Project Name
Paint Brush Hills 13E Pre-Site Dev. Grading
Description
Early Grading Stand Alone
Location
Parcel is located north Londonderry Drive west of Towner
Parcels
5226101007 5226101007
Applicant
Classic Consulting
Marc Whorton ( mwhorton@classicconsulting.net )
(719) 785-2802
Marc Whorton ( mwhorton@classicconsulting.net )
(719) 785-2802
EA Number
17-149
File Number
CDR185
Project Manager
Kari Parsons
Status
Closed
Created
2/1/2018 5:33:58 PM

View: Project Documents



Review Comments (12)

Link Agency Comment
PCD Project Manager
6/11/2018 12:24:49 PM
Approved Docs in additional uploaded documents. 6/11/2018 12:24:49 PM
View PCD Project Manager
6/11/2018 12:23:51 PM
ESQCP Approved 6/11/2018 12:23:51 PM
PCD Engineering Division
5/29/2018 4:47:05 PM
Underdrain must be either shown or a geotech report submitted which confirms the lack of the need to install. In the event that an underdrain is needed in the future it will be the responsibility of this developer to install as a retro fit situation.

Please resubmit the utility drawings with the underdrain shown or submit a geotech report.

EN, 5/29/2018
5/29/2018 4:47:05 PM
PCD Engineering Division
5/16/2018 5:26:23 PM
Review 2: The following comment is unresolved.

The construction drawings did not include an underdrain system. Provide a geotech report that states underdrains are not required.

Be advised that in the future if it is deemed that underdrains are required then the developer is responsible for retrofitting to installing the system.
5/16/2018 5:26:23 PM
View PCD Engineering Division
5/16/2018 5:32:29 PM
Review 2 comments on the Grading and Erosion Control Plan is attached.

Replace the submitted "Final Drainage Report for Paint Brush Hills Filing 13E" with the approved Preliminary Drainage Report for this site. The FDR for Filing 13E will be reviewed with the plat application.
Unresolved. Upload a copy of the PDR for Paint Brush Hills - Phase 2, approved by the county on Jan 27, 2005.


Review 1 comments to the utility construction drawings are unresolved. The uploaded document was the revised Grading and Erosion Control Plans.


Comments resolved on the following documents:
- ESQCP
- Financial Assurance Estimate
- SWMP (Make sure to include a copy of the SWMP Map with the final version)
5/16/2018 5:32:29 PM
View PCD Engineering Division
4/23/2018 5:47:49 PM
Review 1 comments to the SWMP is attached. 4/23/2018 5:47:49 PM
PCD Engineering Division
4/23/2018 5:03:52 PM
Review 1: The construction drawings did not include an underdrain system. Provide a geotech report that states underdrains are not required.

Be advised that in the future if it is deemed that underdrains are required then the developer is responsible for retrofitting to installing the system.
4/23/2018 5:03:52 PM
View PCD Engineering Division
4/23/2018 3:55:22 PM
Review 1 comments to the ESQCP is attached. 4/23/2018 3:55:22 PM
View PCD Engineering Division
4/23/2018 3:53:12 PM
Review 1 comments to the Financial Assurance Estimate is attached. 4/23/2018 3:53:12 PM
PCD Engineering Division
4/23/2018 3:48:22 PM
Review 1:
1. Replace the submitted "Final Drainage Report for Paint Brush Hills Filing 13E" with the approved Preliminary Drainage Report for this site. The FDR for Filing 13E will be reviewed with the plat application.

2. Remove the MS4 Post construction Form and SDI worksheet from this pre-development grading application. These documents will be reviewed with the final plat application.
4/23/2018 3:48:22 PM
View PCD Engineering Division
4/23/2018 5:13:55 PM
Review 1 comments to the Construction Drawings is attached. 4/23/2018 5:13:55 PM
View PCD Engineering Division
4/23/2018 4:07:03 PM
Review 1 comments to the Grading and Erosion Control Plan is attached. 4/23/2018 4:07:03 PM