 8/28/2018 3:04:13 PM
View PCD Project Manager
8/21/2018 10:37:49 AM
MDT Letter 8/21/2018 10:37:49 AM
View PCD Project Manager
8/21/2018 10:34:08 AM
CD Redlines 8/21/2018 10:34:08 AM
View PCD Project Manager
8/21/2018 10:33:46 AM
EGF Redlines 8/21/2018 10:33:46 AM
View PCD Project Manager
8/21/2018 10:33:24 AM
Drainage Redlines 8/21/2018 10:33:24 AM
View PCD Project Manager
8/21/2018 10:33:07 AM
LOI Redlines 8/21/2018 10:33:07 AM
Pikes Peak Regional Building Department
8/21/2018 8:35:59 AM
Enumerations has the following comment:

Street name “Winding Glen” was approved but Winding Bend Lane was not.

Floodplain has the following comment:

LOMA case number 14-08-1121P applies to The Vistas Fil No 1 at Meridian Ranch, but not Winding Walk Fil No 1 or Fil No 2. Please remove LOMA information from plat.
8/21/2018 8:35:59 AM
View PCD Project Manager
8/20/2018 5:27:58 PM
Plat Redlines 8/20/2018 5:27:58 PM
PCD Project Manager
8/20/2018 5:24:32 PM
1. The final plat(s) must be approved and recorded prior to construction of any structure.
3. The detention pond maintenance agreement must be recorded and referenced on the final plat(s).
4. Prior to scheduling the item for hearing, all engineering documents must be signed by the County Engineer.
5. The HOA documents must be recorded prior to the final plat(s) and referenced on the face of the plat.
6. Prior to recording we will need the recording fee, tax valorem showing a zero balance, and title dated within 30 days. Additional documents to be recorded must also be submitted, such as the SIA. The Mylar will need to be signed by all parties other than El Paso County and have the PPRBD stamp placed on it. All recording fees are to be paid prior to recording.
8/20/2018 5:24:32 PM
View Mountain View Electric Association, Inc.
8/20/2018 1:32:47 PM
8/20/2018 1:32:47 PM
View Colorado Parks and Wildlife
8/20/2018 1:32:08 PM
8/20/2018 1:32:08 PM
El Paso County Conservation Dist
8/20/2018 12:42:45 PM
The Board of Supervisors of the El Paso County Conservation District have no comments at this time. 8/20/2018 12:42:45 PM
PCD Engineering Division
8/20/2018 3:43:42 PM
Review 1 comments on the following documents will be uploaded by the Project Manager:
- LOI
- Plat
- Drainage Report
- FAE
- Construction Drawings

* Per the Winding Walk Fil 1 TIS, escrow is to be calculated with each filing for signalization at the intersections of Stapleton/Eastonville and Stapleton/Lambert.
8/20/2018 3:43:42 PM
View EPC County Attorney's Office
8/14/2018 3:40:46 PM
Minor changes to SIA attached. Please provide Detention Maintenance Agreement if needed. 8/14/2018 3:40:46 PM
View Falcon Fire Protection District
8/14/2018 2:29:19 PM
8/14/2018 2:29:19 PM
View 911 Authority - El Paso/Teller County
8/6/2018 11:08:07 AM
See Attached 8/6/2018 11:08:07 AM
View EPC Environmental Services
7/31/2018 3:00:07 PM
7/31/2018 3:00:07 PM
Woodmen Road Metro
7/31/2018 11:02:09 AM
In response to the proposed project this parcel will be subject to the Woodmen Road Metropolitan District Fee’s and mill levies

Platting Fees due at time of final plat $385.00 per lot x 60 lots = $23,100

Building Permit Fees are due at time of Building Permit.
$550.00 per Lot
7/31/2018 11:02:09 AM
Colorado State Forest Service
7/30/2018 4:43:54 PM
The primary wildland fuel type for this proposal is grassland with scattered trees having a low wildfire hazard potential. No special fire mitigation plans or other actions are necessary for final approval by the Colorado State Forest Service. 7/30/2018 4:43:54 PM