View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
1/4/2018 9:34:05 AM |
No additional comments. | 1/4/2018 9:34:05 AM | |
PCD Project Manager
12/3/2017 11:39:05 AM |
All planning issues have been resolved. | 12/3/2017 11:39:05 AM | |
PCD Engineering Division
11/15/2017 10:51:46 AM |
Update the MDDP based on the guidance provided by the County Engineer during the Nov 14, 2017 meeting with the design engineer. 1. The release rates from the proposed pond must be equal to or less than the estimated pre-development runoff rates on the condition that the Board approves the request to remove condition no. 7 of PUD-00-010 requiring the release at approximately 80% of historic rates. 2. Include a section in the MDDP that provides justification for the removal of the board condition which includes the impact analysis and recommendations to the existing downstream infrastructure for the new release rate. |
11/15/2017 10:51:46 AM | |
PCD Project Manager
11/1/2017 7:28:35 AM |
Label sheets 2 and 3 of the sketch plan as existing and as amended. | 11/1/2017 7:28:35 AM | |
View |
PCD Engineering Division
10/23/2017 9:39:24 AM |
See the attached MDDP pdf for redline comments. One of the comment discusses the requirement for the 100-year release rate to be 90% of historic rate for the Full Spectrum Detention. The City's DCM Chapter 1 Section 5.0 states: "References may be modified and/or updated from time to time. It is the responsibility of the Applicant to apply the most current versions of referenced documents. The most current version of the UDFCD Manual are available from UDFCD's website (www.udfcd.org)." This section applies to the entire DCM including Section 3.2.1 of Chapter 12 (FSD) adopted by the County. UDFCD DCM Chapter 12 Section 4.1.2 states "the maximum allowable 100-year release rate for a full spectrum detention facility is equal to 90 percent of the predevelopment discharge for the upstream watershed." This change will only apply if the applicant's request for consideration of the BoCC's condition to release at 80% of historic is approved. |
10/23/2017 9:39:24 AM |
PCD Engineering Division
10/16/2017 10:15:48 AM |
Comments resolved on the Traffic Impact Study. | 10/16/2017 10:15:48 AM | |
View |
PCD Engineering Division
10/16/2017 9:33:46 AM |
Attached is the redline comment to the Letter of Intent. | 10/16/2017 9:33:46 AM |
Falcon 49
10/12/2017 2:24:21 PM |
School District 49 realizes that this is coming in after the due date for comment, however after reviewing information with County Transportation, the comment is necessary. In the Meridian Ranch Development, we are receiving many walk-in students to Meridian Ranch Elementary. We are seeing a lot of these students crossover Londonderry. Drivers are moving quite fast through this stretch. There is no signage alerting drivers that there is a school in the near vicinity, there is not a crosswalk and it is difficult to see kids crossing with the median, making this a large intersection. We would like to see the development provide safe walking opportunities for the students, to include signage along Londonderry, near Rainbow Bridge alerting drivers there is a school in the vicinity, add a cross walk and perhaps adjust the speed in that area. Additionally we need a crosswalk at the intersection of Londonderry and Eastonville for the Falcon High School students. |
10/12/2017 2:24:21 PM | |
Falcon Fire Protection District
8/16/2017 3:43:47 PM |
Falcon Fire has reviewed this Sketch Plan Amendment and has no objections to the Meridian Ranch Development request. Trent Harwig Fire Chief |
8/16/2017 3:43:47 PM | |
El Paso County Conservation Dist
8/15/2017 12:45:22 PM |
The EL Paso County Conservation District and District Conservationist have no comments at this time | 8/15/2017 12:45:22 PM | |
View |
Colorado Department of Transportation - Pueblo Office
8/14/2017 7:30:26 AM |
8/14/2017 7:30:26 AM | |
View |
PCD Project Manager
8/8/2017 3:35:14 PM |
Redlined TIS with hyperlinked comment summary at last page | 8/8/2017 3:35:14 PM |
View |
PCD Project Manager
8/8/2017 3:34:50 PM |
Redlined MDDP with hyperlinked comment summary at last page | 8/8/2017 3:34:50 PM |
View |
PCD Project Manager
8/8/2017 3:33:35 PM |
Redlined Sketch Plan | 8/8/2017 3:33:35 PM |
View |
PCD Project Manager
8/8/2017 3:33:09 PM |
Redlined letter of intent | 8/8/2017 3:33:09 PM |
View |
PCD Project Manager
8/8/2017 3:31:43 PM |
Please see attached comments from outside agencies contained in the comment review letter. Comments from PCD are in the form of redlines to the respective documents. | 8/8/2017 3:31:43 PM |
View |
EPC Parks Department
8/4/2017 3:54:07 PM |
El Paso County Community Services/Parks Final Comments | 8/4/2017 3:54:07 PM |
Pikes Peak Regional Building Department
8/1/2017 2:54:27 PM |
Enumerations/Floodplain have no comment at this stage of the planning. | 8/1/2017 2:54:27 PM | |
View |
EPC Health Department
7/29/2017 3:07:24 PM |
7/29/2017 3:07:24 PM | |
View |
EPC County Attorney's Office
7/27/2017 3:37:43 PM |
7/27/2017 3:37:43 PM | |
View |
PCD Engineering Division
7/27/2017 3:20:32 PM |
Attached are redline comments to the Letter of Intent. | 7/27/2017 3:20:32 PM |
View |
PCD Engineering Division
7/27/2017 3:12:05 PM |
Attached are redline comments to the Traffic Impact Study. | 7/27/2017 3:12:05 PM |
View |
PCD Engineering Division
7/27/2017 3:06:59 PM |
Attached are redline comments to the MDDP. | 7/27/2017 3:06:59 PM |
Woodmen Road Metro
7/21/2017 9:16:21 AM |
In response to the proposed project this parcel will be subject to the Woodmen Road Metropolitan District Fee’s and mill levies This proposed site would be subject at time of building permit, fee’s for Woodmen Road Metropolitan District and Falcon Community Builders for Classrooms |
7/21/2017 9:16:21 AM | |
View |
Mountain View Electric Association, Inc.
7/20/2017 10:27:38 AM |
7/20/2017 10:27:38 AM | |
EPC Environmental Services
7/13/2017 8:56:18 AM |
Environmental has no additional comments | 7/13/2017 8:56:18 AM |