Project Review Comments

Back to List


Project Name
Front Range-Midway Solar Energy Facility
Description
A request to develop a Solar energy Facility adjacent to two(2) existing sub-stations, utilizing existing transmission lines.
Location
North of Rancho Colorado Blvd, west of I-25, and east of Boca Raton Hieghts
Parcels
5717007004 5717007004 5717007005 5717007005 5717007006 5717007006 5717007019 5717007019 5717007047 5717007047 5717007052 5717007052 5717008023 5717008023 5717008024 5717008024 5720000003 5720000003 5720000007 5720000007 5720000010 5720000010 5720007001 5720007001 5720007002 5720007002 5720007003 5720007003 5720007004 5720007004 5721001002 5721001002 5721001003 5721001003 5721001004 5721001004 5721001005 5721001005 5721001006 5721001006 5721001007 5721001007 5721001008 5721001008 5721001009 5721001009 5721001010 5721001010 5721001011 5721001011 5721001012 5721001012 5721001013 5721001013 5721001014 5721001014 5721001015 5721001015 5721001017 5721001017 5722001001 5722001001 5722001002 5722001002 5722001003 5722001003
Applicant
Core Consultants Inc.
Chris Haas ( haas@corecivil.com )
(303) 703-4444 x121
Chris Haas ( haas@corecivil.com )
(303) 703-4444 x121
EA Number
17-46
File Number
WSEO17001
Project Manager
Kari Parsons
Status
Closed
Created
8/23/2017 10:48:47 AM

View: Project Documents



Review Comments (23)

Link Agency Comment
PCD Project Manager
4/11/2018 7:30:32 AM
Waiting for BoCC approval to have WSEO plan signed and recorded. 4/11/2018 7:30:32 AM
PCD Engineering Division
3/26/2018 10:48:01 AM
All remaining comments will be deferred to the 1041. Engineering has no further comments for this WSEO, please submit signed documents for approval. 3/26/2018 10:48:01 AM
PCD Project Manager
3/22/2018 2:49:30 PM
Planning has no further comment. 3/22/2018 2:49:30 PM
View PCD Project Manager
2/12/2018 5:10:08 PM
WSEO Map Redlines V-2 2/12/2018 5:10:08 PM
View PCD Project Manager
2/12/2018 5:05:59 PM
Haul Rote red line V-2 2/12/2018 5:05:59 PM
View PCD Project Manager
2/12/2018 5:04:21 PM
MDT Version 2 2/12/2018 5:04:21 PM
View PCD Project Manager
2/6/2018 12:12:58 PM
Planning Redlines WSEO Map 2/6/2018 12:12:58 PM
View Fountain
12/13/2017 8:35:32 AM
12/13/2017 8:35:32 AM
View PCD Project Manager
11/27/2017 3:07:10 PM
WSEO Map review 1 red lines 11/27/2017 3:07:10 PM
View PCD Project Manager
11/27/2017 3:06:27 PM
Site plan review 1 red-line 11/27/2017 3:06:27 PM
View PCD Project Manager
11/27/2017 3:07:50 PM
Haul Route red-line comments review 1 11/27/2017 3:07:50 PM
View PCD Project Manager
11/27/2017 4:04:55 PM
Multi-discipline comment letter 11/27/2017 4:04:55 PM
Fountain
11/16/2017 3:04:52 PM
The City of Fountain will be providing this this referral to our Planning Commission for comments at the December meeting. Comments will be provided after that. 11/16/2017 3:04:52 PM
View Colorado Parks and Wildlife
11/16/2017 12:24:06 PM
11/16/2017 12:24:06 PM
Pikes Peak Regional Building Department
11/16/2017 11:25:35 AM
Regarding a request for approval of a development plan for the Front Range-Midway Solar Energy Facility, Enumerations has the following comments:

1. Even though this project encompasses multiple parcels of land, it will be built in a single phase, so we would prefer to assign a single address to this project to use when submitting plans for review/permit. Due to the scale or this project, it is recommended that the developer request a pre-submittal consultation with the Pikes Peak Regional Building Department so that any issues regarding this plan can be addressed beforehand. Enumerations can assign an address at that time. Submit the pre-submittal consultation request form (available on our website www.pprbd.org) to Jay Eenhuis (jay@pprbd.org)





Floodplain has no comment or objection to this submittal

BRENT JOHNSON
Enumerations Plans Examiner

(719) 327-2888 www.pprbd.org
11/16/2017 11:25:35 AM
View EPC Health Department
11/15/2017 6:59:00 PM
11/15/2017 6:59:00 PM
View Colorado Department of Transportation - Pueblo Office
11/13/2017 8:29:50 AM
11/13/2017 8:29:50 AM
View EPC Environmental Services
11/9/2017 3:16:05 PM
11/9/2017 3:16:05 PM
View EPC Parks Department
11/9/2017 2:16:14 PM
El Paso County Community Services/Parks Final Comments 11/9/2017 2:16:14 PM
911 Authority - El Paso/Teller County
11/8/2017 11:46:36 AM
No action for 911
No new street names requested
Justin Annan
11/8/2017 11:46:36 AM
View Mountain View Electric Association, Inc.
11/6/2017 12:40:50 PM
11/6/2017 12:40:50 PM
Hanover Fire Protection District
11/3/2017 10:14:44 AM
We would like them to address the road impacts for not only the Residents but for the Emergency Responders so that we have access to this community regardless if they are County or Private Road?

We would like to see how they are going to address the limit access issues when the community main access becomes impassible and will no doubt interfere with this construction of this project.

There is no mention of Private Roads that may be temporary or permanently closed or what impact that it will have on the access for the Residents or emergency responders.

There is no mention to what Private Roads they are going to be using for their Haul Routes. Would like to make sure that the materials that they will be using to improve the Haul Routes will not hinder emergency responders (IE) law enforcement due to the type of vehicles they use.

What long term maintenance of the Haul / Private Roads are they going to do if any so they have access to conduct their routine maintenance program.

We would like to make sure that the Private Roads are left at least in the standard that they are in now or better.

We would like to have at least 2 fire hydrants in the area that we have access to year around.
11/3/2017 10:14:44 AM
El Paso County Conservation Dist
10/26/2017 10:40:38 AM
Comments from EPCCD board and DC

Good noxious weed plan.

Will detention pond outlets be monitored for stability?
10/26/2017 10:40:38 AM